GD incident on 2025-02-25 — OH

Operator
Enbridge Gas Ohio
Cause
Excavation Issue
Commodity
Natural Gas
Program
GD
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$28,000
Incident datetime
2025-02-25 00:00 UTC
Report number
Location
OH, TUSCARAWAS
Narrative
Shortly after 12:00 est on january 29, 2025, enbridge gas ohio (ego) began receiving "no gas" calls from customers on 1st dr sw in new philadelphia, ohio. By approximately 12:30 est, ego employees arrived on site to investigate and discovered a third-party contractor at 230 1st dr sw installing fiber optic conduit using horizontal directional drilling. The contractor's drill path had crossed 811 paint markings indicating the presence of utilities but had not daylighted them. Due to a loss of gas pressure downstream of their work, ego ordered the contractor to stop immediately, and they complied. Ego crews exposed the area where the drill path crossed accurately marked ego facilities and found that the 2" pilot bore had cross-bored the 4" mdpl low-pressure mainline. Additionally, the drilling equipment had damaged a nearby 2" water line, causing water to inundate the ego facility and flow into the gas system at a high rate. Given the natural gas system was operating at less than 1 psig, the water entering the pipeline created an effective seal, resulting in minimal natural gas loss. Ego promptly made repairs and began assessing the extent of water in the gas system. Ultimately, 165 customers were shut off due to no gas or low pressure across several intersecting streets. As the number of affected customers exceeded 100, ego communicated the outage and its impacts to the public utility commission of ohio. Ego crews, along with mobilized approved contractors, initiated a 24/7 operation to dewater mainlines and services in the affected area. Ego also offered hotel accommodations and warming centers to affected customers as overnight temperatures were below freezing. By approximately 16:00 est on january 31, 2025, enough water had been successfully removed from the system to restore adequate pressure for all affected customers. By 12:00 est on february 1, 2025, 150 customers had been restored to service. The remaining 15 customers could not be restored due to no access, but ego continued outreach until all were restored the following week. On february 6, 2025, a consolidated review of timesheets and invoices from the outage showed that the ego response, including damage repairs, dewatering, and restoration of service, would exceed the $149,400 outlined in �191.3. Accordingly, ego notified the nrc and the public utility commission of ohio.
Detailed record list
Report Received Date
2025-02-25 00:00:00
Iyear
2025.0
Report Number
20250003.0
Supplemental Number
40545.0
Report Type
Original Final
Operator Id
Name
Enbridge Gas Ohio
Operator Street Address
1201 East 55th Street
Operator City Name
Cleveland
Operator State Abbreviation
OH
Operator Postal Code
44103.0
Time Zone
Eastern
Daylight Savings Ind
No
Location Street Address
230 1st Dr Sw
Location City Name
New Philadelphia
Location County Name
Tuscarawas
Location State Abbreviation
OH
Location Postal Code
44663.0
Location Latitude
Location Longitude
-81.44751558
Flow Cont Squeeze Off Ind
Yes
Nrc Rpt Num
Additional Nrc Report Numbers
1422996.0
Commodity Released Type
Natural Gas
Unintentional Release
1.0
Intentional Release
1.0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Ignite Ind
No
Num Pub Evacuated
0.0
Communication State Fed Ind
Yes
Party Initiated Communication
Operator
Federal
No
Location Type
Public Property
Incident Area Type
Underground
Incident Area Subtype
Under Pavement
Depth Of Cover
36.0
Other Underground Facilities
No
Crossing
No
Pipe Facility Type
Investor Owned
System Part Involved
Main
Installation Year
2023.0
Manufactured Year
2022.0
Pipe Diameter
4.0
Pipe Specification
Astm D2513
Pipe Manufacturer
Polypipe
Material Involved
Plastic
Plastic Type
Polyethylene (Pe)
Plastic Sdr
13.5
Material Pe Pipe Code
2708
Release Type
Mechanical Puncture
Puncture Axial
2.0
Puncture Circum
2.0
Class Location Type
Class 3 Location
Est Cost Oper Paid
0.0
Est Cost Prop Damage
28000.0
Est Cost Emergency
200000.0
Est Cost Other
0.0
Gas Cost In Mcf
3.71
Est Cost Unintentional Release
4.0
Est Cost Intentional Release
4.0
Prpty
228008.0
Commercial Affected
10.0
Industrial Affected
0.0
Residences Affected
155.0
Num Persons Hosp Not Ovnght
0.0
Num Injured Treated By Emt
0.0
Num Resident Building Affctd
155.0
Num Business Building Affctd
10.0
Accident Psig
0.5
Normal Psig
0.5
Mop Psig
1.0
Mop Cfr Section
Maop Established Date
2023-10-11 00:00:00
Accident Pressure
Pressure Did Not Exceed Maop
Gas Odorized System Type
Combination Of Odorization Types
Gas Odorized Lvl Not Msrd Ind
Yes
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Accident Identifier
Notification From Public
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
Low pressure distribution system not monitored by gas control, and leak was too small to be expected to trigger a hi/lo scada alarm.
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Excavation Damage
Cause Details
Excavation Damage By Third Party
Ex Party Type
Excavation Damage By Third Party
Prior Notification Ind
Yes
One Call System Ind
Yes
State Law Exempt Ind
No
Notify Cga Dirt
Yes
Public Row Ind
Yes
Public Subtype
City Street
Joint Trench Ind
No
Cross Bore Ind
Yes
Depth Of Grade
Measured Depth From Grade
Depth Of Grade Detail
36
Excavator Type
Contractor
Excavator Equipment
Directional Drilling
Work Performed
Telecommunications
One Call Notified Ind
Yes
One Call Center Name
Ohio Utility Protection Service (Oups)
White Lined Ind
Unknown
Locator Type
Contract Locator
Visible Marks
Yes
Service Interruption
Yes
Service Interruption Hours
52.0
Root Cause Category
Excavation Issue
Root Cause Type
Excavator Dug Prior To Verifying Marks By Test-Hole (Pothole)
Excvtn Dmg Third Party Ind
Yes
Preparer Name
D***** E**** E****
Preparer Title
Manager Ohio Pipeline Safety
Preparer Email
D*************@d*************.com
Preparer Telephone
3305715796
Local Contact Name
B****** J******
Local Contact Email
B****************@d************.com
Local Contact Telephone
3308072154
Authorizer Name
D***** E****
Authorizer Title
Manager Ohio Pipeline Safety
Authorizer Telephone
3305715796
Authorizer Email
D*************@d*************.com
Narrative
Shortly after 12:00 est on january 29, 2025, enbridge gas ohio (ego) began receiving "no gas" calls from customers on 1st dr sw in new philadelphia, ohio. By approximately 12:30 est, ego employees arrived on site to investigate and discovered a third-party contractor at 230 1st dr sw installing fiber optic conduit using horizontal directional drilling. The contractor's drill path had crossed 811 paint markings indicating the presence of utilities but had not daylighted them. Due to a loss of gas pressure downstream of their work, ego ordered the contractor to stop immediately, and they complied. Ego crews exposed the area where the drill path crossed accurately marked ego facilities and found that the 2" pilot bore had cross-bored the 4" mdpl low-pressure mainline. Additionally, the drilling equipment had damaged a nearby 2" water line, causing water to inundate the ego facility and flow into the gas system at a high rate. Given the natural gas system was operating at less than 1 psig, the water entering the pipeline created an effective seal, resulting in minimal natural gas loss. Ego promptly made repairs and began assessing the extent of water in the gas system. Ultimately, 165 customers were shut off due to no gas or low pressure across several intersecting streets. As the number of affected customers exceeded 100, ego communicated the outage and its impacts to the public utility commission of ohio. Ego crews, along with mobilized approved contractors, initiated a 24/7 operation to dewater mainlines and services in the affected area. Ego also offered hotel accommodations and warming centers to affected customers as overnight temperatures were below freezing. By approximately 16:00 est on january 31, 2025, enough water had been successfully removed from the system to restore adequate pressure for all affected customers. By 12:00 est on february 1, 2025, 150 customers had been restored to service. The remaining 15 customers could not be restored due to no access, but ego continued outreach until all were restored the following week. On february 6, 2025, a consolidated review of timesheets and invoices from the outage showed that the ego response, including damage repairs, dewatering, and restoration of service, would exceed the $149,400 outlined in �191.3. Accordingly, ego notified the nrc and the public utility commission of ohio.
Report Received Date 2025-02-25 00:00:00
Iyear 2025.0
Report Number 20250003.0
Supplemental Number 40545.0
Report Type Original Final
Operator Id 4060 PHMSA Enforcement
Name Enbridge Gas Ohio
Operator Street Address 1201 East 55th Street
Operator City Name Cleveland
Operator State Abbreviation OH
Operator Postal Code 44103.0
Time Zone Eastern
Daylight Savings Ind No
Location Street Address 230 1st Dr Sw
Location City Name New Philadelphia
Location County Name Tuscarawas
Location State Abbreviation OH
Location Postal Code 44663.0
Location Latitude 40.48719881 Google Maps OpenStreetMap
Location Longitude -81.44751558 Google Maps OpenStreetMap
Flow Cont Squeeze Off Ind Yes
Nrc Rpt Num 1422860.0 NRC Report How to search
Additional Nrc Report Numbers 1422996.0
Commodity Released Type Natural Gas
Unintentional Release 1.0
Intentional Release 1.0
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Ignite Ind No
Num Pub Evacuated 0.0
Communication State Fed Ind Yes
Party Initiated Communication Operator
Federal No
Location Type Public Property
Incident Area Type Underground
Incident Area Subtype Under Pavement
Depth Of Cover 36.0
Other Underground Facilities No
Crossing No
Pipe Facility Type Investor Owned
System Part Involved Main
Installation Year 2023.0
Manufactured Year 2022.0
Pipe Diameter 4.0
Pipe Specification Astm D2513
Pipe Manufacturer Polypipe
Material Involved Plastic
Plastic Type Polyethylene (Pe)
Plastic Sdr 13.5
Material Pe Pipe Code 2708
Release Type Mechanical Puncture
Puncture Axial 2.0
Puncture Circum 2.0
Class Location Type Class 3 Location
Est Cost Oper Paid 0.0
Est Cost Prop Damage 28000.0
Est Cost Emergency 200000.0
Est Cost Other 0.0
Gas Cost In Mcf 3.71
Est Cost Unintentional Release 4.0
Est Cost Intentional Release 4.0
Prpty 228008.0
Commercial Affected 10.0
Industrial Affected 0.0
Residences Affected 155.0
Num Persons Hosp Not Ovnght 0.0
Num Injured Treated By Emt 0.0
Num Resident Building Affctd 155.0
Num Business Building Affctd 10.0
Accident Psig 0.5
Normal Psig 0.5
Mop Psig 1.0
Mop Cfr Section 192.623 View CFR 49 §192
Maop Established Date 2023-10-11 00:00:00
Accident Pressure Pressure Did Not Exceed Maop
Gas Odorized System Type Combination Of Odorization Types
Gas Odorized Lvl Not Msrd Ind Yes
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind No
Scada Conf Ind No
Accident Identifier Notification From Public
Investigation Status No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details Low pressure distribution system not monitored by gas control, and leak was too small to be expected to trigger a hi/lo scada alarm.
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Excavation Damage
Cause Details Excavation Damage By Third Party
Ex Party Type Excavation Damage By Third Party
Prior Notification Ind Yes
One Call System Ind Yes
State Law Exempt Ind No
Notify Cga Dirt Yes
Public Row Ind Yes
Public Subtype City Street
Joint Trench Ind No
Cross Bore Ind Yes
Depth Of Grade Measured Depth From Grade
Depth Of Grade Detail 36
Excavator Type Contractor
Excavator Equipment Directional Drilling
Work Performed Telecommunications
One Call Notified Ind Yes
One Call Center Name Ohio Utility Protection Service (Oups)
White Lined Ind Unknown
Locator Type Contract Locator
Visible Marks Yes
Service Interruption Yes
Service Interruption Hours 52.0
Root Cause Category Excavation Issue
Root Cause Type Excavator Dug Prior To Verifying Marks By Test-Hole (Pothole)
Excvtn Dmg Third Party Ind Yes
Preparer Name D***** E**** E****
Preparer Title Manager Ohio Pipeline Safety
Preparer Email D*************@d*************.com
Preparer Telephone 3305715796
Local Contact Name B****** J******
Local Contact Email B****************@d************.com
Local Contact Telephone 3308072154
Authorizer Name D***** E****
Authorizer Title Manager Ohio Pipeline Safety
Authorizer Telephone 3305715796
Authorizer Email D*************@d*************.com
Narrative Shortly after 12:00 est on january 29, 2025, enbridge gas ohio (ego) began receiving "no gas" calls from customers on 1st dr sw in new philadelphia, ohio. By approximately 12:30 est, ego employees arrived on site to investigate and discovered a third-party contractor at 230 1st dr sw installing fiber optic conduit using horizontal directional drilling. The contractor's drill path had crossed 811 paint markings indicating the presence of utilities but had not daylighted them. Due to a loss of gas pressure downstream of their work, ego ordered the contractor to stop immediately, and they complied. Ego crews exposed the area where the drill path crossed accurately marked ego facilities and found that the 2" pilot bore had cross-bored the 4" mdpl low-pressure mainline. Additionally, the drilling equipment had damaged a nearby 2" water line, causing water to inundate the ego facility and flow into the gas system at a high rate. Given the natural gas system was operating at less than 1 psig, the water entering the pipeline created an effective seal, resulting in minimal natural gas loss. Ego promptly made repairs and began assessing the extent of water in the gas system. Ultimately, 165 customers were shut off due to no gas or low pressure across several intersecting streets. As the number of affected customers exceeded 100, ego communicated the outage and its impacts to the public utility commission of ohio. Ego crews, along with mobilized approved contractors, initiated a 24/7 operation to dewater mainlines and services in the affected area. Ego also offered hotel accommodations and warming centers to affected customers as overnight temperatures were below freezing. By approximately 16:00 est on january 31, 2025, enough water had been successfully removed from the system to restore adequate pressure for all affected customers. By 12:00 est on february 1, 2025, 150 customers had been restored to service. The remaining 15 customers could not be restored due to no access, but ego continued outreach until all were restored the following week. On february 6, 2025, a consolidated review of timesheets and invoices from the outage showed that the ego response, including damage repairs, dewatering, and restoration of service, would exceed the $149,400 outlined in �191.3. Accordingly, ego notified the nrc and the public utility commission of ohio.

All rights reserved. Copyright © by ClearPHMSA