GTG incident on 2025-09-22 — TX

Operator
Energy Transfer Company
Cause
Equipment Failure
Commodity
Natural Gas
Program
GTG
Damage and Injuries
0 fatalities 1 injury
Property damage (nominal)
$1,000
Incident datetime
2025-09-22 07:50
Report number
Location
TX
Narrative
On september 22, 2025, at 7:55 a.M. A 3rd party contractor was blowing down a temporary bypass line connected to the 3902_05 waha comp to dual oasis 30-inch natural gas pipeline. A 3rd party contract employee located at the upstream line stop actuator was injured when 2-inch nipple and valve utilized as part of the blowdown procedure came off the line stop actuator striking the employee on his left arm and torso. At 8:09 a.M. Emergency services were called. The 3rd party contractor employee was transported to medical center hospital in odessa. At 4:41 p.M. The 3rd party contractor's safety representative notified energy transfer's DOT compliance department that an injured contractor was being admitted to medical center hospital. Nrc (report #1443444) and tx rrc (inci# 3411) were notified.
Detailed record list
Report Received Date
2025-10-21 00:00:00
Iyear
2025
Report Number
20250118
Supplemental Number
41493
Report Type
Original
Operator Id
Name
Energy Transfer Company
Operator Street Address
1300 Main Street
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2025-09-22 07:50:00
Time Zone
Central
Daylight Savings Ind
Yes
Location Latitude
Location Longitude
Nrc Rpt Num
Nrc Rpt Datetime
2025-09-22 16:41:00
Additional Nrc Report Numbers
1443621
Commodity Released Type
Natural Gas
Unintentional Release
0
Intentional Release
2.5
Accompanying Liquid
0
Fatality Ind
No
Fatal
0
Injury Ind
Yes
Num Emp Injuries
0
Num Contr Injuries
1
Num Er Injuries
0
Num Worker Injuries
0
Num Gp Injuries
0
Injure
1
Status When Identified
Post-Construction Commissioning
Communication State Fed Ind
Yes
Party Initiated Communication
Operator
Initial Responder Com Datetime
2025-09-22 08:09:00
Ignite Ind
No
Upstream Action Taken
Operational Control
Upstream Oprtnl Cntrl Detail
Additional Valves On 30� Bypass Were Opened To Expedite The Blowdown
Downstream Action Taken
Operational Control
Downstream Oprtnl Cntrl Detail
Additional Valves On 30� Bypass Were Opened To Expedite The Blowdown0
Num Pub Evacuated
0
Incident Identified Datetime
2025-09-22 07:50:00
On Site Datetime
2025-09-22 07:50:00
Confirmed Discovery Datetime
2025-09-22 16:07:00
On Off Shore
Onshore
Onshore State Abbreviation
Tx
Onshore Postal Code
79730
Onshore City Name
Not Within A Municipality
Onshore County Name
Pecos
Designated Location
Not Applicable
Pipe Fac Name
Waha Compressor Station
Segment Name
3902_05 Waha Comp To Dual Oasis
Federal
No
Location Type
Operator-Controlled Property
Incident Area Type
Aboveground
Incident Area Subtype
Typical Aboveground Facility Piping Or Appurtenance
Crossing
No
Pipe Facility Type
Intrastate
System Part Involved
Onshore Pipeline, Including Valve Sites
Item Involved
Tap Fitting(Stopple, Thread-O-Ring, Weld-O-Let, Etc.)
Installation Year
2025
Manufactured Year
Unknown
Material Involved
Carbon Steel
Release Type
Other
Release Type Details
Weld-Let Threads Failed
Class Location Type
Class 1 Location
Could Be Hca
No
Pir Radius
680
Heat Damage Ind
No
Non Heat Damage Ind
No
Hca Fatalities Ind
Yes
Fatal Injure Cause
Fractured Left Ulna And Multiple Left Flank Rib Fractures.
Did Occur In Mca Ind
No
Est Cost Oper Paid
0
Est Cost Unintentional Release
0
Est Cost Intentional Release
7
Est Cost Prop Damage
1000
Est Cost Emergency
5000
Est Cost Other
0
Gas Cost In Mcf
2.81
Prpty
6007
Num Persons Hosp Not Ovnght
0
Num Injured Treated By Emt
0
Num Resident Building Affctd
0
Num Business Building Affctd
0
Wildlife Impact Ind
No
Accident Psig
900
Gas Flow In Pipe In Mcf
0
Mop Psig
1050
Mop Cfr Section
192.619(A)(1)
Maop Established Date
2009-08-06 00:00:00
Maop Reversal Flow Ind
No
Accident Pressure
Pressure Did Not Exceed Maop
Pressure Restriction Ind
No
Gas Required Odorized Ind
No
Length Segment Isolated
450
Internal Inspection Ind
No
Other Inspection Ind
Yes
Internal Inspection Details
No Launchers Or Receivers.
Operation Complications Ind
No
Pipeline Function
Transmission System
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Contractor Working For The Operator
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
The valves being operated at the time of the incident were being operated manually.
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Equipment Failure
Cause Details
Threaded Connection/coupling Failure
Eq Failure Type
Threaded Connection/coupling Failure
Other Stripped Ind
Pipe Nipple
Eq Additional Other Ind
Yes
Eq Additional Other Details
Still Under Investigation
Preparer Name
T*** P******
Preparer Title
Sr. Specialist Dot Compliance
Preparer Email
T***********@e*************.com
Preparer Telephone
(432) 265-6810
Local Contact Name
T*** P******
Local Contact Email
T***********@e*************.com
Local Contact Telephone
(432) 265-6810
Authorizer Name
J***** D*******
Authorizer Title
Manager Dot Compliance
Authorizer Telephone
(713) 989-5231
Authorizer Email
J**************@e*************.com
Narrative
On september 22, 2025, at 7:55 a.M. A 3rd party contractor was blowing down a temporary bypass line connected to the 3902_05 waha comp to dual oasis 30-inch natural gas pipeline. A 3rd party contract employee located at the upstream line stop actuator was injured when 2-inch nipple and valve utilized as part of the blowdown procedure came off the line stop actuator striking the employee on his left arm and torso. At 8:09 a.M. Emergency services were called. The 3rd party contractor employee was transported to medical center hospital in odessa. At 4:41 p.M. The 3rd party contractor's safety representative notified energy transfer's DOT compliance department that an injured contractor was being admitted to medical center hospital. Nrc (report #1443444) and tx rrc (inci# 3411) were notified.
Report Received Date 2025-10-21 00:00:00
Iyear 2025
Report Number 20250118
Supplemental Number 41493
Report Type Original
Operator Id 32099 PHMSA Enforcement
Name Energy Transfer Company
Operator Street Address 1300 Main Street
Operator City Name Houston
Operator State Abbreviation TX
Operator Postal Code 77002
Local Datetime 2025-09-22 07:50:00
Time Zone Central
Daylight Savings Ind Yes
Location Latitude 31.274783 Google Maps OpenStreetMap
Location Longitude -103.071167 Google Maps OpenStreetMap
Nrc Rpt Num 1443444 NRC Report How to search
Nrc Rpt Datetime 2025-09-22 16:41:00
Additional Nrc Report Numbers 1443621
Commodity Released Type Natural Gas
Unintentional Release 0
Intentional Release 2.5
Accompanying Liquid 0
Fatality Ind No
Fatal 0
Injury Ind Yes
Num Emp Injuries 0
Num Contr Injuries 1
Num Er Injuries 0
Num Worker Injuries 0
Num Gp Injuries 0
Injure 1
Status When Identified Post-Construction Commissioning
Communication State Fed Ind Yes
Party Initiated Communication Operator
Initial Responder Com Datetime 2025-09-22 08:09:00
Ignite Ind No
Upstream Action Taken Operational Control
Upstream Oprtnl Cntrl Detail Additional Valves On 30� Bypass Were Opened To Expedite The Blowdown
Downstream Action Taken Operational Control
Downstream Oprtnl Cntrl Detail Additional Valves On 30� Bypass Were Opened To Expedite The Blowdown0
Num Pub Evacuated 0
Incident Identified Datetime 2025-09-22 07:50:00
On Site Datetime 2025-09-22 07:50:00
Confirmed Discovery Datetime 2025-09-22 16:07:00
On Off Shore Onshore
Onshore State Abbreviation Tx
Onshore Postal Code 79730
Onshore City Name Not Within A Municipality
Onshore County Name Pecos
Designated Location Not Applicable
Pipe Fac Name Waha Compressor Station
Segment Name 3902_05 Waha Comp To Dual Oasis
Federal No
Location Type Operator-Controlled Property
Incident Area Type Aboveground
Incident Area Subtype Typical Aboveground Facility Piping Or Appurtenance
Crossing No
Pipe Facility Type Intrastate
System Part Involved Onshore Pipeline, Including Valve Sites
Item Involved Tap Fitting(Stopple, Thread-O-Ring, Weld-O-Let, Etc.)
Installation Year 2025
Manufactured Year Unknown
Material Involved Carbon Steel
Release Type Other
Release Type Details Weld-Let Threads Failed
Class Location Type Class 1 Location
Could Be Hca No
Pir Radius 680
Heat Damage Ind No
Non Heat Damage Ind No
Hca Fatalities Ind Yes
Fatal Injure Cause Fractured Left Ulna And Multiple Left Flank Rib Fractures.
Did Occur In Mca Ind No
Est Cost Oper Paid 0
Est Cost Unintentional Release 0
Est Cost Intentional Release 7
Est Cost Prop Damage 1000
Est Cost Emergency 5000
Est Cost Other 0
Gas Cost In Mcf 2.81
Prpty 6007
Num Persons Hosp Not Ovnght 0
Num Injured Treated By Emt 0
Num Resident Building Affctd 0
Num Business Building Affctd 0
Wildlife Impact Ind No
Accident Psig 900
Gas Flow In Pipe In Mcf 0
Mop Psig 1050
Mop Cfr Section 192.619(A)(1) View CFR 49 §192
Maop Established Date 2009-08-06 00:00:00
Maop Reversal Flow Ind No
Accident Pressure Pressure Did Not Exceed Maop
Pressure Restriction Ind No
Gas Required Odorized Ind No
Length Segment Isolated 450
Internal Inspection Ind No
Other Inspection Ind Yes
Internal Inspection Details No Launchers Or Receivers.
Operation Complications Ind No
Pipeline Function Transmission System
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind No
Scada Conf Ind No
Accident Identifier Local Operating Personnel, Including Contractors
Operator Type Contractor Working For The Operator
Investigation Status No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details The valves being operated at the time of the incident were being operated manually.
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Equipment Failure
Cause Details Threaded Connection/coupling Failure
Eq Failure Type Threaded Connection/coupling Failure
Other Stripped Ind Pipe Nipple
Eq Additional Other Ind Yes
Eq Additional Other Details Still Under Investigation
Preparer Name T*** P******
Preparer Title Sr. Specialist Dot Compliance
Preparer Email T***********@e*************.com
Preparer Telephone (432) 265-6810
Local Contact Name T*** P******
Local Contact Email T***********@e*************.com
Local Contact Telephone (432) 265-6810
Authorizer Name J***** D*******
Authorizer Title Manager Dot Compliance
Authorizer Telephone (713) 989-5231
Authorizer Email J**************@e*************.com
Narrative On september 22, 2025, at 7:55 a.M. A 3rd party contractor was blowing down a temporary bypass line connected to the 3902_05 waha comp to dual oasis 30-inch natural gas pipeline. A 3rd party contract employee located at the upstream line stop actuator was injured when 2-inch nipple and valve utilized as part of the blowdown procedure came off the line stop actuator striking the employee on his left arm and torso. At 8:09 a.M. Emergency services were called. The 3rd party contractor employee was transported to medical center hospital in odessa. At 4:41 p.M. The 3rd party contractor's safety representative notified energy transfer's DOT compliance department that an injured contractor was being admitted to medical center hospital. Nrc (report #1443444) and tx rrc (inci# 3411) were notified.