GTG incident on 2023-09-01 — TX

Operator
Cheniere Corpus Christi Pipeline
Cause
Equipment Failure
Commodity
Natural Gas
Program
GTG
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$0
Incident datetime
2023-09-01 00:00 UTC
Report number
Location
TX
Narrative
At 04:14 on 08/19/23 the control center received a critical alarm indicating the station esd was activated. All compressors were shutdown and isolation valves were closed in the station. Upon activation of the esd the compressor station began an entire blowdown of natural gas. The onsite operator went to the compressor building to determine if there was a fire or any gas detected within the building. Once confirmed there was no immediate danger, the operator began closing off the manual block valves to reduce the venting of gas emissions to the atmosphere. Additional operators were called out to assist the onsite operator and arrived at 05:00. The operators reviewed all alarms and found esd 9832u was activated. During the troubleshooting of the esd switch, it was determined the esd rio fuse was blown which caused the esd to activate. The fuse was replaced and all circuits were verified and the esd cleared. At 05:39 the compressor units and station piping were pressured up to normal operating pressure. The first compressor unit was started and put back into service at 07:00 and the second compressor unit was back in service at 07:30. All other compressor units are pressured up and are on standby. All required notifications were submitted and the compressor station was returned to normal operations at 09:45. Final report
Detailed record list
Report Received Date
2023-09-01 00:00:00
Iyear
2023
Report Number
20230082
Supplemental Number
39054
Report Type
Supplemental Final
Operator Id
Name
Cheniere Corpus Christi Pipeline
Operator Street Address
845 Texas St. Suite 1250
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Time Zone
Central
Daylight Savings Ind
Yes
Location Latitude
Location Longitude
Nrc Rpt Num
Commodity Released Type
Natural Gas
Unintentional Release
3984
Intentional Release
0
Accompanying Liquid
0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Status When Identified
Normal Operation, Includes Pauses During Maintenance
Shutdown Due Accident Ind
Yes
Communication State Fed Ind
No
Ignite Ind
No
Num Pub Evacuated
0
On Off Shore
Onshore
Onshore State Abbreviation
Tx
Onshore Postal Code
78387
Onshore City Name
Not Within A Municipality
Onshore County Name
San Patricio
Designated Location
Survey Station No.
Designated Name
1145+69
Pipe Fac Name
Cheniere Corpus Christi Pipeline
Segment Name
Sinton Compressor Station
Federal
No
Location Type
Operator-Controlled Property
Incident Area Type
Aboveground
Incident Area Subtype
Other
Incident Area Details
Compressor Station Esd Shutdown
Crossing
No
Pipe Facility Type
Interstate
System Part Involved
Onshore Compressor Station Equipment And Piping
Item Involved
Compressor
Installation Year
2017
Manufactured Year
Unknown
Material Involved
Carbon Steel
Release Type
Other
Release Type Details
Compressor Station Esd Activation, Blowdown Of Natural Gas From Facility.
Class Location Type
Class 1 Location
Could Be Hca
No
Pir Radius
1330
Heat Damage Ind
No
Non Heat Damage Ind
No
Did Occur In Mca Ind
No
Est Cost Oper Paid
0
Est Cost Unintentional Release
10677
Est Cost Intentional Release
0
Est Cost Prop Damage
0
Est Cost Emergency
0
Est Cost Other
0
Gas Cost In Mcf
2.68
Prpty
10677
Num Persons Hosp Not Ovnght
0
Num Injured Treated By Emt
0
Num Resident Building Affctd
0
Num Business Building Affctd
0
Wildlife Impact Ind
No
Accident Psig
1220
Gas Flow In Pipe In Mcf
2230000
Mop Psig
1440
Mop Cfr Section
192.619(A)(1)
Maop Established Date
2018-03-09 00:00:00
Maop Reversal Flow Ind
No
Accident Pressure
Pressure Did Not Exceed Maop
Pressure Restriction Ind
No
Gas Required Odorized Ind
No
Pipeline Function
Transmission System
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
Yes
Scada Conf Ind
Yes
Accident Identifier
Scada-Based Information (Such As Alarm(S), Alert(S), Event(S), And/or Volume Or Pack Calculations)
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
No control room or controller action was required.
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Equipment Failure
Cause Details
Malfunction Of Control/relief Equipment
Eq Failure Type
Malfunction Of Control/relief Equipment
Esd System Failure Ind
Yes
Eq Additional Other Ind
Yes
Eq Additional Other Details
Faulty Fuse
Eqf Control Releaf Ind
Yes
Preparer Name
P*** F******
Preparer Title
Manager Pipeline Regulatory Compliance
Preparer Email
P***********@c*******.com
Preparer Telephone
713-375-5855
Preparer Fax
713-375-6000
Local Contact Name
J** C****
Local Contact Email
J********@c*******.com
Local Contact Telephone
361-977-1885
Authorizer Name
C**** W*******
Authorizer Title
Vice President Pipeline Operations
Authorizer Telephone
713-375-5662
Authorizer Email
C*************@c*******.com
Narrative
At 04:14 on 08/19/23 the control center received a critical alarm indicating the station esd was activated. All compressors were shutdown and isolation valves were closed in the station. Upon activation of the esd the compressor station began an entire blowdown of natural gas. The onsite operator went to the compressor building to determine if there was a fire or any gas detected within the building. Once confirmed there was no immediate danger, the operator began closing off the manual block valves to reduce the venting of gas emissions to the atmosphere. Additional operators were called out to assist the onsite operator and arrived at 05:00. The operators reviewed all alarms and found esd 9832u was activated. During the troubleshooting of the esd switch, it was determined the esd rio fuse was blown which caused the esd to activate. The fuse was replaced and all circuits were verified and the esd cleared. At 05:39 the compressor units and station piping were pressured up to normal operating pressure. The first compressor unit was started and put back into service at 07:00 and the second compressor unit was back in service at 07:30. All other compressor units are pressured up and are on standby. All required notifications were submitted and the compressor station was returned to normal operations at 09:45. Final report
Report Received Date 2023-09-01 00:00:00
Iyear 2023
Report Number 20230082
Supplemental Number 39054
Report Type Supplemental Final
Operator Id 39429 PHMSA Enforcement
Name Cheniere Corpus Christi Pipeline
Operator Street Address 845 Texas St. Suite 1250
Operator City Name Houston
Operator State Abbreviation TX
Operator Postal Code 77002
Time Zone Central
Daylight Savings Ind Yes
Location Latitude 28.0922 Google Maps OpenStreetMap
Location Longitude -93.49317 Google Maps OpenStreetMap
Nrc Rpt Num 1376645 NRC Report How to search
Commodity Released Type Natural Gas
Unintentional Release 3984
Intentional Release 0
Accompanying Liquid 0
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Status When Identified Normal Operation, Includes Pauses During Maintenance
Shutdown Due Accident Ind Yes
Communication State Fed Ind No
Ignite Ind No
Num Pub Evacuated 0
On Off Shore Onshore
Onshore State Abbreviation Tx
Onshore Postal Code 78387
Onshore City Name Not Within A Municipality
Onshore County Name San Patricio
Designated Location Survey Station No.
Designated Name 1145+69
Pipe Fac Name Cheniere Corpus Christi Pipeline
Segment Name Sinton Compressor Station
Federal No
Location Type Operator-Controlled Property
Incident Area Type Aboveground
Incident Area Subtype Other
Incident Area Details Compressor Station Esd Shutdown
Crossing No
Pipe Facility Type Interstate
System Part Involved Onshore Compressor Station Equipment And Piping
Item Involved Compressor
Installation Year 2017
Manufactured Year Unknown
Material Involved Carbon Steel
Release Type Other
Release Type Details Compressor Station Esd Activation, Blowdown Of Natural Gas From Facility.
Class Location Type Class 1 Location
Could Be Hca No
Pir Radius 1330
Heat Damage Ind No
Non Heat Damage Ind No
Did Occur In Mca Ind No
Est Cost Oper Paid 0
Est Cost Unintentional Release 10677
Est Cost Intentional Release 0
Est Cost Prop Damage 0
Est Cost Emergency 0
Est Cost Other 0
Gas Cost In Mcf 2.68
Prpty 10677
Num Persons Hosp Not Ovnght 0
Num Injured Treated By Emt 0
Num Resident Building Affctd 0
Num Business Building Affctd 0
Wildlife Impact Ind No
Accident Psig 1220
Gas Flow In Pipe In Mcf 2230000
Mop Psig 1440
Mop Cfr Section 192.619(A)(1) View CFR 49 §192
Maop Established Date 2018-03-09 00:00:00
Maop Reversal Flow Ind No
Accident Pressure Pressure Did Not Exceed Maop
Pressure Restriction Ind No
Gas Required Odorized Ind No
Pipeline Function Transmission System
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind Yes
Scada Conf Ind Yes
Accident Identifier Scada-Based Information (Such As Alarm(S), Alert(S), Event(S), And/or Volume Or Pack Calculations)
Investigation Status No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details No control room or controller action was required.
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Equipment Failure
Cause Details Malfunction Of Control/relief Equipment
Eq Failure Type Malfunction Of Control/relief Equipment
Esd System Failure Ind Yes
Eq Additional Other Ind Yes
Eq Additional Other Details Faulty Fuse
Eqf Control Releaf Ind Yes
Preparer Name P*** F******
Preparer Title Manager Pipeline Regulatory Compliance
Preparer Email P***********@c*******.com
Preparer Telephone 713-375-5855
Preparer Fax 713-375-6000
Local Contact Name J** C****
Local Contact Email J********@c*******.com
Local Contact Telephone 361-977-1885
Authorizer Name C**** W*******
Authorizer Title Vice President Pipeline Operations
Authorizer Telephone 713-375-5662
Authorizer Email C*************@c*******.com
Narrative At 04:14 on 08/19/23 the control center received a critical alarm indicating the station esd was activated. All compressors were shutdown and isolation valves were closed in the station. Upon activation of the esd the compressor station began an entire blowdown of natural gas. The onsite operator went to the compressor building to determine if there was a fire or any gas detected within the building. Once confirmed there was no immediate danger, the operator began closing off the manual block valves to reduce the venting of gas emissions to the atmosphere. Additional operators were called out to assist the onsite operator and arrived at 05:00. The operators reviewed all alarms and found esd 9832u was activated. During the troubleshooting of the esd switch, it was determined the esd rio fuse was blown which caused the esd to activate. The fuse was replaced and all circuits were verified and the esd cleared. At 05:39 the compressor units and station piping were pressured up to normal operating pressure. The first compressor unit was started and put back into service at 07:00 and the second compressor unit was back in service at 07:30. All other compressor units are pressured up and are on standby. All required notifications were submitted and the compressor station was returned to normal operations at 09:45. Final report