Incident details
Operator, cause, commodity and consequences with raw source fields.
HL incident on 2025-09-07 — AZ
Operator
Navajo Nation Oil And Gas Company
Cause
Equipment Failure
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$5,425
Incident datetime
2025-09-07 21:59
Report number
Location
AZ
Narrative
At approximately 9:25pm on september 07, 2025. A third party notification contacted running horse pipeline (rhp) supervisor, edison tapaha. He reported a crude oil smell coming from our montezuma creek station. Rhp pipeline controller, broderick lee, notified rhp operator, pierce benally jr., to investigate the smell at the station. At approximately, 9:59pm on september 07, 2025, pierce benally jr. Confirmed crude oil spill by the sump pump and notified broderick lee to shut down the pipeline. Pipeline was shutdown approximately around 10:12pm. The pipeline station was shutdown due to oil spill sump overflow. Rhp used local contractors for swift response and start of cleanup started approximately 11:10pm, september 07,2025. Approximately 30 barrels spilled around the sump and a vacuum truck was used to pick up approximately 25 barrels. The accident was result of equipment failure, proving loop pressure relief valve failed to open.
Detailed record list
Report Received Date
2025-10-07 00:00:00
Iyear
2025
Report Number
20250237
Supplemental Number
41435
Report Type
Original Final
Operator Id
31663
Name
Navajo Nation Oil And Gas Company
Operator Street Address
50 Narbono Circle West
Operator City Name
St. Michaels
Operator State Abbreviation
AZ
Operator Postal Code
86511
Local Datetime
2025-09-07 21:25:00
Time Zone
Mountain
Daylight Savings Ind
Yes
Location Latitude
37.266492
Location Longitude
-109.307894
Commodity Released Type
Crude Oil
Unintentional Release Bbls
30
Recovered Bbls
25
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Notification From Public
Incident Identified Datetime
2025-09-07 21:59:00
System Part Involved
Onshore Pump/meter Station Equipment And Piping
On Off Shore
Onshore
Status When Identified
Normal Operation, Includes Pauses Between Batches And During Maintenance
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2025-09-07 22:12:00
Restart Datetime
2025-09-09 09:10:00
Communication State Fed Ind
No
On Site Datetime
2025-09-07 23:41:00
Confirmed Discovery Datetime
2025-09-07 21:59:00
Nrc Rpt Datetime
2025-09-08 08:06:00
Nrc Rpt Num
1442099
Ignite Ind
No
Notify Qualified Indiv Ind
No
Oil Spill Removal Org Ind
No
Num Pub Evacuated
0
Pipe Fac Name
Montezuma Creek Facility
Segment Name
Running Horse Pipeline
Onshore State Abbreviation
Ut
Onshore Postal Code
84534
Onshore City Name
Montezuma Creek
Onshore County Name
San Juan
Designated Location
Milepost
Designated Name
Facility
Federal
Yes
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Tank, Including Attached Appurtenances
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Sump
Installation Year
2010
Manufactured Year
2009
Material Involved
Material Other Than Carbon Steel
Material Details
Sump Tank - Fiberglass
Release Type
Overfill Or Overflow
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
Yes
Other Pop Ind
Yes
Other Pop Yes No
Yes
Usa Drinking Ind
Yes
Usa Drinking Yes No
Yes
Usa Ecological Ind
Yes
Usa Ecological Yes No
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
308
Est Cost Prop Damage
5425
Est Cost Emergency
2356
Est Cost Environmental
15987
Est Cost Other
5200
Est Cost Other Details
Running Horse Pipeline Overhead Cost.
Prpty
29276
Num Persons Hosp Not Ovnght
0
Num Injured Treated By Emt
0
Num Resident Building Affctd
0
Num Business Building Affctd
0
Accident Psig
370
Mop Psig
720
Mop Cfr Section
Component Design Pressure �195.406(A)(2)
Maop Established Date
2008-03-13 00:00:00
Maop Reversal Flow Ind
No
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
Yes
Scada Conf Ind
Yes
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
Yes
Cpm Detection Ind
Yes
Cpm Conf Ind
Yes
Investigation Status
Yes, specify investigation result(s): (select all that apply)
Invest Maint Ind
Yes
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Equipment Failure
Cause Details
Malfunction Of Control/relief Equipment
Eq Failure Type
Malfunction Of Control/relief Equipment
Relief Valve Ind
Yes
Additional Erosion Wear Ind
Yes
Eqf Control Releaf Ind
Yes
Io Not Installed Properly Ind
Yes
Preparer Name
T*** W*****
Preparer Title
Pipeline Engineer
Preparer Email
T******@n****.com
Preparer Telephone
505-409-0019
Prepared Date
2025-10-06 00:00:00
Authorizer Name
J***** R********
Authorizer Telephone
505-215-3522
Authorizer Title
Vice President Of Pipeline Operations
Authorizer Email
J*********@n****.com
Narrative
At approximately 9:25pm on september 07, 2025. A third party notification contacted running horse pipeline (rhp) supervisor, edison tapaha. He reported a crude oil smell coming from our montezuma creek station. Rhp pipeline controller, broderick lee, notified rhp operator, pierce benally jr., to investigate the smell at the station. At approximately, 9:59pm on september 07, 2025, pierce benally jr. Confirmed crude oil spill by the sump pump and notified broderick lee to shut down the pipeline. Pipeline was shutdown approximately around 10:12pm. The pipeline station was shutdown due to oil spill sump overflow. Rhp used local contractors for swift response and start of cleanup started approximately 11:10pm, september 07,2025. Approximately 30 barrels spilled around the sump and a vacuum truck was used to pick up approximately 25 barrels. The accident was result of equipment failure, proving loop pressure relief valve failed to open.
| Report Received Date | 2025-10-07 00:00:00 |
|---|---|
| Iyear | 2025 |
| Report Number | 20250237 |
| Supplemental Number | 41435 |
| Report Type | Original Final |
| Operator Id | 31663 PHMSA Enforcement |
| Name | Navajo Nation Oil And Gas Company |
| Operator Street Address | 50 Narbono Circle West |
| Operator City Name | St. Michaels |
| Operator State Abbreviation | AZ |
| Operator Postal Code | 86511 |
| Local Datetime | 2025-09-07 21:25:00 |
| Time Zone | Mountain |
| Daylight Savings Ind | Yes |
| Location Latitude | 37.266492 Google Maps OpenStreetMap |
| Location Longitude | -109.307894 Google Maps OpenStreetMap |
| Commodity Released Type | Crude Oil |
| Unintentional Release Bbls | 30 |
| Recovered Bbls | 25 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Notification From Public |
| Incident Identified Datetime | 2025-09-07 21:59:00 |
| System Part Involved | Onshore Pump/meter Station Equipment And Piping |
| On Off Shore | Onshore |
| Status When Identified | Normal Operation, Includes Pauses Between Batches And During Maintenance |
| Shutdown Due Accident Ind | Yes |
| Shutdown Datetime | 2025-09-07 22:12:00 |
| Restart Datetime | 2025-09-09 09:10:00 |
| Communication State Fed Ind | No |
| On Site Datetime | 2025-09-07 23:41:00 |
| Confirmed Discovery Datetime | 2025-09-07 21:59:00 |
| Nrc Rpt Datetime | 2025-09-08 08:06:00 |
| Nrc Rpt Num | 1442099 NRC Report How to search |
| Ignite Ind | No |
| Notify Qualified Indiv Ind | No |
| Oil Spill Removal Org Ind | No |
| Num Pub Evacuated | 0 |
| Pipe Fac Name | Montezuma Creek Facility |
| Segment Name | Running Horse Pipeline |
| Onshore State Abbreviation | Ut |
| Onshore Postal Code | 84534 |
| Onshore City Name | Montezuma Creek |
| Onshore County Name | San Juan |
| Designated Location | Milepost |
| Designated Name | Facility |
| Federal | Yes |
| Location Type | Totally Contained On Operator-Controlled Property |
| Incident Area Type | Tank, Including Attached Appurtenances |
| Crossing | No |
| Pipe Facility Type | Interstate |
| Item Involved | Sump |
| Installation Year | 2010 |
| Manufactured Year | 2009 |
| Material Involved | Material Other Than Carbon Steel |
| Material Details | Sump Tank - Fiberglass |
| Release Type | Overfill Or Overflow |
| Wildlife Impact Ind | No |
| Soil Contamination | Yes |
| Long Term Assessment | No |
| Remediation Ind | No |
| Water Contam Ind | No |
| Could Be Hca | Yes |
| Commodity Reached Hca | Yes |
| Other Pop Ind | Yes |
| Other Pop Yes No | Yes |
| Usa Drinking Ind | Yes |
| Usa Drinking Yes No | Yes |
| Usa Ecological Ind | Yes |
| Usa Ecological Yes No | Yes |
| Est Cost Oper Paid | 0 |
| Est Cost Gas Released | 308 |
| Est Cost Prop Damage | 5425 |
| Est Cost Emergency | 2356 |
| Est Cost Environmental | 15987 |
| Est Cost Other | 5200 |
| Est Cost Other Details | Running Horse Pipeline Overhead Cost. |
| Prpty | 29276 |
| Num Persons Hosp Not Ovnght | 0 |
| Num Injured Treated By Emt | 0 |
| Num Resident Building Affctd | 0 |
| Num Business Building Affctd | 0 |
| Accident Psig | 370 |
| Mop Psig | 720 |
| Mop Cfr Section | Component Design Pressure �195.406(A)(2) View CFR 49 §192 |
| Maop Established Date | 2008-03-13 00:00:00 |
| Maop Reversal Flow Ind | No |
| Accident Pressure | Pressure Did Not Exceed Mop |
| Pressure Restriction Ind | No |
| Pipeline Function | > 20% Smys Regulated Transmission |
| Scada In Place Ind | Yes |
| Scada Operating Ind | Yes |
| Scada Functional Ind | Yes |
| Scada Detection Ind | Yes |
| Scada Conf Ind | Yes |
| Cpm In Place Ind | Yes |
| Cpm Operating Ind | Yes |
| Cpm Functional Ind | Yes |
| Cpm Detection Ind | Yes |
| Cpm Conf Ind | Yes |
| Investigation Status | Yes, specify investigation result(s): (select all that apply) |
| Invest Maint Ind | Yes |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | No |
| Cause | Equipment Failure |
| Cause Details | Malfunction Of Control/relief Equipment |
| Eq Failure Type | Malfunction Of Control/relief Equipment |
| Relief Valve Ind | Yes |
| Additional Erosion Wear Ind | Yes |
| Eqf Control Releaf Ind | Yes |
| Io Not Installed Properly Ind | Yes |
| Preparer Name | T*** W***** |
| Preparer Title | Pipeline Engineer |
| Preparer Email | T******@n****.com |
| Preparer Telephone | 505-409-0019 |
| Prepared Date | 2025-10-06 00:00:00 |
| Authorizer Name | J***** R******** |
| Authorizer Telephone | 505-215-3522 |
| Authorizer Title | Vice President Of Pipeline Operations |
| Authorizer Email | J*********@n****.com |
| Narrative | At approximately 9:25pm on september 07, 2025. A third party notification contacted running horse pipeline (rhp) supervisor, edison tapaha. He reported a crude oil smell coming from our montezuma creek station. Rhp pipeline controller, broderick lee, notified rhp operator, pierce benally jr., to investigate the smell at the station. At approximately, 9:59pm on september 07, 2025, pierce benally jr. Confirmed crude oil spill by the sump pump and notified broderick lee to shut down the pipeline. Pipeline was shutdown approximately around 10:12pm. The pipeline station was shutdown due to oil spill sump overflow. Rhp used local contractors for swift response and start of cleanup started approximately 11:10pm, september 07,2025. Approximately 30 barrels spilled around the sump and a vacuum truck was used to pick up approximately 25 barrels. The accident was result of equipment failure, proving loop pressure relief valve failed to open. |