Incident details
Operator, cause, commodity and consequences with raw source fields.
GTG incident on 2025-10-08 — OK
Operator
Williams Mlp Operating, Llc
Cause
Corrosion Failure
Commodity
Natural Gas
Program
GTG
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$536,000
Incident datetime
2025-10-08 10:30
Report number
Location
OK
Narrative
� 09:26 tech I received call from gc concerning possible leak on putnam wc � 09:30 supervisor called tech ii was called to head to location to investigate. � 10:00 tech ii arrived at location to start investigation � 10:30 tech notified supervisor of leak found on pipeline. � 10:35 supervisor notified the customer of need for shut in of putnam and mitchell well pads. � environmental specialist was in the office and notified immediately. � 10:43 pipeline control notified of leak discovered and that we were shutting in the putnam and mitchel well connects. � 10:51 putnam and mitchell well pads confirmed offline. � 10:54 tech�s I and tech ii were notified to isolate pipeline. � 10:55 soc was notified � 11:15 called pipeline safety rep to notify of leak. � 11:40 techs had isolation complete and began blowing down the putnam well connect. . � 13:49 pipeline was completely blown down.
Detailed record list
Report Received Date
2025-10-31 00:00:00
Iyear
2025
Report Number
20250121
Supplemental Number
41537
Report Type
Original
Operator Id
31703
Name
Williams Mlp Operating, Llc
Operator Street Address
One Williams Center 43-4
Operator City Name
Tulsa
Operator State Abbreviation
OK
Operator Postal Code
74172
Local Datetime
2025-10-08 09:26:00
Time Zone
Eastern
Daylight Savings Ind
Yes
Location Latitude
40.53775
Location Longitude
-81.090068
Nrc Rpt Num
1445462
Nrc Rpt Datetime
2025-10-14 16:24:00
Additional Nrc Report Numbers
1445596
Commodity Released Type
Natural Gas
Unintentional Release
68
Intentional Release
0
Accompanying Liquid
0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Status When Identified
Normal Operation, Includes Pauses During Maintenance
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2025-10-08 11:40:00
Still Shutdown Ind
Yes
Communication State Fed Ind
Yes
Party Initiated Communication
Local/state/federal Emergency Responder
Initial Responder Com Datetime
2025-10-08 10:30:00
Ignite Ind
No
Upstream Action Taken
Valve Closure
Upstream Valve Close Datetime
2025-10-08 10:51:00
Downstream Action Taken
Valve Closure
Downstream Vlv Close Datetime
2025-10-08 10:51:00
Num Pub Evacuated
0
Incident Identified Datetime
2025-10-08 10:30:00
On Site Datetime
2025-10-08 10:00:00
Confirmed Discovery Datetime
2025-10-14 16:24:00
On Off Shore
Onshore
Onshore State Abbreviation
Oh
Onshore Postal Code
44615
Onshore City Name
Not Within A Municipality
Onshore County Name
Carroll
Designated Location
Not Applicable
Pipe Fac Name
Putnam Well Connect
Segment Name
590536
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
36
Other Underground Facilities
No
Crossing
No
Pipe Facility Type
Intrastate
System Part Involved
Onshore Pipeline, Including Valve Sites
Item Involved
Pipe
Pipe Type
Pipe Body
Pipe Diameter
8
Puddle Weld Ind
No
Pipe Wall Thickness
0.219
Pipe Smys
52000
Pipe Specification
20
Pipe Seam Type
Seamless
Pipe Manufacturer
Tmk
Pipe Coating Type
Epoxy
Coating Applied Ind
No
Installation Year
2013
Manufactured Year
2013
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Pinhole
Class Location Type
Class 1 Location
Could Be Hca
No
Pir Radius
158
Heat Damage Ind
No
Non Heat Damage Ind
No
Did Occur In Mca Ind
No
Est Cost Oper Paid
0
Est Cost Unintentional Release
204
Est Cost Intentional Release
0
Est Cost Prop Damage
536000
Est Cost Emergency
0
Est Cost Other
0
Est Cost Other Details
The Costs Have Been For Environmental Clean Up.
Gas Cost In Mcf
3
Prpty
536204
Num Persons Hosp Not Ovnght
0
Num Injured Treated By Emt
0
Num Resident Building Affctd
0
Num Business Building Affctd
0
Wildlife Impact Ind
No
Accident Psig
250
Gas Flow In Pipe In Mcf
6280
Mop Psig
720
Mop Cfr Section
192.619(A)(2)
Maop Established Date
2013-10-20 00:00:00
Maop Reversal Flow Ind
Bi-Directional
Accident Pressure
Pressure Did Not Exceed Maop
Pressure Restriction Ind
No
Gas Required Odorized Ind
No
Upstream Valve Type Ind
Manual
Downstream Valve Type Ind
Manual
Length Segment Isolated
12452
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
Type C Gathering
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
Yes
Scada Conf Ind
Yes
Accident Identifier
Notification From Public
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
No actions were possible from the controller that could have led to the issue or a contributing factor.
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Corrosion Failure
Cause Details
Internal Corrosion
Internal External
Internal Corrosion
Int Visual Exam Results
Not Cut Open
Int Microbiological Ind
Yes
Int Field Exam Basis Ind
Yes
Int Low Point Pipe Loc Ind
Yes
Corrosion Inhibitors
Yes
Corrosion Lining
No
Cleaning Dewatering
No
Corrosion Coupons
Yes
Collected Data Ind
No
Has Hydrtst Conduc Before Ind
No
Direct Asmnt Conducted
No
Non Destructive Exam Ind
Yes
Exm Radiography Rcnt Year
2013
Exm Radiography Rcnt Ind
Yes
Preparer Name
K**** A*******
Preparer Title
Regulatory Compliance Specialist Sr
Preparer Email
K*************@w*******.com
Preparer Telephone
7405846022
Local Contact Name
M*** C****
Local Contact Email
M*********@w*******.com
Local Contact Telephone
3304916392
Authorizer Name
L***** H***
Authorizer Title
Manager Pipeline Safety
Authorizer Telephone
9182404259
Authorizer Email
L**********@w*******.com
Narrative
� 09:26 tech I received call from gc concerning possible leak on putnam wc � 09:30 supervisor called tech ii was called to head to location to investigate. � 10:00 tech ii arrived at location to start investigation � 10:30 tech notified supervisor of leak found on pipeline. � 10:35 supervisor notified the customer of need for shut in of putnam and mitchell well pads. � environmental specialist was in the office and notified immediately. � 10:43 pipeline control notified of leak discovered and that we were shutting in the putnam and mitchel well connects. � 10:51 putnam and mitchell well pads confirmed offline. � 10:54 tech�s I and tech ii were notified to isolate pipeline. � 10:55 soc was notified � 11:15 called pipeline safety rep to notify of leak. � 11:40 techs had isolation complete and began blowing down the putnam well connect. . � 13:49 pipeline was completely blown down.
| Report Received Date | 2025-10-31 00:00:00 |
|---|---|
| Iyear | 2025 |
| Report Number | 20250121 |
| Supplemental Number | 41537 |
| Report Type | Original |
| Operator Id | 31703 PHMSA Enforcement |
| Name | Williams Mlp Operating, Llc |
| Operator Street Address | One Williams Center 43-4 |
| Operator City Name | Tulsa |
| Operator State Abbreviation | OK |
| Operator Postal Code | 74172 |
| Local Datetime | 2025-10-08 09:26:00 |
| Time Zone | Eastern |
| Daylight Savings Ind | Yes |
| Location Latitude | 40.53775 Google Maps OpenStreetMap |
| Location Longitude | -81.090068 Google Maps OpenStreetMap |
| Nrc Rpt Num | 1445462 NRC Report How to search |
| Nrc Rpt Datetime | 2025-10-14 16:24:00 |
| Additional Nrc Report Numbers | 1445596 |
| Commodity Released Type | Natural Gas |
| Unintentional Release | 68 |
| Intentional Release | 0 |
| Accompanying Liquid | 0 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Status When Identified | Normal Operation, Includes Pauses During Maintenance |
| Shutdown Due Accident Ind | Yes |
| Shutdown Datetime | 2025-10-08 11:40:00 |
| Still Shutdown Ind | Yes |
| Communication State Fed Ind | Yes |
| Party Initiated Communication | Local/state/federal Emergency Responder |
| Initial Responder Com Datetime | 2025-10-08 10:30:00 |
| Ignite Ind | No |
| Upstream Action Taken | Valve Closure |
| Upstream Valve Close Datetime | 2025-10-08 10:51:00 |
| Downstream Action Taken | Valve Closure |
| Downstream Vlv Close Datetime | 2025-10-08 10:51:00 |
| Num Pub Evacuated | 0 |
| Incident Identified Datetime | 2025-10-08 10:30:00 |
| On Site Datetime | 2025-10-08 10:00:00 |
| Confirmed Discovery Datetime | 2025-10-14 16:24:00 |
| On Off Shore | Onshore |
| Onshore State Abbreviation | Oh |
| Onshore Postal Code | 44615 |
| Onshore City Name | Not Within A Municipality |
| Onshore County Name | Carroll |
| Designated Location | Not Applicable |
| Pipe Fac Name | Putnam Well Connect |
| Segment Name | 590536 |
| Federal | No |
| Location Type | Pipeline Right-Of-Way |
| Incident Area Type | Underground |
| Incident Area Subtype | Under Soil |
| Depth Of Cover | 36 |
| Other Underground Facilities | No |
| Crossing | No |
| Pipe Facility Type | Intrastate |
| System Part Involved | Onshore Pipeline, Including Valve Sites |
| Item Involved | Pipe |
| Pipe Type | Pipe Body |
| Pipe Diameter | 8 |
| Puddle Weld Ind | No |
| Pipe Wall Thickness | 0.219 |
| Pipe Smys | 52000 |
| Pipe Specification | 20 |
| Pipe Seam Type | Seamless |
| Pipe Manufacturer | Tmk |
| Pipe Coating Type | Epoxy |
| Coating Applied Ind | No |
| Installation Year | 2013 |
| Manufactured Year | 2013 |
| Material Involved | Carbon Steel |
| Release Type | Leak |
| Leak Type | Pinhole |
| Class Location Type | Class 1 Location |
| Could Be Hca | No |
| Pir Radius | 158 |
| Heat Damage Ind | No |
| Non Heat Damage Ind | No |
| Did Occur In Mca Ind | No |
| Est Cost Oper Paid | 0 |
| Est Cost Unintentional Release | 204 |
| Est Cost Intentional Release | 0 |
| Est Cost Prop Damage | 536000 |
| Est Cost Emergency | 0 |
| Est Cost Other | 0 |
| Est Cost Other Details | The Costs Have Been For Environmental Clean Up. |
| Gas Cost In Mcf | 3 |
| Prpty | 536204 |
| Num Persons Hosp Not Ovnght | 0 |
| Num Injured Treated By Emt | 0 |
| Num Resident Building Affctd | 0 |
| Num Business Building Affctd | 0 |
| Wildlife Impact Ind | No |
| Accident Psig | 250 |
| Gas Flow In Pipe In Mcf | 6280 |
| Mop Psig | 720 |
| Mop Cfr Section | 192.619(A)(2) View CFR 49 §192 |
| Maop Established Date | 2013-10-20 00:00:00 |
| Maop Reversal Flow Ind | Bi-Directional |
| Accident Pressure | Pressure Did Not Exceed Maop |
| Pressure Restriction Ind | No |
| Gas Required Odorized Ind | No |
| Upstream Valve Type Ind | Manual |
| Downstream Valve Type Ind | Manual |
| Length Segment Isolated | 12452 |
| Internal Inspection Ind | Yes |
| Operation Complications Ind | No |
| Pipeline Function | Type C Gathering |
| Scada In Place Ind | Yes |
| Scada Operating Ind | Yes |
| Scada Functional Ind | Yes |
| Scada Detection Ind | Yes |
| Scada Conf Ind | Yes |
| Accident Identifier | Notification From Public |
| Investigation Status | No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate) |
| Investigation Status Details | No actions were possible from the controller that could have led to the issue or a contributing factor. |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | No |
| Cause | Corrosion Failure |
| Cause Details | Internal Corrosion |
| Internal External | Internal Corrosion |
| Int Visual Exam Results | Not Cut Open |
| Int Microbiological Ind | Yes |
| Int Field Exam Basis Ind | Yes |
| Int Low Point Pipe Loc Ind | Yes |
| Corrosion Inhibitors | Yes |
| Corrosion Lining | No |
| Cleaning Dewatering | No |
| Corrosion Coupons | Yes |
| Collected Data Ind | No |
| Has Hydrtst Conduc Before Ind | No |
| Direct Asmnt Conducted | No |
| Non Destructive Exam Ind | Yes |
| Exm Radiography Rcnt Year | 2013 |
| Exm Radiography Rcnt Ind | Yes |
| Preparer Name | K**** A******* |
| Preparer Title | Regulatory Compliance Specialist Sr |
| Preparer Email | K*************@w*******.com |
| Preparer Telephone | 7405846022 |
| Local Contact Name | M*** C**** |
| Local Contact Email | M*********@w*******.com |
| Local Contact Telephone | 3304916392 |
| Authorizer Name | L***** H*** |
| Authorizer Title | Manager Pipeline Safety |
| Authorizer Telephone | 9182404259 |
| Authorizer Email | L**********@w*******.com |
| Narrative | � 09:26 tech I received call from gc concerning possible leak on putnam wc � 09:30 supervisor called tech ii was called to head to location to investigate. � 10:00 tech ii arrived at location to start investigation � 10:30 tech notified supervisor of leak found on pipeline. � 10:35 supervisor notified the customer of need for shut in of putnam and mitchell well pads. � environmental specialist was in the office and notified immediately. � 10:43 pipeline control notified of leak discovered and that we were shutting in the putnam and mitchel well connects. � 10:51 putnam and mitchell well pads confirmed offline. � 10:54 tech�s I and tech ii were notified to isolate pipeline. � 10:55 soc was notified � 11:15 called pipeline safety rep to notify of leak. � 11:40 techs had isolation complete and began blowing down the putnam well connect. . � 13:49 pipeline was completely blown down. |