HL incident on 2024-09-11 — TX

Operator
Centurion Pipeline L.p.
Cause
Natural Force Damage
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$100
Incident datetime
2024-09-11 00:00 UTC
Report number
Location
TX
Narrative
On 8/11/24 at 23:30, a leak was discovered in the mainline pump strainer area of the el reno to cushing system #2 line at el reno station. The area was isolated and the line shutdown. The investigation determined the leak was coming from a threaded 1/2-inch pvit fitting. Approximately 5 barrels of crude oil was released to the ground. Released product was cleaned up and impacted soil remediated. Failed fitting was replaced and line restarted. The cause of the leak is still under investigation. A supplemental report will be submitted once the investigation is complete. Supplemental report filed on november 15, 2024: during the accident investigation, it was determined that sudden heavy rainfall cause increased settling of the soil in the area of the fitting. Prior to the leak, the ground had previously been excavated and backfilled. Weather conditions were in drought prior to the rainfall. With the age of the fitting and the sudden rainfall causing settling, the fitting leaked. The threaded fitting was replaced with a single stainless steel line to prevent future reoccurrence. The single stainless steel line will prevent multiple connection points that could serve as potential leak points.
Detailed record list
Report Received Date
2024-09-11 00:00:00
Iyear
2024
Report Number
20240216
Supplemental Number
40223
Report Type
Supplemental Final
Operator Id
Name
Centurion Pipeline L.p.
Operator Street Address
1300 Main Street
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Time Zone
Central
Daylight Savings Ind
Yes
Location Latitude
Location Longitude
Commodity Released Type
Crude Oil
Unintentional Release Bbls
5
Recovered Bbls
5
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Operator Employee
System Part Involved
Onshore Pump/meter Station Equipment And Piping
On Off Shore
Onshore
Status When Identified
Normal Operation, Includes Pauses Between Batches And During Maintenance
Shutdown Due Accident Ind
Yes
Communication State Fed Ind
No
Nrc Rpt Num
Nrc Notification Not Required
Ignite Ind
No
Notify Qualified Indiv Ind
Yes
Oil Spill Removal Org Ind
No
Num Pub Evacuated
0
Pipe Fac Name
El Reno Station
Segment Name
El Reno To Cushing System #2 16-Inch
Onshore State Abbreviation
Ok
Onshore Postal Code
73036
Onshore City Name
El Reno
Onshore County Name
Canadian
Designated Location
Milepost
Designated Name
0+00
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
28
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Tubing
Tubing Material
Stainless Steel
Tubing Type
Rigid
Installation Year
Unknown
Manufactured Year
Unknown
Material Involved
Material Other Than Carbon Steel
Material Details
Stainless Steel
Release Type
Leak
Leak Type
Crack
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
Yes
Soil Remed Ind
Yes
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
Yes
Other Pop Ind
Yes
Other Pop Yes No
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
0
Est Cost Prop Damage
100
Est Cost Emergency
20000
Est Cost Environmental
20000
Est Cost Other
0
Prpty
40100
Num Persons Hosp Not Ovnght
0
Num Injured Treated By Emt
0
Num Resident Building Affctd
0
Num Business Building Affctd
0
Accident Psig
258
Mop Psig
740
Mop Cfr Section
Subpart E Pressure Test �195.406(A)(3)
Maop Established Date
2016-11-10 00:00:00
Maop Reversal Flow Ind
No
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
Yes
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
A review of the accident determined that there were no control room actions that contributed to the event.
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Natural Force Damage
Cause Details
Heavy Rains/floods
Natural Force Type
Heavy Rains/floods
Heavy Rains Subtype
Other
Nf Other Details
Increased Earth Settling From Extreme Dry Weather To Sudden Rainfall.
Nf Extreme Weather Ind
No
Preparer Name
T*** N*******
Preparer Title
Director - Dot Compliance
Preparer Email
T************@e*************.com
Preparer Telephone
713-989-7126
Prepared Date
2024-11-14 00:00:00
Authorizer Name
T*** N*******
Authorizer Telephone
713-989-7126
Authorizer Title
Director - Dot Compliance
Authorizer Email
T************@e*************.com
Narrative
On 8/11/24 at 23:30, a leak was discovered in the mainline pump strainer area of the el reno to cushing system #2 line at el reno station. The area was isolated and the line shutdown. The investigation determined the leak was coming from a threaded 1/2-inch pvit fitting. Approximately 5 barrels of crude oil was released to the ground. Released product was cleaned up and impacted soil remediated. Failed fitting was replaced and line restarted. The cause of the leak is still under investigation. A supplemental report will be submitted once the investigation is complete. Supplemental report filed on november 15, 2024: during the accident investigation, it was determined that sudden heavy rainfall cause increased settling of the soil in the area of the fitting. Prior to the leak, the ground had previously been excavated and backfilled. Weather conditions were in drought prior to the rainfall. With the age of the fitting and the sudden rainfall causing settling, the fitting leaked. The threaded fitting was replaced with a single stainless steel line to prevent future reoccurrence. The single stainless steel line will prevent multiple connection points that could serve as potential leak points.
Report Received Date 2024-09-11 00:00:00
Iyear 2024
Report Number 20240216
Supplemental Number 40223
Report Type Supplemental Final
Operator Id 31888 PHMSA Enforcement
Name Centurion Pipeline L.p.
Operator Street Address 1300 Main Street
Operator City Name Houston
Operator State Abbreviation TX
Operator Postal Code 77002
Time Zone Central
Daylight Savings Ind Yes
Location Latitude 35.511293 Google Maps OpenStreetMap
Location Longitude -97.884654 Google Maps OpenStreetMap
Commodity Released Type Crude Oil
Unintentional Release Bbls 5
Recovered Bbls 5
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Local Operating Personnel, Including Contractors
Operator Type Operator Employee
System Part Involved Onshore Pump/meter Station Equipment And Piping
On Off Shore Onshore
Status When Identified Normal Operation, Includes Pauses Between Batches And During Maintenance
Shutdown Due Accident Ind Yes
Communication State Fed Ind No
Nrc Rpt Num Nrc Notification Not Required NRC Report How to search
Ignite Ind No
Notify Qualified Indiv Ind Yes
Oil Spill Removal Org Ind No
Num Pub Evacuated 0
Pipe Fac Name El Reno Station
Segment Name El Reno To Cushing System #2 16-Inch
Onshore State Abbreviation Ok
Onshore Postal Code 73036
Onshore City Name El Reno
Onshore County Name Canadian
Designated Location Milepost
Designated Name 0+00
Federal No
Location Type Totally Contained On Operator-Controlled Property
Incident Area Type Underground
Incident Area Subtype Under Soil
Depth Of Cover 28
Crossing No
Pipe Facility Type Interstate
Item Involved Tubing
Tubing Material Stainless Steel
Tubing Type Rigid
Installation Year Unknown
Manufactured Year Unknown
Material Involved Material Other Than Carbon Steel
Material Details Stainless Steel
Release Type Leak
Leak Type Crack
Wildlife Impact Ind No
Soil Contamination Yes
Long Term Assessment No
Remediation Ind Yes
Soil Remed Ind Yes
Water Contam Ind No
Could Be Hca Yes
Commodity Reached Hca Yes
Other Pop Ind Yes
Other Pop Yes No Yes
Est Cost Oper Paid 0
Est Cost Gas Released 0
Est Cost Prop Damage 100
Est Cost Emergency 20000
Est Cost Environmental 20000
Est Cost Other 0
Prpty 40100
Num Persons Hosp Not Ovnght 0
Num Injured Treated By Emt 0
Num Resident Building Affctd 0
Num Business Building Affctd 0
Accident Psig 258
Mop Psig 740
Mop Cfr Section Subpart E Pressure Test �195.406(A)(3) View CFR 49 §192
Maop Established Date 2016-11-10 00:00:00
Maop Reversal Flow Ind No
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Pipeline Function > 20% Smys Regulated Transmission
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind No
Scada Conf Ind No
Cpm In Place Ind Yes
Cpm Operating Ind Yes
Cpm Functional Ind Yes
Cpm Detection Ind No
Cpm Conf Ind No
Investigation Status No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details A review of the accident determined that there were no control room actions that contributed to the event.
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Natural Force Damage
Cause Details Heavy Rains/floods
Natural Force Type Heavy Rains/floods
Heavy Rains Subtype Other
Nf Other Details Increased Earth Settling From Extreme Dry Weather To Sudden Rainfall.
Nf Extreme Weather Ind No
Preparer Name T*** N*******
Preparer Title Director - Dot Compliance
Preparer Email T************@e*************.com
Preparer Telephone 713-989-7126
Prepared Date 2024-11-14 00:00:00
Authorizer Name T*** N*******
Authorizer Telephone 713-989-7126
Authorizer Title Director - Dot Compliance
Authorizer Email T************@e*************.com
Narrative On 8/11/24 at 23:30, a leak was discovered in the mainline pump strainer area of the el reno to cushing system #2 line at el reno station. The area was isolated and the line shutdown. The investigation determined the leak was coming from a threaded 1/2-inch pvit fitting. Approximately 5 barrels of crude oil was released to the ground. Released product was cleaned up and impacted soil remediated. Failed fitting was replaced and line restarted. The cause of the leak is still under investigation. A supplemental report will be submitted once the investigation is complete. Supplemental report filed on november 15, 2024: during the accident investigation, it was determined that sudden heavy rainfall cause increased settling of the soil in the area of the fitting. Prior to the leak, the ground had previously been excavated and backfilled. Weather conditions were in drought prior to the rainfall. With the age of the fitting and the sudden rainfall causing settling, the fitting leaked. The threaded fitting was replaced with a single stainless steel line to prevent future reoccurrence. The single stainless steel line will prevent multiple connection points that could serve as potential leak points.