GTG incident on 2025-05-23 — TX

Operator
Sea Robin Pipeline Co
Cause
Other Incident Cause
Commodity
Natural Gas
Program
GTG
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$2,457,394
Incident datetime
2025-05-23 00:00 UTC
Report number
Location
TX
Narrative
At approximately 1051 on 01/24/25, operations received a call from a 3rd party reporting bubbles in the area near the sea robin 319b-2400 in south timbalier 151 (st 151). Nrc was called reporting the bubbles in st151 (nrc#1421791, 48hr update#1421896). An overflight was conducted to verify the location of the bubbles. Pipeline was isolated on 01/24/25 at 1330. Overflights were conducted daily to monitor the area for any changes as weather permitted. Due to weather conditions, sea states and dsv availability, the repair contractor was not able to deploy until 4/24/25. Divers verified leak location on 04/25/25 at 0215 on the sea robin 319b-2400 pipeline. An attempt was made to repair the leak location. The repair was not completed due to the clamp not sealing. A specialized clamp is on order. The pipeline remains isolated until the clamp can be installed. The 48hr nrc notification was updated on 04/25/25 at 0859 to reflect the change from unknown owner to sea robin pipeline. (#1429408)
Detailed record list
Report Received Date
2025-05-23 00:00:00
Iyear
2025
Report Number
20250056
Supplemental Number
40937
Report Type
Original
Operator Id
Name
Sea Robin Pipeline Co
Operator Street Address
1300 Main Street
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Time Zone
Central
Daylight Savings Ind
Yes
Location Latitude
Location Longitude
Nrc Rpt Num
Additional Nrc Report Numbers
1421896, 1429408
Commodity Released Type
Natural Gas
Unintentional Release
5718
Intentional Release
2318
Accompanying Liquid
0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Status When Identified
Normal Operation, Includes Pauses During Maintenance
Shutdown Due Accident Ind
Yes
Still Shutdown Ind
Yes
Communication State Fed Ind
Yes
Party Initiated Communication
Operator
Ignite Ind
No
Upstream Action Taken
Valve Closure
Downstream Action Taken
Valve Closure
Num Pub Evacuated
0
On Off Shore
Offshore
Pipe Fac Name
Sea Robin
Segment Name
319b-2400
Off Water Depth
156
Off Accident Origin
On The Outer Continental Shelf (Ocs)
Ocs Type
Ocs-Gulf Of America
Off Ocs Area
South Timbalier
Off Ocs Block
151
Off Area Accident Type
Below Water, Pipe Buried Or Jetted Below Seabed
Pipe Facility Type
Interstate
System Part Involved
Offshore Pipeline, Including Riser And Riser Bend
Item Involved
Pipe
Pipe Type
Pipe Body
Pipe Diameter
20
Puddle Weld Ind
No
Pipe Wall Thickness
0.469
Pipe Smys
52000
Pipe Specification
Api 5l X52
Pipe Seam Type
Dsaw
Pipe Manufacturer
Kaiser Steel
Pipe Coating Type
Coal Tar
Coating Applied Ind
No
Installation Year
1976
Manufactured Year
1976
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Pinhole
Class Location Type
Class 1 Location
Could Be Hca
No
Pir Radius
482
Heat Damage Ind
No
Non Heat Damage Ind
No
Did Occur In Mca Ind
No
Est Cost Oper Paid
0
Est Cost Unintentional Release
20528
Est Cost Intentional Release
8322
Est Cost Prop Damage
2457394
Est Cost Emergency
107500
Est Cost Other
0
Gas Cost In Mcf
3.59
Prpty
2593744
Num Persons Hosp Not Ovnght
0
Num Injured Treated By Emt
0
Num Resident Building Affctd
0
Num Business Building Affctd
0
Wildlife Impact Ind
No
Accident Psig
850
Gas Flow In Pipe In Mcf
0
Mop Psig
1200
Mop Cfr Section
192.619(A)(2)
Maop Established Date
1977-01-01 00:00:00
Maop Reversal Flow Ind
No
Accident Pressure
Pressure Did Not Exceed Maop
Pressure Restriction Ind
No
Gas Required Odorized Ind
No
Upstream Valve Type Ind
Manual
Downstream Valve Type Ind
Manual
Length Segment Isolated
66105
Internal Inspection Ind
No
Tight Mitered Ind
Yes
Operation Complications Ind
No
Pipeline Function
Transmission System
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Accident Identifier
Other
Accident Details
Notified By Arena Platform
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
Leak was too small for scada to detect.
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Other Incident Cause
Cause Details
Unknown
Other Type
Unknown
Unknown Subtype
Still Under Investigation, Cause Of Incident To Be Determined* (*supplemental Report Required)
Preparer Name
P**** W***
Preparer Title
Manager Dot Compliance
Preparer Email
P*********@e*************.com
Preparer Telephone
4092023088
Authorizer Name
P**** W***
Authorizer Title
Manager Dot Compliance
Authorizer Telephone
4092023088
Authorizer Email
P*********@e*************.com
Narrative
At approximately 1051 on 01/24/25, operations received a call from a 3rd party reporting bubbles in the area near the sea robin 319b-2400 in south timbalier 151 (st 151). Nrc was called reporting the bubbles in st151 (nrc#1421791, 48hr update#1421896). An overflight was conducted to verify the location of the bubbles. Pipeline was isolated on 01/24/25 at 1330. Overflights were conducted daily to monitor the area for any changes as weather permitted. Due to weather conditions, sea states and dsv availability, the repair contractor was not able to deploy until 4/24/25. Divers verified leak location on 04/25/25 at 0215 on the sea robin 319b-2400 pipeline. An attempt was made to repair the leak location. The repair was not completed due to the clamp not sealing. A specialized clamp is on order. The pipeline remains isolated until the clamp can be installed. The 48hr nrc notification was updated on 04/25/25 at 0859 to reflect the change from unknown owner to sea robin pipeline. (#1429408)
Report Received Date 2025-05-23 00:00:00
Iyear 2025
Report Number 20250056
Supplemental Number 40937
Report Type Original
Operator Id 18152 PHMSA Enforcement
Name Sea Robin Pipeline Co
Operator Street Address 1300 Main Street
Operator City Name Houston
Operator State Abbreviation TX
Operator Postal Code 77002
Time Zone Central
Daylight Savings Ind Yes
Location Latitude 28.615134 Google Maps OpenStreetMap
Location Longitude -90.251182 Google Maps OpenStreetMap
Nrc Rpt Num 1421791 NRC Report How to search
Additional Nrc Report Numbers 1421896, 1429408
Commodity Released Type Natural Gas
Unintentional Release 5718
Intentional Release 2318
Accompanying Liquid 0
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Status When Identified Normal Operation, Includes Pauses During Maintenance
Shutdown Due Accident Ind Yes
Still Shutdown Ind Yes
Communication State Fed Ind Yes
Party Initiated Communication Operator
Ignite Ind No
Upstream Action Taken Valve Closure
Downstream Action Taken Valve Closure
Num Pub Evacuated 0
On Off Shore Offshore
Pipe Fac Name Sea Robin
Segment Name 319b-2400
Off Water Depth 156
Off Accident Origin On The Outer Continental Shelf (Ocs)
Ocs Type Ocs-Gulf Of America
Off Ocs Area South Timbalier
Off Ocs Block 151
Off Area Accident Type Below Water, Pipe Buried Or Jetted Below Seabed
Pipe Facility Type Interstate
System Part Involved Offshore Pipeline, Including Riser And Riser Bend
Item Involved Pipe
Pipe Type Pipe Body
Pipe Diameter 20
Puddle Weld Ind No
Pipe Wall Thickness 0.469
Pipe Smys 52000
Pipe Specification Api 5l X52
Pipe Seam Type Dsaw
Pipe Manufacturer Kaiser Steel
Pipe Coating Type Coal Tar
Coating Applied Ind No
Installation Year 1976
Manufactured Year 1976
Material Involved Carbon Steel
Release Type Leak
Leak Type Pinhole
Class Location Type Class 1 Location
Could Be Hca No
Pir Radius 482
Heat Damage Ind No
Non Heat Damage Ind No
Did Occur In Mca Ind No
Est Cost Oper Paid 0
Est Cost Unintentional Release 20528
Est Cost Intentional Release 8322
Est Cost Prop Damage 2457394
Est Cost Emergency 107500
Est Cost Other 0
Gas Cost In Mcf 3.59
Prpty 2593744
Num Persons Hosp Not Ovnght 0
Num Injured Treated By Emt 0
Num Resident Building Affctd 0
Num Business Building Affctd 0
Wildlife Impact Ind No
Accident Psig 850
Gas Flow In Pipe In Mcf 0
Mop Psig 1200
Mop Cfr Section 192.619(A)(2) View CFR 49 §192
Maop Established Date 1977-01-01 00:00:00
Maop Reversal Flow Ind No
Accident Pressure Pressure Did Not Exceed Maop
Pressure Restriction Ind No
Gas Required Odorized Ind No
Upstream Valve Type Ind Manual
Downstream Valve Type Ind Manual
Length Segment Isolated 66105
Internal Inspection Ind No
Tight Mitered Ind Yes
Operation Complications Ind No
Pipeline Function Transmission System
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind No
Scada Conf Ind No
Accident Identifier Other
Accident Details Notified By Arena Platform
Investigation Status No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details Leak was too small for scada to detect.
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Other Incident Cause
Cause Details Unknown
Other Type Unknown
Unknown Subtype Still Under Investigation, Cause Of Incident To Be Determined* (*supplemental Report Required)
Preparer Name P**** W***
Preparer Title Manager Dot Compliance
Preparer Email P*********@e*************.com
Preparer Telephone 4092023088
Authorizer Name P**** W***
Authorizer Title Manager Dot Compliance
Authorizer Telephone 4092023088
Authorizer Email P*********@e*************.com
Narrative At approximately 1051 on 01/24/25, operations received a call from a 3rd party reporting bubbles in the area near the sea robin 319b-2400 in south timbalier 151 (st 151). Nrc was called reporting the bubbles in st151 (nrc#1421791, 48hr update#1421896). An overflight was conducted to verify the location of the bubbles. Pipeline was isolated on 01/24/25 at 1330. Overflights were conducted daily to monitor the area for any changes as weather permitted. Due to weather conditions, sea states and dsv availability, the repair contractor was not able to deploy until 4/24/25. Divers verified leak location on 04/25/25 at 0215 on the sea robin 319b-2400 pipeline. An attempt was made to repair the leak location. The repair was not completed due to the clamp not sealing. A specialized clamp is on order. The pipeline remains isolated until the clamp can be installed. The 48hr nrc notification was updated on 04/25/25 at 0859 to reflect the change from unknown owner to sea robin pipeline. (#1429408)