Incident details
Operator, cause, commodity and consequences with raw source fields.
GD incident on 2025-02-25 — OH
Operator
Enbridge Gas Ohio
Cause
Excavation Issue
Commodity
Natural Gas
Program
GD
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$28,000
Incident datetime
2025-02-25 00:00 UTC
Report number
Location
OH, TUSCARAWAS
Narrative
Shortly after 12:00 est on january 29, 2025, enbridge gas ohio (ego) began receiving "no gas" calls from customers on 1st dr sw in new philadelphia, ohio. By approximately 12:30 est, ego employees arrived on site to investigate and discovered a third-party contractor at 230 1st dr sw installing fiber optic conduit using horizontal directional drilling. The contractor's drill path had crossed 811 paint markings indicating the presence of utilities but had not daylighted them. Due to a loss of gas pressure downstream of their work, ego ordered the contractor to stop immediately, and they complied. Ego crews exposed the area where the drill path crossed accurately marked ego facilities and found that the 2" pilot bore had cross-bored the 4" mdpl low-pressure mainline. Additionally, the drilling equipment had damaged a nearby 2" water line, causing water to inundate the ego facility and flow into the gas system at a high rate. Given the natural gas system was operating at less than 1 psig, the water entering the pipeline created an effective seal, resulting in minimal natural gas loss. Ego promptly made repairs and began assessing the extent of water in the gas system. Ultimately, 165 customers were shut off due to no gas or low pressure across several intersecting streets. As the number of affected customers exceeded 100, ego communicated the outage and its impacts to the public utility commission of ohio. Ego crews, along with mobilized approved contractors, initiated a 24/7 operation to dewater mainlines and services in the affected area. Ego also offered hotel accommodations and warming centers to affected customers as overnight temperatures were below freezing. By approximately 16:00 est on january 31, 2025, enough water had been successfully removed from the system to restore adequate pressure for all affected customers. By 12:00 est on february 1, 2025, 150 customers had been restored to service. The remaining 15 customers could not be restored due to no access, but ego continued outreach until all were restored the following week. On february 6, 2025, a consolidated review of timesheets and invoices from the outage showed that the ego response, including damage repairs, dewatering, and restoration of service, would exceed the $149,400 outlined in �191.3. Accordingly, ego notified the nrc and the public utility commission of ohio.
Detailed record list
Report Received Date
2025-02-25 00:00:00
Iyear
2025.0
Report Number
20250003.0
Supplemental Number
40545.0
Report Type
Original Final
Operator Id
4060
Name
Enbridge Gas Ohio
Operator Street Address
1201 East 55th Street
Operator City Name
Cleveland
Operator State Abbreviation
OH
Operator Postal Code
44103.0
Time Zone
Eastern
Daylight Savings Ind
No
Location Street Address
230 1st Dr Sw
Location City Name
New Philadelphia
Location County Name
Tuscarawas
Location State Abbreviation
OH
Location Postal Code
44663.0
Location Latitude
40.48719881
Location Longitude
-81.44751558
Flow Cont Squeeze Off Ind
Yes
Nrc Rpt Num
1422860.0
Additional Nrc Report Numbers
1422996.0
Commodity Released Type
Natural Gas
Unintentional Release
1.0
Intentional Release
1.0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Ignite Ind
No
Num Pub Evacuated
0.0
Communication State Fed Ind
Yes
Party Initiated Communication
Operator
Federal
No
Location Type
Public Property
Incident Area Type
Underground
Incident Area Subtype
Under Pavement
Depth Of Cover
36.0
Other Underground Facilities
No
Crossing
No
Pipe Facility Type
Investor Owned
System Part Involved
Main
Installation Year
2023.0
Manufactured Year
2022.0
Pipe Diameter
4.0
Pipe Specification
Astm D2513
Pipe Manufacturer
Polypipe
Material Involved
Plastic
Plastic Type
Polyethylene (Pe)
Plastic Sdr
13.5
Material Pe Pipe Code
2708
Release Type
Mechanical Puncture
Puncture Axial
2.0
Puncture Circum
2.0
Class Location Type
Class 3 Location
Est Cost Oper Paid
0.0
Est Cost Prop Damage
28000.0
Est Cost Emergency
200000.0
Est Cost Other
0.0
Gas Cost In Mcf
3.71
Est Cost Unintentional Release
4.0
Est Cost Intentional Release
4.0
Prpty
228008.0
Commercial Affected
10.0
Industrial Affected
0.0
Residences Affected
155.0
Num Persons Hosp Not Ovnght
0.0
Num Injured Treated By Emt
0.0
Num Resident Building Affctd
155.0
Num Business Building Affctd
10.0
Accident Psig
0.5
Normal Psig
0.5
Mop Psig
1.0
Mop Cfr Section
192.623
Maop Established Date
2023-10-11 00:00:00
Accident Pressure
Pressure Did Not Exceed Maop
Gas Odorized System Type
Combination Of Odorization Types
Gas Odorized Lvl Not Msrd Ind
Yes
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Accident Identifier
Notification From Public
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
Low pressure distribution system not monitored by gas control, and leak was too small to be expected to trigger a hi/lo scada alarm.
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Excavation Damage
Cause Details
Excavation Damage By Third Party
Ex Party Type
Excavation Damage By Third Party
Prior Notification Ind
Yes
One Call System Ind
Yes
State Law Exempt Ind
No
Notify Cga Dirt
Yes
Public Row Ind
Yes
Public Subtype
City Street
Joint Trench Ind
No
Cross Bore Ind
Yes
Depth Of Grade
Measured Depth From Grade
Depth Of Grade Detail
36
Excavator Type
Contractor
Excavator Equipment
Directional Drilling
Work Performed
Telecommunications
One Call Notified Ind
Yes
One Call Center Name
Ohio Utility Protection Service (Oups)
White Lined Ind
Unknown
Locator Type
Contract Locator
Visible Marks
Yes
Service Interruption
Yes
Service Interruption Hours
52.0
Root Cause Category
Excavation Issue
Root Cause Type
Excavator Dug Prior To Verifying Marks By Test-Hole (Pothole)
Excvtn Dmg Third Party Ind
Yes
Preparer Name
D***** E**** E****
Preparer Title
Manager Ohio Pipeline Safety
Preparer Email
D*************@d*************.com
Preparer Telephone
3305715796
Local Contact Name
B****** J******
Local Contact Email
B****************@d************.com
Local Contact Telephone
3308072154
Authorizer Name
D***** E****
Authorizer Title
Manager Ohio Pipeline Safety
Authorizer Telephone
3305715796
Authorizer Email
D*************@d*************.com
Narrative
Shortly after 12:00 est on january 29, 2025, enbridge gas ohio (ego) began receiving "no gas" calls from customers on 1st dr sw in new philadelphia, ohio. By approximately 12:30 est, ego employees arrived on site to investigate and discovered a third-party contractor at 230 1st dr sw installing fiber optic conduit using horizontal directional drilling. The contractor's drill path had crossed 811 paint markings indicating the presence of utilities but had not daylighted them. Due to a loss of gas pressure downstream of their work, ego ordered the contractor to stop immediately, and they complied. Ego crews exposed the area where the drill path crossed accurately marked ego facilities and found that the 2" pilot bore had cross-bored the 4" mdpl low-pressure mainline. Additionally, the drilling equipment had damaged a nearby 2" water line, causing water to inundate the ego facility and flow into the gas system at a high rate. Given the natural gas system was operating at less than 1 psig, the water entering the pipeline created an effective seal, resulting in minimal natural gas loss. Ego promptly made repairs and began assessing the extent of water in the gas system. Ultimately, 165 customers were shut off due to no gas or low pressure across several intersecting streets. As the number of affected customers exceeded 100, ego communicated the outage and its impacts to the public utility commission of ohio. Ego crews, along with mobilized approved contractors, initiated a 24/7 operation to dewater mainlines and services in the affected area. Ego also offered hotel accommodations and warming centers to affected customers as overnight temperatures were below freezing. By approximately 16:00 est on january 31, 2025, enough water had been successfully removed from the system to restore adequate pressure for all affected customers. By 12:00 est on february 1, 2025, 150 customers had been restored to service. The remaining 15 customers could not be restored due to no access, but ego continued outreach until all were restored the following week. On february 6, 2025, a consolidated review of timesheets and invoices from the outage showed that the ego response, including damage repairs, dewatering, and restoration of service, would exceed the $149,400 outlined in �191.3. Accordingly, ego notified the nrc and the public utility commission of ohio.
Report Received Date | 2025-02-25 00:00:00 |
---|---|
Iyear | 2025.0 |
Report Number | 20250003.0 |
Supplemental Number | 40545.0 |
Report Type | Original Final |
Operator Id | 4060 PHMSA Enforcement |
Name | Enbridge Gas Ohio |
Operator Street Address | 1201 East 55th Street |
Operator City Name | Cleveland |
Operator State Abbreviation | OH |
Operator Postal Code | 44103.0 |
Time Zone | Eastern |
Daylight Savings Ind | No |
Location Street Address | 230 1st Dr Sw |
Location City Name | New Philadelphia |
Location County Name | Tuscarawas |
Location State Abbreviation | OH |
Location Postal Code | 44663.0 |
Location Latitude | 40.48719881 Google Maps OpenStreetMap |
Location Longitude | -81.44751558 Google Maps OpenStreetMap |
Flow Cont Squeeze Off Ind | Yes |
Nrc Rpt Num | 1422860.0 NRC Report How to search |
Additional Nrc Report Numbers | 1422996.0 |
Commodity Released Type | Natural Gas |
Unintentional Release | 1.0 |
Intentional Release | 1.0 |
Fatality Ind | No |
Fatal | 0 |
Injury Ind | No |
Injure | 0 |
Ignite Ind | No |
Num Pub Evacuated | 0.0 |
Communication State Fed Ind | Yes |
Party Initiated Communication | Operator |
Federal | No |
Location Type | Public Property |
Incident Area Type | Underground |
Incident Area Subtype | Under Pavement |
Depth Of Cover | 36.0 |
Other Underground Facilities | No |
Crossing | No |
Pipe Facility Type | Investor Owned |
System Part Involved | Main |
Installation Year | 2023.0 |
Manufactured Year | 2022.0 |
Pipe Diameter | 4.0 |
Pipe Specification | Astm D2513 |
Pipe Manufacturer | Polypipe |
Material Involved | Plastic |
Plastic Type | Polyethylene (Pe) |
Plastic Sdr | 13.5 |
Material Pe Pipe Code | 2708 |
Release Type | Mechanical Puncture |
Puncture Axial | 2.0 |
Puncture Circum | 2.0 |
Class Location Type | Class 3 Location |
Est Cost Oper Paid | 0.0 |
Est Cost Prop Damage | 28000.0 |
Est Cost Emergency | 200000.0 |
Est Cost Other | 0.0 |
Gas Cost In Mcf | 3.71 |
Est Cost Unintentional Release | 4.0 |
Est Cost Intentional Release | 4.0 |
Prpty | 228008.0 |
Commercial Affected | 10.0 |
Industrial Affected | 0.0 |
Residences Affected | 155.0 |
Num Persons Hosp Not Ovnght | 0.0 |
Num Injured Treated By Emt | 0.0 |
Num Resident Building Affctd | 155.0 |
Num Business Building Affctd | 10.0 |
Accident Psig | 0.5 |
Normal Psig | 0.5 |
Mop Psig | 1.0 |
Mop Cfr Section | 192.623 View CFR 49 §192 |
Maop Established Date | 2023-10-11 00:00:00 |
Accident Pressure | Pressure Did Not Exceed Maop |
Gas Odorized System Type | Combination Of Odorization Types |
Gas Odorized Lvl Not Msrd Ind | Yes |
Scada In Place Ind | Yes |
Scada Operating Ind | Yes |
Scada Functional Ind | Yes |
Scada Detection Ind | No |
Scada Conf Ind | No |
Accident Identifier | Notification From Public |
Investigation Status | No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate) |
Investigation Status Details | Low pressure distribution system not monitored by gas control, and leak was too small to be expected to trigger a hi/lo scada alarm. |
Employee Drug Test Ind | No |
Contractor Drug Test Ind | No |
Cause | Excavation Damage |
Cause Details | Excavation Damage By Third Party |
Ex Party Type | Excavation Damage By Third Party |
Prior Notification Ind | Yes |
One Call System Ind | Yes |
State Law Exempt Ind | No |
Notify Cga Dirt | Yes |
Public Row Ind | Yes |
Public Subtype | City Street |
Joint Trench Ind | No |
Cross Bore Ind | Yes |
Depth Of Grade | Measured Depth From Grade |
Depth Of Grade Detail | 36 |
Excavator Type | Contractor |
Excavator Equipment | Directional Drilling |
Work Performed | Telecommunications |
One Call Notified Ind | Yes |
One Call Center Name | Ohio Utility Protection Service (Oups) |
White Lined Ind | Unknown |
Locator Type | Contract Locator |
Visible Marks | Yes |
Service Interruption | Yes |
Service Interruption Hours | 52.0 |
Root Cause Category | Excavation Issue |
Root Cause Type | Excavator Dug Prior To Verifying Marks By Test-Hole (Pothole) |
Excvtn Dmg Third Party Ind | Yes |
Preparer Name | D***** E**** E**** |
Preparer Title | Manager Ohio Pipeline Safety |
Preparer Email | D*************@d*************.com |
Preparer Telephone | 3305715796 |
Local Contact Name | B****** J****** |
Local Contact Email | B****************@d************.com |
Local Contact Telephone | 3308072154 |
Authorizer Name | D***** E**** |
Authorizer Title | Manager Ohio Pipeline Safety |
Authorizer Telephone | 3305715796 |
Authorizer Email | D*************@d*************.com |
Narrative | Shortly after 12:00 est on january 29, 2025, enbridge gas ohio (ego) began receiving "no gas" calls from customers on 1st dr sw in new philadelphia, ohio. By approximately 12:30 est, ego employees arrived on site to investigate and discovered a third-party contractor at 230 1st dr sw installing fiber optic conduit using horizontal directional drilling. The contractor's drill path had crossed 811 paint markings indicating the presence of utilities but had not daylighted them. Due to a loss of gas pressure downstream of their work, ego ordered the contractor to stop immediately, and they complied. Ego crews exposed the area where the drill path crossed accurately marked ego facilities and found that the 2" pilot bore had cross-bored the 4" mdpl low-pressure mainline. Additionally, the drilling equipment had damaged a nearby 2" water line, causing water to inundate the ego facility and flow into the gas system at a high rate. Given the natural gas system was operating at less than 1 psig, the water entering the pipeline created an effective seal, resulting in minimal natural gas loss. Ego promptly made repairs and began assessing the extent of water in the gas system. Ultimately, 165 customers were shut off due to no gas or low pressure across several intersecting streets. As the number of affected customers exceeded 100, ego communicated the outage and its impacts to the public utility commission of ohio. Ego crews, along with mobilized approved contractors, initiated a 24/7 operation to dewater mainlines and services in the affected area. Ego also offered hotel accommodations and warming centers to affected customers as overnight temperatures were below freezing. By approximately 16:00 est on january 31, 2025, enough water had been successfully removed from the system to restore adequate pressure for all affected customers. By 12:00 est on february 1, 2025, 150 customers had been restored to service. The remaining 15 customers could not be restored due to no access, but ego continued outreach until all were restored the following week. On february 6, 2025, a consolidated review of timesheets and invoices from the outage showed that the ego response, including damage repairs, dewatering, and restoration of service, would exceed the $149,400 outlined in �191.3. Accordingly, ego notified the nrc and the public utility commission of ohio. |
External Resources
PHMSA pipeline safety insights.
Product
Features
Company
All rights reserved. Copyright © by ClearPHMSA