HL incident on 2025-07-24 — CO

Operator
Mplx Lp
Cause
Corrosion Failure
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$200,000
Incident datetime
2025-07-24 00:00 UTC
Report number
Location
CO
Narrative
On june 24, 2025, mplx operations personnel arrived at conan station and observed evidence of a crude oil leak originating from below ground. The leak was located in the vicinity of the enterprise 20� outgoing line and an adjacent 10� relief line. In response, the operator initiated an emergency shutdown (esd) of the station and immediately notified the control room and the operations manager. Both lines were isolated to determine the source of the leak. After confirming the leaking line, inlet flows to the station were returned to service. The enterprise 20� outgoing line was then disconnected and blinded. The station was subsequently brought back online. An estimated volume of approximately 10 barrels (bbls) of crude oil was released. All released product remained contained on mplx property with no off-site impact. Investigation findings: the investigation concluded that the failure was caused by internal corrosion due to microbiological activity, likely exacerbated by the line�s low flow rates. Path forward: � abandon the affected line. � retie the line to alternate headers to increase flow frequency. � replace the line, as necessary, to ensure continued safe operation.
Detailed record list
Report Received Date
2025-07-24 00:00:00
Iyear
2025
Report Number
20250174
Supplemental Number
41170
Report Type
Original Final
Operator Id
Name
Mplx Lp
Operator Street Address
1515 Arapahoe Street Suite 1600
Operator City Name
Denver
Operator State Abbreviation
CO
Operator Postal Code
80202
Time Zone
Central
Daylight Savings Ind
Yes
Location Latitude
Location Longitude
Commodity Released Type
Crude Oil
Unintentional Release Bbls
10
Recovered Bbls
10
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Operator Employee
System Part Involved
Onshore Pump/meter Station Equipment And Piping
On Off Shore
Onshore
Status When Identified
Normal Operation, Includes Pauses Between Batches And During Maintenance
Shutdown Due Accident Ind
Yes
Communication State Fed Ind
No
Nrc Rpt Num
Additional Nrc Report Numbers
1435190
Ignite Ind
No
Notify Qualified Indiv Ind
Yes
Oil Spill Removal Org Ind
Yes
Osro Arrived On Site Dt
6/24/2025 9:10
Num Pub Evacuated
0
Pipe Fac Name
Conan Station
Segment Name
Enterprise Suction Line
Onshore State Abbreviation
Tx
Onshore Postal Code
79754
Onshore City Name
Not Within A Municipality
Onshore County Name
Loving
Designated Location
Survey Station No.
Designated Name
0.85
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
36
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Pipe
Pipe Type
Pipe Body
Puddle Weld Ind
No
Pipe Diameter
20
Pipe Wall Thickness
0.375
Pipe Smys
52000
Pipe Specification
Api 5l Ss,erw
Pipe Seam Type
Erw - High Frequency
Pipe Manufacturer
Unknown
Pipe Coating Type
Fusion Bonded Epoxy(Fbe)
Coating Applied Ind
No
Installation Year
2018
Manufactured Year
Unknown
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Pinhole
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
0
Est Cost Gas Released
650
Est Cost Prop Damage
200000
Est Cost Emergency
0
Est Cost Environmental
175000
Est Cost Other
0
Prpty
375650
Num Persons Hosp Not Ovnght
0
Num Injured Treated By Emt
0
Num Resident Building Affctd
0
Num Business Building Affctd
0
Accident Psig
3
Mop Psig
285
Mop Cfr Section
Component Design Pressure �195.406(A)(2)
Maop Established Date
2018-04-14 00:00:00
Maop Reversal Flow Ind
No
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Pipeline Function
< 20% Smys Regulated Transmission
Scada In Place Ind
No
Cpm In Place Ind
No
Investigation Status
No, the facility was not monitored by a controller(s) at the time of the accident
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Corrosion Failure
Cause Details
Internal Corrosion
Internal External
Internal Corrosion
Int Visual Exam Results
General Corrosion
Int Microbiological Ind
Yes
Int Field Exam Basis Ind
Yes
Int Low Point Pipe Loc Ind
Yes
Corrosion Inhibitors
No
Corrosion Lining
No
Cleaning Dewatering
No
Corrosion Coupons
Not Applicable - Not Mainline Pipe
Collected Data Ind
No
Has Hydrtst Conduc Before Ind
No
Direct Asmnt Conducted
No
Non Destructive Exam Ind
No
Intrnl Cor Microbiologic Ind
Yes
Preparer Name
W****** K N*****
Preparer Title
Pipeline Compliance Specialist
Preparer Email
W*******@m***.com
Preparer Telephone
5053600834
Prepared Date
2025-07-24 00:00:00
Local Contact Name
K**** N*****
Local Contact Email
W*******@m***.com
Local Contact Telephone
5053600834
Authorizer Name
A***** R********
Authorizer Telephone
2102438906
Authorizer Title
Compliance Manager
Authorizer Email
A**********@m***.com
Narrative
On june 24, 2025, mplx operations personnel arrived at conan station and observed evidence of a crude oil leak originating from below ground. The leak was located in the vicinity of the enterprise 20� outgoing line and an adjacent 10� relief line. In response, the operator initiated an emergency shutdown (esd) of the station and immediately notified the control room and the operations manager. Both lines were isolated to determine the source of the leak. After confirming the leaking line, inlet flows to the station were returned to service. The enterprise 20� outgoing line was then disconnected and blinded. The station was subsequently brought back online. An estimated volume of approximately 10 barrels (bbls) of crude oil was released. All released product remained contained on mplx property with no off-site impact. Investigation findings: the investigation concluded that the failure was caused by internal corrosion due to microbiological activity, likely exacerbated by the line�s low flow rates. Path forward: � abandon the affected line. � retie the line to alternate headers to increase flow frequency. � replace the line, as necessary, to ensure continued safe operation.
Report Received Date 2025-07-24 00:00:00
Iyear 2025
Report Number 20250174
Supplemental Number 41170
Report Type Original Final
Operator Id 40149 PHMSA Enforcement
Name Mplx Lp
Operator Street Address 1515 Arapahoe Street Suite 1600
Operator City Name Denver
Operator State Abbreviation CO
Operator Postal Code 80202
Time Zone Central
Daylight Savings Ind Yes
Location Latitude 31.977837 Google Maps OpenStreetMap
Location Longitude -103.66352 Google Maps OpenStreetMap
Commodity Released Type Crude Oil
Unintentional Release Bbls 10
Recovered Bbls 10
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Local Operating Personnel, Including Contractors
Operator Type Operator Employee
System Part Involved Onshore Pump/meter Station Equipment And Piping
On Off Shore Onshore
Status When Identified Normal Operation, Includes Pauses Between Batches And During Maintenance
Shutdown Due Accident Ind Yes
Communication State Fed Ind No
Nrc Rpt Num 1434981 NRC Report How to search
Additional Nrc Report Numbers 1435190
Ignite Ind No
Notify Qualified Indiv Ind Yes
Oil Spill Removal Org Ind Yes
Osro Arrived On Site Dt 6/24/2025 9:10
Num Pub Evacuated 0
Pipe Fac Name Conan Station
Segment Name Enterprise Suction Line
Onshore State Abbreviation Tx
Onshore Postal Code 79754
Onshore City Name Not Within A Municipality
Onshore County Name Loving
Designated Location Survey Station No.
Designated Name 0.85
Federal No
Location Type Totally Contained On Operator-Controlled Property
Incident Area Type Underground
Incident Area Subtype Under Soil
Depth Of Cover 36
Crossing No
Pipe Facility Type Interstate
Item Involved Pipe
Pipe Type Pipe Body
Puddle Weld Ind No
Pipe Diameter 20
Pipe Wall Thickness 0.375
Pipe Smys 52000
Pipe Specification Api 5l Ss,erw
Pipe Seam Type Erw - High Frequency
Pipe Manufacturer Unknown
Pipe Coating Type Fusion Bonded Epoxy(Fbe)
Coating Applied Ind No
Installation Year 2018
Manufactured Year Unknown
Material Involved Carbon Steel
Release Type Leak
Leak Type Pinhole
Wildlife Impact Ind No
Soil Contamination Yes
Long Term Assessment No
Remediation Ind No
Water Contam Ind No
Could Be Hca No
Commodity Reached Hca No
Est Cost Oper Paid 0
Est Cost Gas Released 650
Est Cost Prop Damage 200000
Est Cost Emergency 0
Est Cost Environmental 175000
Est Cost Other 0
Prpty 375650
Num Persons Hosp Not Ovnght 0
Num Injured Treated By Emt 0
Num Resident Building Affctd 0
Num Business Building Affctd 0
Accident Psig 3
Mop Psig 285
Mop Cfr Section Component Design Pressure �195.406(A)(2) View CFR 49 §192
Maop Established Date 2018-04-14 00:00:00
Maop Reversal Flow Ind No
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Pipeline Function < 20% Smys Regulated Transmission
Scada In Place Ind No
Cpm In Place Ind No
Investigation Status No, the facility was not monitored by a controller(s) at the time of the accident
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Corrosion Failure
Cause Details Internal Corrosion
Internal External Internal Corrosion
Int Visual Exam Results General Corrosion
Int Microbiological Ind Yes
Int Field Exam Basis Ind Yes
Int Low Point Pipe Loc Ind Yes
Corrosion Inhibitors No
Corrosion Lining No
Cleaning Dewatering No
Corrosion Coupons Not Applicable - Not Mainline Pipe
Collected Data Ind No
Has Hydrtst Conduc Before Ind No
Direct Asmnt Conducted No
Non Destructive Exam Ind No
Intrnl Cor Microbiologic Ind Yes
Preparer Name W****** K N*****
Preparer Title Pipeline Compliance Specialist
Preparer Email W*******@m***.com
Preparer Telephone 5053600834
Prepared Date 2025-07-24 00:00:00
Local Contact Name K**** N*****
Local Contact Email W*******@m***.com
Local Contact Telephone 5053600834
Authorizer Name A***** R********
Authorizer Telephone 2102438906
Authorizer Title Compliance Manager
Authorizer Email A**********@m***.com
Narrative On june 24, 2025, mplx operations personnel arrived at conan station and observed evidence of a crude oil leak originating from below ground. The leak was located in the vicinity of the enterprise 20� outgoing line and an adjacent 10� relief line. In response, the operator initiated an emergency shutdown (esd) of the station and immediately notified the control room and the operations manager. Both lines were isolated to determine the source of the leak. After confirming the leaking line, inlet flows to the station were returned to service. The enterprise 20� outgoing line was then disconnected and blinded. The station was subsequently brought back online. An estimated volume of approximately 10 barrels (bbls) of crude oil was released. All released product remained contained on mplx property with no off-site impact. Investigation findings: the investigation concluded that the failure was caused by internal corrosion due to microbiological activity, likely exacerbated by the line�s low flow rates. Path forward: � abandon the affected line. � retie the line to alternate headers to increase flow frequency. � replace the line, as necessary, to ensure continued safe operation.