HL incident on 2022-09-27 — TX

Operator
Enterprise Products Operating Llc
Cause
Equipment Failure
Commodity
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$500
Incident datetime
2022-09-27 11:45
Report number
Location
TX
Narrative
On september 27, 2022 at 11:45 am, the houston control center (hcc) received a gas detector alarm at the ngl sulphur pump station. The ngl sulphur pump was previously isolated and not in use during the gas detector alarm. Hcc dispatched local personnel to the pump station to investigate the alarm. The pipeline technician arrived on site at 12:20 pm and confirmed a leak on stainless steel tubing near the pump. The technician isolated the tubing leak at 12:30 pm. It was determined that a crack developed in the tubing fitting near the valve manifold on the loutex ngl pump piping. The tubing bracing was found to be loose, allowing tubing to vibrate and crack. The bracing was re-secured so the tubing would not incur any vibration. A station review of all bracing was performed to ensure no other bracing was loose. The pump station was returned to normal operation.
Detailed record list
Report Received Date
2022-10-25 00:00:00
Iyear
2022
Report Number
20220242
Supplemental Number
37279
Report Type
Original Final
Operator Id
Name
Enterprise Products Operating Llc
Operator Street Address
1100 Louisiana Street
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2022-09-27 11:45:00
Time Zone
Central
Daylight Savings Ind
Yes
Location Latitude
Location Longitude
Commodity Released Type
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Commodity Subtype
Gasoline (Non-Ethanol)
Unintentional Release Bbls
14.3
Recovered Bbls
14.3
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Scada-Based Information (Such As Alarm(S), Alert(S), Event(S), And/or Volume Or Pack Calculations)
Incident Identified Datetime
2022-09-27 11:45:00
System Part Involved
Onshore Pump/meter Station Equipment And Piping
On Off Shore
Onshore
Status When Identified
Normal Operation, Includes Pauses Between Batches And During Maintenance
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2022-09-27 12:25:00
Restart Datetime
2022-09-27 15:00:00
Communication State Fed Ind
Yes
Party Initiated Communication
Operator
Initial Responder Com Datetime
2022-09-27 13:05:00
On Site Datetime
2022-09-27 12:20:00
Confirmed Discovery Datetime
2022-09-27 12:20:00
Nrc Rpt Num
Nrc Notification Not Required
Ignite Ind
No
Notify Qualified Indiv Ind
Yes
Qualified Indiv Notif Datetime
2022-09-27 12:30:00
Oil Spill Removal Org Ind
Yes
Osro Activated Datetime
2022-09-27 12:40:00
Osro Arrived On Site Dt
9/27/2022 13:30
Num Pub Evacuated
0
Pipe Fac Name
Loutex Ngl 12"
Segment Name
24740
Onshore State Abbreviation
La
Onshore Postal Code
70663
Onshore City Name
Sulphur
Onshore County Name
Calcasieu
Designated Location
Milepost
Designated Name
102.2
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Aboveground
Incident Area Subtype
Typical Aboveground Facility Piping Or Appurtenance
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Tubing
Tubing Material
Stainless Steel
Tubing Type
Rigid
Installation Year
Unknown
Manufactured Year
Unknown
Material Involved
Material Other Than Carbon Steel
Material Details
Stainless Steel
Release Type
Leak
Leak Type
Connection Failure
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
Yes
High Pop Ind
Yes
High Pop Yes No
Yes
Other Pop Ind
Yes
Other Pop Yes No
Yes
Usa Drinking Ind
Yes
Usa Drinking Yes No
No
Est Cost Oper Paid
0
Est Cost Gas Released
1200
Est Cost Prop Damage
500
Est Cost Emergency
2000
Est Cost Environmental
2500
Est Cost Other
0
Prpty
6200
Num Persons Hosp Not Ovnght
0
Num Injured Treated By Emt
0
Num Resident Building Affctd
0
Num Business Building Affctd
0
Accident Psig
792
Mop Psig
1440
Mop Cfr Section
Component Design Pressure �195.406(A)(2)
Maop Established Date
2020-09-27 00:00:00
Maop Reversal Flow Ind
No
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
Yes
Scada Conf Ind
No
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
Yes
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
This was a stainless-steel tubing failure leak. The controller action did not contribute to the accident.
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Equipment Failure
Cause Details
Defective Or Loose Tubing Or Fitting
Eq Failure Type
Defective Or Loose Tubing Or Fitting
Additional Vibration Ind
Yes
Additional Support Ind
Yes
Preparer Name
N***** G***
Preparer Title
Senior Pipeline Compliance Specialist
Preparer Email
N****@e****.com
Preparer Telephone
985-493-4629
Prepared Date
2022-10-25 00:00:00
Local Contact Name
N***** G***
Local Contact Email
N****@e****.com
Local Contact Telephone
985-493-4629
Authorizer Name
N*** T*****
Authorizer Telephone
713-381-2493
Authorizer Title
Senior Compliance Manager
Authorizer Email
N*******@e****.com
Narrative
On september 27, 2022 at 11:45 am, the houston control center (hcc) received a gas detector alarm at the ngl sulphur pump station. The ngl sulphur pump was previously isolated and not in use during the gas detector alarm. Hcc dispatched local personnel to the pump station to investigate the alarm. The pipeline technician arrived on site at 12:20 pm and confirmed a leak on stainless steel tubing near the pump. The technician isolated the tubing leak at 12:30 pm. It was determined that a crack developed in the tubing fitting near the valve manifold on the loutex ngl pump piping. The tubing bracing was found to be loose, allowing tubing to vibrate and crack. The bracing was re-secured so the tubing would not incur any vibration. A station review of all bracing was performed to ensure no other bracing was loose. The pump station was returned to normal operation.
Report Received Date 2022-10-25 00:00:00
Iyear 2022
Report Number 20220242
Supplemental Number 37279
Report Type Original Final
Operator Id 31618 PHMSA Enforcement
Name Enterprise Products Operating Llc
Operator Street Address 1100 Louisiana Street
Operator City Name Houston
Operator State Abbreviation TX
Operator Postal Code 77002
Local Datetime 2022-09-27 11:45:00
Time Zone Central
Daylight Savings Ind Yes
Location Latitude 30.164776 Google Maps OpenStreetMap
Location Longitude -93.351486 Google Maps OpenStreetMap
Commodity Released Type Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Commodity Subtype Gasoline (Non-Ethanol)
Unintentional Release Bbls 14.3
Recovered Bbls 14.3
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Scada-Based Information (Such As Alarm(S), Alert(S), Event(S), And/or Volume Or Pack Calculations)
Incident Identified Datetime 2022-09-27 11:45:00
System Part Involved Onshore Pump/meter Station Equipment And Piping
On Off Shore Onshore
Status When Identified Normal Operation, Includes Pauses Between Batches And During Maintenance
Shutdown Due Accident Ind Yes
Shutdown Datetime 2022-09-27 12:25:00
Restart Datetime 2022-09-27 15:00:00
Communication State Fed Ind Yes
Party Initiated Communication Operator
Initial Responder Com Datetime 2022-09-27 13:05:00
On Site Datetime 2022-09-27 12:20:00
Confirmed Discovery Datetime 2022-09-27 12:20:00
Nrc Rpt Num Nrc Notification Not Required NRC Report How to search
Ignite Ind No
Notify Qualified Indiv Ind Yes
Qualified Indiv Notif Datetime 2022-09-27 12:30:00
Oil Spill Removal Org Ind Yes
Osro Activated Datetime 2022-09-27 12:40:00
Osro Arrived On Site Dt 9/27/2022 13:30
Num Pub Evacuated 0
Pipe Fac Name Loutex Ngl 12"
Segment Name 24740
Onshore State Abbreviation La
Onshore Postal Code 70663
Onshore City Name Sulphur
Onshore County Name Calcasieu
Designated Location Milepost
Designated Name 102.2
Federal No
Location Type Totally Contained On Operator-Controlled Property
Incident Area Type Aboveground
Incident Area Subtype Typical Aboveground Facility Piping Or Appurtenance
Crossing No
Pipe Facility Type Interstate
Item Involved Tubing
Tubing Material Stainless Steel
Tubing Type Rigid
Installation Year Unknown
Manufactured Year Unknown
Material Involved Material Other Than Carbon Steel
Material Details Stainless Steel
Release Type Leak
Leak Type Connection Failure
Wildlife Impact Ind No
Soil Contamination Yes
Long Term Assessment No
Remediation Ind No
Water Contam Ind No
Could Be Hca Yes
Commodity Reached Hca Yes
High Pop Ind Yes
High Pop Yes No Yes
Other Pop Ind Yes
Other Pop Yes No Yes
Usa Drinking Ind Yes
Usa Drinking Yes No No
Est Cost Oper Paid 0
Est Cost Gas Released 1200
Est Cost Prop Damage 500
Est Cost Emergency 2000
Est Cost Environmental 2500
Est Cost Other 0
Prpty 6200
Num Persons Hosp Not Ovnght 0
Num Injured Treated By Emt 0
Num Resident Building Affctd 0
Num Business Building Affctd 0
Accident Psig 792
Mop Psig 1440
Mop Cfr Section Component Design Pressure �195.406(A)(2) View CFR 49 §192
Maop Established Date 2020-09-27 00:00:00
Maop Reversal Flow Ind No
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Pipeline Function > 20% Smys Regulated Transmission
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind Yes
Scada Conf Ind No
Cpm In Place Ind Yes
Cpm Operating Ind Yes
Cpm Functional Ind Yes
Cpm Detection Ind No
Cpm Conf Ind No
Investigation Status No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details This was a stainless-steel tubing failure leak. The controller action did not contribute to the accident.
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Equipment Failure
Cause Details Defective Or Loose Tubing Or Fitting
Eq Failure Type Defective Or Loose Tubing Or Fitting
Additional Vibration Ind Yes
Additional Support Ind Yes
Preparer Name N***** G***
Preparer Title Senior Pipeline Compliance Specialist
Preparer Email N****@e****.com
Preparer Telephone 985-493-4629
Prepared Date 2022-10-25 00:00:00
Local Contact Name N***** G***
Local Contact Email N****@e****.com
Local Contact Telephone 985-493-4629
Authorizer Name N*** T*****
Authorizer Telephone 713-381-2493
Authorizer Title Senior Compliance Manager
Authorizer Email N*******@e****.com
Narrative On september 27, 2022 at 11:45 am, the houston control center (hcc) received a gas detector alarm at the ngl sulphur pump station. The ngl sulphur pump was previously isolated and not in use during the gas detector alarm. Hcc dispatched local personnel to the pump station to investigate the alarm. The pipeline technician arrived on site at 12:20 pm and confirmed a leak on stainless steel tubing near the pump. The technician isolated the tubing leak at 12:30 pm. It was determined that a crack developed in the tubing fitting near the valve manifold on the loutex ngl pump piping. The tubing bracing was found to be loose, allowing tubing to vibrate and crack. The bracing was re-secured so the tubing would not incur any vibration. A station review of all bracing was performed to ensure no other bracing was loose. The pump station was returned to normal operation.