GD incident on 2023-07-07 — FL

Operator
Peoples Gas System Inc
Cause
Locating Issue
Commodity
Natural Gas
Program
GD
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$354,400
Incident datetime
2023-07-07 00:00 UTC
Report number
Location
FL, USA
Narrative
On june 7, 2023, at approximately 02:00 hours, pgs was notified that a third-party contractor had struck a gas pipeline at state road 31 & state road 80 in ft myers, florida. Responding crews were dispatched and arrived to find a soil sampling rig was the cause of the damaged pipeline and escaping gas. An assessment was made of the scene, including the ability to safely manage the site. An evaluation of options for the one-way-fed 8" steel pipeline, concluded that the pipeline would remain in service to continually supply approximately 25,300 customers downstream, until a bypass could be installed to isolate the damaged section of pipeline. Over the following days, crews worked to install 750' of 8" steel bypass around the damaged section of pipeline. The bypass was able to isolate the damaged section of pipeline on june 10, 2023, at 13:25, and complete stoppage of the escaping gas. A root cause investigation was concluded and found two primary contributing factors: 1. The gas pipeline in the location of this incident was/is classified as a "high priority subsurface installation (hpsi)" by pgs through the positive response code of "2c". Per florida statue chapter 556 hpsi requires special procedures when digging near an hpsi. With this classification, before any digging or demolition, the excavator must notify the member operator of the start date and time of the excavation. In accordance with f.S. 556, this hpsi was marked by pgs, and a response communicated back to the requesting excavator using a 2c (marked with exceptions: high profile subsurface installation in conflict). The instructions provided and communicated to the excavator indicated, "excavator must notify the member operator of the excavation or demolition start date and time" which the excavator failed to do. In addition, peoples gas also sent an e-mail to the excavator notifying the excavator about the hpsi and requesting the start date and time. The failure by the excavator to notify pgs of the timing of their excavation and the specific location did not allow pgs to give additional location information and specifications related to the pipeline identified as "in conflict". The failure also prevented the possibility of a peoples gas locator being on-site during the excavation. 2. The depth of the pipeline at the damaged location was over thirteen feet deep. When pgs' locator performed the initial locate marking, the locate signal unknowingly jumped off the gas pipeline onto an adjacent telecommunication facility. This caused the locate markings to veer off the gas pipeline by approximately 36" to 48" at the damaged location.
Detailed record list
Report Received Date
2023-07-07 00:00:00
Iyear
2023.0
Report Number
20230033.0
Supplemental Number
38576.0
Report Type
Supplemental Final
Operator Id
Name
Peoples Gas System Inc
Operator Street Address
Po Box 2562
Operator City Name
Tampa
Operator State Abbreviation
FL
Operator Postal Code
33601.0
Time Zone
Eastern
Daylight Savings Ind
Yes
Location Street Address
State Road 31 & State Road 80
Location City Name
Ft.myers
Location County Name
Usa
Location State Abbreviation
FL
Location Postal Code
33905.0
Location Latitude
Location Longitude
Flow Cont Other Ind
Yes
Flow Cont Other Detail
Lowered Pressure At Supplying Gate From 350 Psi To 250 Psi.
Nrc Rpt Num
Additional Nrc Report Numbers
1369590.0
Commodity Released Type
Natural Gas
Unintentional Release
4797.0
Intentional Release
0.0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Ignite Ind
No
Num Pub Evacuated
0.0
Communication State Fed Ind
Yes
Party Initiated Communication
Operator
Federal
No
Location Type
Utility Right-Of-Way / Easement
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
162.0
Other Underground Facilities
No
Crossing
No
Pipe Facility Type
Investor Owned
System Part Involved
Main
Installation Year
2000.0
Pipe Diameter
8.0
Pipe Specification
Api 5l X52
Pipe Manufacturer
Unknown
Material Involved
Steel
Steel Seam Type
Longitudinal Erw - High Frequency
Wt Steel
0.219
Release Type
Mechanical Puncture
Puncture Axial
0.5
Puncture Circum
0.5
Class Location Type
Class 1 Location
Est Cost Oper Paid
0.0
Est Cost Prop Damage
354400.0
Est Cost Emergency
37000.0
Est Cost Other
0.0
Gas Cost In Mcf
9.0
Est Cost Unintentional Release
43173.0
Est Cost Intentional Release
0.0
Prpty
434573.0
Commercial Affected
0.0
Industrial Affected
0.0
Residences Affected
0.0
Num Persons Hosp Not Ovnght
0.0
Num Injured Treated By Emt
0.0
Num Resident Building Affctd
0.0
Num Business Building Affctd
0.0
Accident Psig
350.0
Normal Psig
350.0
Mop Psig
476.0
Mop Cfr Section
192.619(A)(2)
Maop Established Date
2013-02-15 00:00:00
Accident Pressure
Pressure Did Not Exceed Maop
Gas Odorized System Type
Injection Pump
Gas Odorized Lvl Not Msrd Ind
Yes
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Accident Identifier
Other
Accident Details
Water Department
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
Excavator damage to facility.
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Excavation Damage
Cause Details
Excavation Damage By Third Party
Ex Party Type
Excavation Damage By Third Party
Prior Notification Ind
Yes
One Call System Ind
Yes
State Law Exempt Ind
No
Notify Cga Dirt
No
Public Row Ind
Yes
Public Subtype
State Highway
Excavator Type
Contractor
Excavator Equipment
Drilling
Work Performed
Engineering/surveying
One Call Notified Ind
Yes
One Call Ticket Num
132300796.0
Locator Type
Facility Owner
Visible Marks
Yes
Service Interruption
No
Root Cause Category
Locating Issue
Root Cause Type
Facility Not Marked Due To Incomplete Marks At Damage Location
Preparer Name
I***** J****
Preparer Title
Compliance Analyst
Preparer Email
I******@t*********.com
Preparer Telephone
407-420-6617
Authorizer Name
R****** H*****
Authorizer Title
Manager Pipeline Safety Compliance
Authorizer Telephone
407-420-6667
Authorizer Email
R******@t*********.com
Narrative
On june 7, 2023, at approximately 02:00 hours, pgs was notified that a third-party contractor had struck a gas pipeline at state road 31 & state road 80 in ft myers, florida. Responding crews were dispatched and arrived to find a soil sampling rig was the cause of the damaged pipeline and escaping gas. An assessment was made of the scene, including the ability to safely manage the site. An evaluation of options for the one-way-fed 8" steel pipeline, concluded that the pipeline would remain in service to continually supply approximately 25,300 customers downstream, until a bypass could be installed to isolate the damaged section of pipeline. Over the following days, crews worked to install 750' of 8" steel bypass around the damaged section of pipeline. The bypass was able to isolate the damaged section of pipeline on june 10, 2023, at 13:25, and complete stoppage of the escaping gas. A root cause investigation was concluded and found two primary contributing factors: 1. The gas pipeline in the location of this incident was/is classified as a "high priority subsurface installation (hpsi)" by pgs through the positive response code of "2c". Per florida statue chapter 556 hpsi requires special procedures when digging near an hpsi. With this classification, before any digging or demolition, the excavator must notify the member operator of the start date and time of the excavation. In accordance with f.S. 556, this hpsi was marked by pgs, and a response communicated back to the requesting excavator using a 2c (marked with exceptions: high profile subsurface installation in conflict). The instructions provided and communicated to the excavator indicated, "excavator must notify the member operator of the excavation or demolition start date and time" which the excavator failed to do. In addition, peoples gas also sent an e-mail to the excavator notifying the excavator about the hpsi and requesting the start date and time. The failure by the excavator to notify pgs of the timing of their excavation and the specific location did not allow pgs to give additional location information and specifications related to the pipeline identified as "in conflict". The failure also prevented the possibility of a peoples gas locator being on-site during the excavation. 2. The depth of the pipeline at the damaged location was over thirteen feet deep. When pgs' locator performed the initial locate marking, the locate signal unknowingly jumped off the gas pipeline onto an adjacent telecommunication facility. This caused the locate markings to veer off the gas pipeline by approximately 36" to 48" at the damaged location.
Report Received Date 2023-07-07 00:00:00
Iyear 2023.0
Report Number 20230033.0
Supplemental Number 38576.0
Report Type Supplemental Final
Operator Id 15348 PHMSA Enforcement
Name Peoples Gas System Inc
Operator Street Address Po Box 2562
Operator City Name Tampa
Operator State Abbreviation FL
Operator Postal Code 33601.0
Time Zone Eastern
Daylight Savings Ind Yes
Location Street Address State Road 31 & State Road 80
Location City Name Ft.myers
Location County Name Usa
Location State Abbreviation FL
Location Postal Code 33905.0
Location Latitude 26.7014321 Google Maps OpenStreetMap
Location Longitude -81.7601848 Google Maps OpenStreetMap
Flow Cont Other Ind Yes
Flow Cont Other Detail Lowered Pressure At Supplying Gate From 350 Psi To 250 Psi.
Nrc Rpt Num 1369358.0 NRC Report How to search
Additional Nrc Report Numbers 1369590.0
Commodity Released Type Natural Gas
Unintentional Release 4797.0
Intentional Release 0.0
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Ignite Ind No
Num Pub Evacuated 0.0
Communication State Fed Ind Yes
Party Initiated Communication Operator
Federal No
Location Type Utility Right-Of-Way / Easement
Incident Area Type Underground
Incident Area Subtype Under Soil
Depth Of Cover 162.0
Other Underground Facilities No
Crossing No
Pipe Facility Type Investor Owned
System Part Involved Main
Installation Year 2000.0
Pipe Diameter 8.0
Pipe Specification Api 5l X52
Pipe Manufacturer Unknown
Material Involved Steel
Steel Seam Type Longitudinal Erw - High Frequency
Wt Steel 0.219
Release Type Mechanical Puncture
Puncture Axial 0.5
Puncture Circum 0.5
Class Location Type Class 1 Location
Est Cost Oper Paid 0.0
Est Cost Prop Damage 354400.0
Est Cost Emergency 37000.0
Est Cost Other 0.0
Gas Cost In Mcf 9.0
Est Cost Unintentional Release 43173.0
Est Cost Intentional Release 0.0
Prpty 434573.0
Commercial Affected 0.0
Industrial Affected 0.0
Residences Affected 0.0
Num Persons Hosp Not Ovnght 0.0
Num Injured Treated By Emt 0.0
Num Resident Building Affctd 0.0
Num Business Building Affctd 0.0
Accident Psig 350.0
Normal Psig 350.0
Mop Psig 476.0
Mop Cfr Section 192.619(A)(2) View CFR 49 §192
Maop Established Date 2013-02-15 00:00:00
Accident Pressure Pressure Did Not Exceed Maop
Gas Odorized System Type Injection Pump
Gas Odorized Lvl Not Msrd Ind Yes
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind No
Scada Conf Ind No
Accident Identifier Other
Accident Details Water Department
Investigation Status No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details Excavator damage to facility.
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Excavation Damage
Cause Details Excavation Damage By Third Party
Ex Party Type Excavation Damage By Third Party
Prior Notification Ind Yes
One Call System Ind Yes
State Law Exempt Ind No
Notify Cga Dirt No
Public Row Ind Yes
Public Subtype State Highway
Excavator Type Contractor
Excavator Equipment Drilling
Work Performed Engineering/surveying
One Call Notified Ind Yes
One Call Ticket Num 132300796.0
Locator Type Facility Owner
Visible Marks Yes
Service Interruption No
Root Cause Category Locating Issue
Root Cause Type Facility Not Marked Due To Incomplete Marks At Damage Location
Preparer Name I***** J****
Preparer Title Compliance Analyst
Preparer Email I******@t*********.com
Preparer Telephone 407-420-6617
Authorizer Name R****** H*****
Authorizer Title Manager Pipeline Safety Compliance
Authorizer Telephone 407-420-6667
Authorizer Email R******@t*********.com
Narrative On june 7, 2023, at approximately 02:00 hours, pgs was notified that a third-party contractor had struck a gas pipeline at state road 31 & state road 80 in ft myers, florida. Responding crews were dispatched and arrived to find a soil sampling rig was the cause of the damaged pipeline and escaping gas. An assessment was made of the scene, including the ability to safely manage the site. An evaluation of options for the one-way-fed 8" steel pipeline, concluded that the pipeline would remain in service to continually supply approximately 25,300 customers downstream, until a bypass could be installed to isolate the damaged section of pipeline. Over the following days, crews worked to install 750' of 8" steel bypass around the damaged section of pipeline. The bypass was able to isolate the damaged section of pipeline on june 10, 2023, at 13:25, and complete stoppage of the escaping gas. A root cause investigation was concluded and found two primary contributing factors: 1. The gas pipeline in the location of this incident was/is classified as a "high priority subsurface installation (hpsi)" by pgs through the positive response code of "2c". Per florida statue chapter 556 hpsi requires special procedures when digging near an hpsi. With this classification, before any digging or demolition, the excavator must notify the member operator of the start date and time of the excavation. In accordance with f.S. 556, this hpsi was marked by pgs, and a response communicated back to the requesting excavator using a 2c (marked with exceptions: high profile subsurface installation in conflict). The instructions provided and communicated to the excavator indicated, "excavator must notify the member operator of the excavation or demolition start date and time" which the excavator failed to do. In addition, peoples gas also sent an e-mail to the excavator notifying the excavator about the hpsi and requesting the start date and time. The failure by the excavator to notify pgs of the timing of their excavation and the specific location did not allow pgs to give additional location information and specifications related to the pipeline identified as "in conflict". The failure also prevented the possibility of a peoples gas locator being on-site during the excavation. 2. The depth of the pipeline at the damaged location was over thirteen feet deep. When pgs' locator performed the initial locate marking, the locate signal unknowingly jumped off the gas pipeline onto an adjacent telecommunication facility. This caused the locate markings to veer off the gas pipeline by approximately 36" to 48" at the damaged location.

All rights reserved. Copyright © by ClearPHMSA