| (2014) Report update | Program | State | Operator | Cause | Consequences | Damage |
|---|---|---|---|---|---|---|
| 2015-01-23 | GTG | KY | Southern Star Central Gas Pipeline, Inc | Corrosion Failure | $58,700 | |
| 2015-01-14 | GTG | KY | Southern Star Central Gas Pipeline, Inc | Equipment Failure | $0 | |
| 2014-12-19 | GTG | KY | Southern Star Central Gas Pipeline, Inc | Equipment Failure | $2,100 | |
| 2014-12-17 | GTG | OK | Transcontinental Gas Pipe Line Company | Corrosion Failure | $275,000 | |
| 2014-12-15 | GTG | OK | Williams Energy, Llc | Other Outside Force Damage | $2,733,406 | |
| 2014-11-24 | GTG | OK | Oneok Westex Transmission, Llc | Corrosion Failure | $121,863 | |
| 2014-11-06 | GTG | OK | Transcontinental Gas Pipe Line Company | Corrosion Failure | $350,000 | |
| 2014-10-13 | GTG | OK | Transcontinental Gas Pipe Line Company | Corrosion Failure | $475,000 | |
| 2014-09-30 | GTG | OK | Oneok Gas Transportation, Llc | Material Failure Of Pipe Or Weld | $60,800 | |
| 2014-07-31 | GTG | KY | Southern Star Central Gas Pipeline, Inc | Equipment Failure | $0 | |
| 2014-06-17 | GTG | KY | Southern Star Central Gas Pipeline, Inc | Corrosion Failure | $151,000 | |
| 2014-05-09 | GTG | OK | Oneok Westex Transmission, Llc | Material Failure Of Pipe Or Weld | $82,800 | |
| 2014-05-06 | GTG | OK | Black Marlin Pipeline Co | Equipment Failure | $160,000 | |
| 2014-04-14 | GTG | OK | Transcontinental Gas Pipe Line Company | Corrosion Failure | $175,000 | |
| 2014-04-11 | GTG | OK | Enlink Lig, Llc | Corrosion Failure | $0 | |
| 2014-03-31 | GTG | OK | Transcontinental Gas Pipe Line Company | Material Failure Of Pipe Or Weld | $200,000 | |
| 2014-02-05 | GTG | OK | Oneok Gas Transportation, Llc | Corrosion Failure | $180,000 | |
| 2014-01-21 | GTG | OK | Transcontinental Gas Pipe Line Company | Equipment Failure | $250,000 | |
| 2014-01-20 | GTG | KY | Southern Star Central Gas Pipeline, Inc | Equipment Failure | $15,772 | |
| 2014-01-17 | GTG | OK | Questar Pipeline Company | Equipment Failure | $100 |