HL incident on 2022-10-28 — OK

Operator
Magellan Pipeline Company, Lp
Cause
Incorrect Operation
Commodity
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$4,500
Incident datetime
2022-10-28 11:10
Report number
Location
OK
Narrative
At approximately 10:30am, magellan operations personnel began refilling a pig trap after routine pigging operations. At approximately 11:10am magellan operations personnel noticed product releasing from the sump vent pipe. It was determined the pig trap drain valve leading to the sump was inadvertently left open resulting in product backing up and releasing through the sump vent pipe. Operations were immediately stopped and cleanup activities were initiated. After cleanup activities were completed, the line was placed back into service. To prevent a reoccurrence, 9.01-adm-110 perform pigging operations procedure was reviewed with the affected employee with an emphasis on closing the trap drain valve.
Detailed record list
Report Received Date
2022-11-28 00:00:00
Iyear
2022
Report Number
20220261
Supplemental Number
37386
Report Type
Original Final
Operator Id
Name
Magellan Pipeline Company, Lp
Operator Street Address
100 West 5th Street
Operator City Name
Tulsa
Operator State Abbreviation
OK
Operator Postal Code
74103
Local Datetime
2022-10-28 11:10:00
Time Zone
Central
Daylight Savings Ind
Yes
Location Latitude
Location Longitude
Commodity Released Type
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Commodity Subtype
Gasoline (Non-Ethanol)
Unintentional Release Bbls
0.24
Recovered Bbls
0.12
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Operator Employee
Incident Identified Datetime
2022-10-28 11:10:00
System Part Involved
Onshore Pump/meter Station Equipment And Piping
On Off Shore
Onshore
Status When Identified
Normal Operation, Includes Pauses Between Batches And During Maintenance
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2022-10-28 11:10:00
Restart Datetime
2022-10-28 12:30:00
Communication State Fed Ind
Yes
Party Initiated Communication
Operator
Initial Responder Com Datetime
2022-10-28 12:06:00
On Site Datetime
2022-10-28 11:10:00
Confirmed Discovery Datetime
2022-10-28 11:10:00
Nrc Rpt Num
Nrc Notification Not Required
Ignite Ind
No
Notify Qualified Indiv Ind
Yes
Qualified Indiv Notif Datetime
2022-10-28 11:10:00
Oil Spill Removal Org Ind
No
Num Pub Evacuated
0
Pipe Fac Name
Willmar
Segment Name
780
Onshore State Abbreviation
Mn
Onshore Postal Code
56201
Onshore City Name
Willmar
Onshore County Name
Kandiyohi
Designated Location
Milepost
Designated Name
0
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Aboveground
Incident Area Subtype
Typical Aboveground Facility Piping Or Appurtenance
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Sump
Installation Year
1985
Manufactured Year
1985
Material Involved
Carbon Steel
Release Type
Other
Release Type Details
Valve Misalignment Resulted In Product Going Up The Sump Vent Line, Rather Than Filling The Sump, Causing A Small Amount Of Product To Spray The Ground Surrounding The Sump Vent Pipe.
Wildlife Impact Ind
No
Soil Contamination
No
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
Yes
Usa Drinking Ind
Yes
Usa Drinking Yes No
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
30
Est Cost Prop Damage
4500
Est Cost Emergency
24665
Est Cost Environmental
0
Est Cost Other
0
Prpty
29195
Num Persons Hosp Not Ovnght
0
Num Injured Treated By Emt
0
Num Resident Building Affctd
0
Num Business Building Affctd
0
Accident Psig
10
Mop Psig
275
Mop Cfr Section
Component Design Pressure �195.406(A)(2)
Maop Established Date
1985-01-01 00:00:00
Maop Reversal Flow Ind
No
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
Yes
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
Local operation not tied to ops control.
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Incorrect Operation
Cause Details
Valve Left Or Placed In Wrong Position, But Not Resulting In A Tank, Vessel, Or Sump/separator Overflow Or Facility Overpressure
Operation Type
Valve Left Or Placed In Wrong Position, But Not Resulting In A Tank, Vessel, Or Sump/separator Overflow Or Facility Overpressure
Related Failure Follow Ind
Yes
Category Type
Routine Maintenance
Operator Qualification Ind
Yes
Qualified Individuals
Yes, They Were Qualified For The Task(S)
Io Follow Procedure Ind
Yes
Preparer Name
C******* R******
Preparer Title
Strategic Data Engineer
Preparer Email
C***************@m*********.com
Preparer Telephone
9185747065
Prepared Date
2022-10-28 00:00:00
Authorizer Name
G**** R****
Authorizer Telephone
9185747165
Authorizer Title
Supv. Integrity Mgmt And Regulatory Compliance
Authorizer Email
G**********@m*********.com
Narrative
At approximately 10:30am, magellan operations personnel began refilling a pig trap after routine pigging operations. At approximately 11:10am magellan operations personnel noticed product releasing from the sump vent pipe. It was determined the pig trap drain valve leading to the sump was inadvertently left open resulting in product backing up and releasing through the sump vent pipe. Operations were immediately stopped and cleanup activities were initiated. After cleanup activities were completed, the line was placed back into service. To prevent a reoccurrence, 9.01-adm-110 perform pigging operations procedure was reviewed with the affected employee with an emphasis on closing the trap drain valve.
Report Received Date 2022-11-28 00:00:00
Iyear 2022
Report Number 20220261
Supplemental Number 37386
Report Type Original Final
Operator Id 22610 PHMSA Enforcement
Name Magellan Pipeline Company, Lp
Operator Street Address 100 West 5th Street
Operator City Name Tulsa
Operator State Abbreviation OK
Operator Postal Code 74103
Local Datetime 2022-10-28 11:10:00
Time Zone Central
Daylight Savings Ind Yes
Location Latitude 45.103927 Google Maps OpenStreetMap
Location Longitude -95.082402 Google Maps OpenStreetMap
Commodity Released Type Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Commodity Subtype Gasoline (Non-Ethanol)
Unintentional Release Bbls 0.24
Recovered Bbls 0.12
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Local Operating Personnel, Including Contractors
Operator Type Operator Employee
Incident Identified Datetime 2022-10-28 11:10:00
System Part Involved Onshore Pump/meter Station Equipment And Piping
On Off Shore Onshore
Status When Identified Normal Operation, Includes Pauses Between Batches And During Maintenance
Shutdown Due Accident Ind Yes
Shutdown Datetime 2022-10-28 11:10:00
Restart Datetime 2022-10-28 12:30:00
Communication State Fed Ind Yes
Party Initiated Communication Operator
Initial Responder Com Datetime 2022-10-28 12:06:00
On Site Datetime 2022-10-28 11:10:00
Confirmed Discovery Datetime 2022-10-28 11:10:00
Nrc Rpt Num Nrc Notification Not Required NRC Report How to search
Ignite Ind No
Notify Qualified Indiv Ind Yes
Qualified Indiv Notif Datetime 2022-10-28 11:10:00
Oil Spill Removal Org Ind No
Num Pub Evacuated 0
Pipe Fac Name Willmar
Segment Name 780
Onshore State Abbreviation Mn
Onshore Postal Code 56201
Onshore City Name Willmar
Onshore County Name Kandiyohi
Designated Location Milepost
Designated Name 0
Federal No
Location Type Totally Contained On Operator-Controlled Property
Incident Area Type Aboveground
Incident Area Subtype Typical Aboveground Facility Piping Or Appurtenance
Crossing No
Pipe Facility Type Interstate
Item Involved Sump
Installation Year 1985
Manufactured Year 1985
Material Involved Carbon Steel
Release Type Other
Release Type Details Valve Misalignment Resulted In Product Going Up The Sump Vent Line, Rather Than Filling The Sump, Causing A Small Amount Of Product To Spray The Ground Surrounding The Sump Vent Pipe.
Wildlife Impact Ind No
Soil Contamination No
Long Term Assessment No
Remediation Ind No
Water Contam Ind No
Could Be Hca Yes
Commodity Reached Hca Yes
Usa Drinking Ind Yes
Usa Drinking Yes No Yes
Est Cost Oper Paid 0
Est Cost Gas Released 30
Est Cost Prop Damage 4500
Est Cost Emergency 24665
Est Cost Environmental 0
Est Cost Other 0
Prpty 29195
Num Persons Hosp Not Ovnght 0
Num Injured Treated By Emt 0
Num Resident Building Affctd 0
Num Business Building Affctd 0
Accident Psig 10
Mop Psig 275
Mop Cfr Section Component Design Pressure �195.406(A)(2) View CFR 49 §192
Maop Established Date 1985-01-01 00:00:00
Maop Reversal Flow Ind No
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Pipeline Function > 20% Smys Regulated Transmission
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind No
Scada Conf Ind No
Cpm In Place Ind Yes
Cpm Operating Ind Yes
Cpm Functional Ind Yes
Cpm Detection Ind No
Cpm Conf Ind No
Investigation Status No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details Local operation not tied to ops control.
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Incorrect Operation
Cause Details Valve Left Or Placed In Wrong Position, But Not Resulting In A Tank, Vessel, Or Sump/separator Overflow Or Facility Overpressure
Operation Type Valve Left Or Placed In Wrong Position, But Not Resulting In A Tank, Vessel, Or Sump/separator Overflow Or Facility Overpressure
Related Failure Follow Ind Yes
Category Type Routine Maintenance
Operator Qualification Ind Yes
Qualified Individuals Yes, They Were Qualified For The Task(S)
Io Follow Procedure Ind Yes
Preparer Name C******* R******
Preparer Title Strategic Data Engineer
Preparer Email C***************@m*********.com
Preparer Telephone 9185747065
Prepared Date 2022-10-28 00:00:00
Authorizer Name G**** R****
Authorizer Telephone 9185747165
Authorizer Title Supv. Integrity Mgmt And Regulatory Compliance
Authorizer Email G**********@m*********.com
Narrative At approximately 10:30am, magellan operations personnel began refilling a pig trap after routine pigging operations. At approximately 11:10am magellan operations personnel noticed product releasing from the sump vent pipe. It was determined the pig trap drain valve leading to the sump was inadvertently left open resulting in product backing up and releasing through the sump vent pipe. Operations were immediately stopped and cleanup activities were initiated. After cleanup activities were completed, the line was placed back into service. To prevent a reoccurrence, 9.01-adm-110 perform pigging operations procedure was reviewed with the affected employee with an emphasis on closing the trap drain valve.