Incident details
Operator, cause, commodity and consequences with raw source fields.
GTG incident on 2023-11-02 — TX
Operator
Enable Gas Transmission, Llc
Cause
Material Failure Of Pipe Or Weld
Commodity
Natural Gas
Program
GTG
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$10,000,000
Incident datetime
2023-11-02 00:00 UTC
Report number
Location
TX
Narrative
On 10/04/2023 at approximately 443pm, bt-1-an, a natural gas transmission pipeline, ruptured and ignited at jessieville junction. -443pm: system control was notified by a caller from the general public at 443pm -445pm: the lead gas controller began notifying ops personnel at 445pm of a possible failure at jessieville junction. -447pm: the lead gas controller received a rate of change alarm indicating a rapid loss of line pressure. -529pm: ops personnel arrived on site and confirmed that a pipeline had failed at jessieville junction. -531pm: ops personnel isolated the downstream valve 16" bt-1-as valve at hwy 88. -544pm: nrc notification was made (nrc# 1380909); 48hr nrc update (nrc# 1381352) -615pm: determination was made that above ground piping for bt-1-an 24", bt-1 16", bt-1-as 16", and bt-1 30" were affected at jessieville junction. -630pm: ops personnel isolated the upstream valves for bt-1 16" and bt-1-an 24" at dry fork mlv ops personnel manned the valves at dry fork and hwy 88 while additional technicians stayed onsite at jessieville junction throughout the night to monitor the flame as it burned out. Three people were evacuated from a home approximately 645' from the failure site on 10/04/2023; they were evacuated at the time of incident and able to return to the home at approximately 730pm that evening. 10/05/2023 -744am: the fire at the failure site was confirmed to be completely extinguished. -800am: ops personnel initiated the operation of air movers -1255pm: failure site was cleared for access and personnel from aid and the sw region were able to begin their investigation 10/07/2023 -the suspected origin failure piece (bt-1-an) was loaded on a truck to be shipped to adv integrity lab in magnolia, tx -contract crew began excavating bt-1-an, bt-1 16", bt-1 30", and bt-1-as 16" to the appropriate location on each segment to cut and cap. The metallurgical testing results for the origin piece of pipe are pending and a supplemental report will be filed. On 10/13/2023, energy transfer received a corrective action order (4-2023-007 cao egt) defining the requirements to return bt-1-an, bt-1 16", bt-1 30", and bt-1-as to service from dry fork mlv to hwy 88 gate valve. The segments remain isolated and out of service at the of this filing. Customer impact -there are 12 total taps and 1 town border out of service due to the isolated segment from dry fork mlv to hwy 88 gate valve being out of service. -8 domestic style taps and 4 rural extension u-shape taps -hot springs #2 town border -the local distribution company in the area has 244 customers affected with the isolated segments from dry fork mlv to hwy 88 gate valve out of service. *supplemental report updates* part c - additional facility information was updated: -3c: smys is 60,000 -3f: pipe manufacturer is a.O. Smith/ US steel -c6: type of release is longitudinal and approx. Size of release is 30.0in x 538in part g - apparent cause was updated: -g5 - "material failure of pipe or weld" was selected as the apparent cause. -determined by metallurgical analysis. -environmental cracking-related "stress corrosion cracking". -post construction pt pressure was added part j - integrity inspections -updated with most recent and previous tool run information. Updated supplemental and final report with date and time that flow was established on bt-1-an. The pipeline was officially restarted on 3-28-2024 at 19:20.
Detailed record list
Report Received Date
2023-11-02 00:00:00
Iyear
2023
Report Number
20230099
Supplemental Number
39400
Report Type
Supplemental Final
Operator Id
Name
Enable Gas Transmission, Llc
Operator Street Address
1300 Main Street
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Time Zone
Central
Daylight Savings Ind
Yes
Location Latitude
34.68262454
Location Longitude
-93.1115072
Nrc Rpt Num
1380909
Additional Nrc Report Numbers
1381352
Commodity Released Type
Natural Gas
Unintentional Release
99860
Intentional Release
0
Accompanying Liquid
0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Status When Identified
Normal Operation, Includes Pauses During Maintenance
Shutdown Due Accident Ind
Yes
Communication State Fed Ind
Yes
Party Initiated Communication
Local/state/federal Emergency Responder
Ignite Ind
Yes
How Extinguished
Allowed To Burn Out
Gas Consumed By Fire In Mcf
99860
Explode Ind
No
Upstream Action Taken
Valve Closure
Downstream Action Taken
Valve Closure
Num Pub Evacuated
2
On Off Shore
Onshore
Onshore State Abbreviation
Ar
Onshore Postal Code
71949
Onshore City Name
Not Within A Municipality
Onshore County Name
Garland
Designated Location
Not Applicable
Pipe Fac Name
Bt-1-An At Jessieville Junction
Segment Name
Bt-1-An
Federal
No
Location Type
Operator-Controlled Property
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
48
Other Underground Facilities
No
Crossing
No
Pipe Facility Type
Interstate
System Part Involved
Onshore Pipeline, Including Valve Sites
Item Involved
Pipe
Pipe Type
Pipe Body
Pipe Diameter
24
Puddle Weld Ind
No
Pipe Wall Thickness
0.281
Pipe Smys
60000
Pipe Specification
Api-5l
Pipe Seam Type
Dsaw
Pipe Manufacturer
A.o. Smith/us Steel
Pipe Coating Type
Coal Tar
Coating Applied Ind
No
Installation Year
1967
Manufactured Year
Unknown
Material Involved
Carbon Steel
Release Type
Rupture
Rupture Orient
Longitudinal
Rupture Length
538
Rupture Width
30
Class Location Type
Class 1 Location
Could Be Hca
No
Pir Radius
524
Heat Damage Ind
Yes
Non Heat Damage Ind
No
Did Occur In Mca Ind
No
Est Cost Oper Paid
60345
Est Cost Unintentional Release
300379
Est Cost Intentional Release
0
Est Cost Prop Damage
10000000
Est Cost Emergency
75000
Est Cost Other
0
Gas Cost In Mcf
3.008
Prpty
10435724
Num Persons Hosp Not Ovnght
0
Num Injured Treated By Emt
0
Num Resident Building Affctd
10
Num Business Building Affctd
4
Wildlife Impact Ind
No
Accident Psig
980
Gas Flow In Pipe In Mcf
220000
Mop Psig
1000
Mop Cfr Section
192.619(A)(1)
Maop Established Date
1967-10-04 00:00:00
Maop Reversal Flow Ind
No
Accident Pressure
Pressure Did Not Exceed Maop
Pressure Restriction Ind
No
Gas Required Odorized Ind
No
Upstream Valve Type Ind
Manual
Downstream Valve Type Ind
Manual
Length Segment Isolated
153120
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
Transmission System
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
Yes
Scada Conf Ind
Yes
Accident Identifier
Notification From Public
Investigation Status
Yes, specify investigation result(s): (select all that apply)
Invest Schedule Ind
Yes
Invest No Control Room Ind
Yes
Invest No Controller Ind
Yes
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Material Failure Of Pipe Or Weld
Cause Details
Environmental Cracking-Related
Pwjf Failure Type
Environmental Cracking-Related
Metallurgical Ind
Yes
Stress Subtype
Stress Corrosion Cracking
Post Constr Pressure Test Val
1415
Collected Data Ind
Yes
Axial Magnetic Flx Lkg Ind
Yes
Geometry Deformation Ind
Yes
Axial Recent Year
2023
Axial Rcnt Propul Method
Free Swimming
Axial Rcnt Attuned Detect
Metal Loss
Axial Rcnt Atnd Dtct Metal
High Resolution
Axial Previous Year
2013
Axial Prev Propul Method
Free Swimming
Axial Prev Attuned Detect
Metal Loss
Axial Prev Atnd Dtct Metal
High Resolution
Geometry Recent Year
2023
Geometry Rcnt Propul Method
Free Swimming
Geometry Rcnt Resolution
High Resolution
Geometrt Rcnt Measur Cups
No Cups
Geometry Previous Year
2013
Geometry Prev Propul Method
Free Swimming
Geometry Prev Resolution
Standard Resolution
Geometrt Prev Measur Cups
Inside Ili Cups
Has Hydrtst Conduc Before Ind
No
Direct Asmnt Conducted
No
Non Destructive Exam Ind
No
Extrnl Cor Galvanic Ind
Yes
Preparer Name
D***** A******
Preparer Title
Sr. Dot Specialist
Preparer Email
D*************@e*************.com
Preparer Telephone
501-351-8513
Local Contact Name
D***** A******
Local Contact Email
D*************@e*************.com
Local Contact Telephone
501-351-8513
Authorizer Name
S**** S*****
Authorizer Title
Director Regulatory Compliance
Authorizer Telephone
405-557-5271
Authorizer Email
S***********@e*************.com
Narrative
On 10/04/2023 at approximately 443pm, bt-1-an, a natural gas transmission pipeline, ruptured and ignited at jessieville junction. -443pm: system control was notified by a caller from the general public at 443pm -445pm: the lead gas controller began notifying ops personnel at 445pm of a possible failure at jessieville junction. -447pm: the lead gas controller received a rate of change alarm indicating a rapid loss of line pressure. -529pm: ops personnel arrived on site and confirmed that a pipeline had failed at jessieville junction. -531pm: ops personnel isolated the downstream valve 16" bt-1-as valve at hwy 88. -544pm: nrc notification was made (nrc# 1380909); 48hr nrc update (nrc# 1381352) -615pm: determination was made that above ground piping for bt-1-an 24", bt-1 16", bt-1-as 16", and bt-1 30" were affected at jessieville junction. -630pm: ops personnel isolated the upstream valves for bt-1 16" and bt-1-an 24" at dry fork mlv ops personnel manned the valves at dry fork and hwy 88 while additional technicians stayed onsite at jessieville junction throughout the night to monitor the flame as it burned out. Three people were evacuated from a home approximately 645' from the failure site on 10/04/2023; they were evacuated at the time of incident and able to return to the home at approximately 730pm that evening. 10/05/2023 -744am: the fire at the failure site was confirmed to be completely extinguished. -800am: ops personnel initiated the operation of air movers -1255pm: failure site was cleared for access and personnel from aid and the sw region were able to begin their investigation 10/07/2023 -the suspected origin failure piece (bt-1-an) was loaded on a truck to be shipped to adv integrity lab in magnolia, tx -contract crew began excavating bt-1-an, bt-1 16", bt-1 30", and bt-1-as 16" to the appropriate location on each segment to cut and cap. The metallurgical testing results for the origin piece of pipe are pending and a supplemental report will be filed. On 10/13/2023, energy transfer received a corrective action order (4-2023-007 cao egt) defining the requirements to return bt-1-an, bt-1 16", bt-1 30", and bt-1-as to service from dry fork mlv to hwy 88 gate valve. The segments remain isolated and out of service at the of this filing. Customer impact -there are 12 total taps and 1 town border out of service due to the isolated segment from dry fork mlv to hwy 88 gate valve being out of service. -8 domestic style taps and 4 rural extension u-shape taps -hot springs #2 town border -the local distribution company in the area has 244 customers affected with the isolated segments from dry fork mlv to hwy 88 gate valve out of service. *supplemental report updates* part c - additional facility information was updated: -3c: smys is 60,000 -3f: pipe manufacturer is a.O. Smith/ US steel -c6: type of release is longitudinal and approx. Size of release is 30.0in x 538in part g - apparent cause was updated: -g5 - "material failure of pipe or weld" was selected as the apparent cause. -determined by metallurgical analysis. -environmental cracking-related "stress corrosion cracking". -post construction pt pressure was added part j - integrity inspections -updated with most recent and previous tool run information. Updated supplemental and final report with date and time that flow was established on bt-1-an. The pipeline was officially restarted on 3-28-2024 at 19:20.
Report Received Date | 2023-11-02 00:00:00 |
---|---|
Iyear | 2023 |
Report Number | 20230099 |
Supplemental Number | 39400 |
Report Type | Supplemental Final |
Operator Id | 602 PHMSA Enforcement |
Name | Enable Gas Transmission, Llc |
Operator Street Address | 1300 Main Street |
Operator City Name | Houston |
Operator State Abbreviation | TX |
Operator Postal Code | 77002 |
Time Zone | Central |
Daylight Savings Ind | Yes |
Location Latitude | 34.68262454 Google Maps OpenStreetMap |
Location Longitude | -93.1115072 Google Maps OpenStreetMap |
Nrc Rpt Num | 1380909 NRC Report How to search |
Additional Nrc Report Numbers | 1381352 |
Commodity Released Type | Natural Gas |
Unintentional Release | 99860 |
Intentional Release | 0 |
Accompanying Liquid | 0 |
Fatality Ind | No |
Fatal | 0 |
Injury Ind | No |
Injure | 0 |
Status When Identified | Normal Operation, Includes Pauses During Maintenance |
Shutdown Due Accident Ind | Yes |
Communication State Fed Ind | Yes |
Party Initiated Communication | Local/state/federal Emergency Responder |
Ignite Ind | Yes |
How Extinguished | Allowed To Burn Out |
Gas Consumed By Fire In Mcf | 99860 |
Explode Ind | No |
Upstream Action Taken | Valve Closure |
Downstream Action Taken | Valve Closure |
Num Pub Evacuated | 2 |
On Off Shore | Onshore |
Onshore State Abbreviation | Ar |
Onshore Postal Code | 71949 |
Onshore City Name | Not Within A Municipality |
Onshore County Name | Garland |
Designated Location | Not Applicable |
Pipe Fac Name | Bt-1-An At Jessieville Junction |
Segment Name | Bt-1-An |
Federal | No |
Location Type | Operator-Controlled Property |
Incident Area Type | Underground |
Incident Area Subtype | Under Soil |
Depth Of Cover | 48 |
Other Underground Facilities | No |
Crossing | No |
Pipe Facility Type | Interstate |
System Part Involved | Onshore Pipeline, Including Valve Sites |
Item Involved | Pipe |
Pipe Type | Pipe Body |
Pipe Diameter | 24 |
Puddle Weld Ind | No |
Pipe Wall Thickness | 0.281 |
Pipe Smys | 60000 |
Pipe Specification | Api-5l |
Pipe Seam Type | Dsaw |
Pipe Manufacturer | A.o. Smith/us Steel |
Pipe Coating Type | Coal Tar |
Coating Applied Ind | No |
Installation Year | 1967 |
Manufactured Year | Unknown |
Material Involved | Carbon Steel |
Release Type | Rupture |
Rupture Orient | Longitudinal |
Rupture Length | 538 |
Rupture Width | 30 |
Class Location Type | Class 1 Location |
Could Be Hca | No |
Pir Radius | 524 |
Heat Damage Ind | Yes |
Non Heat Damage Ind | No |
Did Occur In Mca Ind | No |
Est Cost Oper Paid | 60345 |
Est Cost Unintentional Release | 300379 |
Est Cost Intentional Release | 0 |
Est Cost Prop Damage | 10000000 |
Est Cost Emergency | 75000 |
Est Cost Other | 0 |
Gas Cost In Mcf | 3.008 |
Prpty | 10435724 |
Num Persons Hosp Not Ovnght | 0 |
Num Injured Treated By Emt | 0 |
Num Resident Building Affctd | 10 |
Num Business Building Affctd | 4 |
Wildlife Impact Ind | No |
Accident Psig | 980 |
Gas Flow In Pipe In Mcf | 220000 |
Mop Psig | 1000 |
Mop Cfr Section | 192.619(A)(1) View CFR 49 §192 |
Maop Established Date | 1967-10-04 00:00:00 |
Maop Reversal Flow Ind | No |
Accident Pressure | Pressure Did Not Exceed Maop |
Pressure Restriction Ind | No |
Gas Required Odorized Ind | No |
Upstream Valve Type Ind | Manual |
Downstream Valve Type Ind | Manual |
Length Segment Isolated | 153120 |
Internal Inspection Ind | Yes |
Operation Complications Ind | No |
Pipeline Function | Transmission System |
Scada In Place Ind | Yes |
Scada Operating Ind | Yes |
Scada Functional Ind | Yes |
Scada Detection Ind | Yes |
Scada Conf Ind | Yes |
Accident Identifier | Notification From Public |
Investigation Status | Yes, specify investigation result(s): (select all that apply) |
Invest Schedule Ind | Yes |
Invest No Control Room Ind | Yes |
Invest No Controller Ind | Yes |
Employee Drug Test Ind | No |
Contractor Drug Test Ind | No |
Cause | Material Failure Of Pipe Or Weld |
Cause Details | Environmental Cracking-Related |
Pwjf Failure Type | Environmental Cracking-Related |
Metallurgical Ind | Yes |
Stress Subtype | Stress Corrosion Cracking |
Post Constr Pressure Test Val | 1415 |
Collected Data Ind | Yes |
Axial Magnetic Flx Lkg Ind | Yes |
Geometry Deformation Ind | Yes |
Axial Recent Year | 2023 |
Axial Rcnt Propul Method | Free Swimming |
Axial Rcnt Attuned Detect | Metal Loss |
Axial Rcnt Atnd Dtct Metal | High Resolution |
Axial Previous Year | 2013 |
Axial Prev Propul Method | Free Swimming |
Axial Prev Attuned Detect | Metal Loss |
Axial Prev Atnd Dtct Metal | High Resolution |
Geometry Recent Year | 2023 |
Geometry Rcnt Propul Method | Free Swimming |
Geometry Rcnt Resolution | High Resolution |
Geometrt Rcnt Measur Cups | No Cups |
Geometry Previous Year | 2013 |
Geometry Prev Propul Method | Free Swimming |
Geometry Prev Resolution | Standard Resolution |
Geometrt Prev Measur Cups | Inside Ili Cups |
Has Hydrtst Conduc Before Ind | No |
Direct Asmnt Conducted | No |
Non Destructive Exam Ind | No |
Extrnl Cor Galvanic Ind | Yes |
Preparer Name | D***** A****** |
Preparer Title | Sr. Dot Specialist |
Preparer Email | D*************@e*************.com |
Preparer Telephone | 501-351-8513 |
Local Contact Name | D***** A****** |
Local Contact Email | D*************@e*************.com |
Local Contact Telephone | 501-351-8513 |
Authorizer Name | S**** S***** |
Authorizer Title | Director Regulatory Compliance |
Authorizer Telephone | 405-557-5271 |
Authorizer Email | S***********@e*************.com |
Narrative | On 10/04/2023 at approximately 443pm, bt-1-an, a natural gas transmission pipeline, ruptured and ignited at jessieville junction. -443pm: system control was notified by a caller from the general public at 443pm -445pm: the lead gas controller began notifying ops personnel at 445pm of a possible failure at jessieville junction. -447pm: the lead gas controller received a rate of change alarm indicating a rapid loss of line pressure. -529pm: ops personnel arrived on site and confirmed that a pipeline had failed at jessieville junction. -531pm: ops personnel isolated the downstream valve 16" bt-1-as valve at hwy 88. -544pm: nrc notification was made (nrc# 1380909); 48hr nrc update (nrc# 1381352) -615pm: determination was made that above ground piping for bt-1-an 24", bt-1 16", bt-1-as 16", and bt-1 30" were affected at jessieville junction. -630pm: ops personnel isolated the upstream valves for bt-1 16" and bt-1-an 24" at dry fork mlv ops personnel manned the valves at dry fork and hwy 88 while additional technicians stayed onsite at jessieville junction throughout the night to monitor the flame as it burned out. Three people were evacuated from a home approximately 645' from the failure site on 10/04/2023; they were evacuated at the time of incident and able to return to the home at approximately 730pm that evening. 10/05/2023 -744am: the fire at the failure site was confirmed to be completely extinguished. -800am: ops personnel initiated the operation of air movers -1255pm: failure site was cleared for access and personnel from aid and the sw region were able to begin their investigation 10/07/2023 -the suspected origin failure piece (bt-1-an) was loaded on a truck to be shipped to adv integrity lab in magnolia, tx -contract crew began excavating bt-1-an, bt-1 16", bt-1 30", and bt-1-as 16" to the appropriate location on each segment to cut and cap. The metallurgical testing results for the origin piece of pipe are pending and a supplemental report will be filed. On 10/13/2023, energy transfer received a corrective action order (4-2023-007 cao egt) defining the requirements to return bt-1-an, bt-1 16", bt-1 30", and bt-1-as to service from dry fork mlv to hwy 88 gate valve. The segments remain isolated and out of service at the of this filing. Customer impact -there are 12 total taps and 1 town border out of service due to the isolated segment from dry fork mlv to hwy 88 gate valve being out of service. -8 domestic style taps and 4 rural extension u-shape taps -hot springs #2 town border -the local distribution company in the area has 244 customers affected with the isolated segments from dry fork mlv to hwy 88 gate valve out of service. *supplemental report updates* part c - additional facility information was updated: -3c: smys is 60,000 -3f: pipe manufacturer is a.O. Smith/ US steel -c6: type of release is longitudinal and approx. Size of release is 30.0in x 538in part g - apparent cause was updated: -g5 - "material failure of pipe or weld" was selected as the apparent cause. -determined by metallurgical analysis. -environmental cracking-related "stress corrosion cracking". -post construction pt pressure was added part j - integrity inspections -updated with most recent and previous tool run information. Updated supplemental and final report with date and time that flow was established on bt-1-an. The pipeline was officially restarted on 3-28-2024 at 19:20. |