Incident details
Operator, cause, commodity and consequences with raw source fields.
HL incident on 2022-08-15 — TX
Operator
Centurion Pipeline L.p.
Cause
Corrosion Failure
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$1,200
Incident datetime
2022-08-15 07:35
Report number
Location
TX
Narrative
On august 15, 2022, at approximately 07:35 cst, a centurion pipeline, l.P. (cpl) employee discovered a leak in cpl's midland station near midland, texas. Cpl determined the source of the leak to be station piping and promptly isolated the leak. However, 0.65 barrels of crude oil was released. The contaminated soil will be remediated on site. No injuries, fatalities, or fires were associated with this incident. Cpl reported the leak to the texas railroad commission, office of pipeline safety at 08:16 cst on august 15, 2022, and was issued incident number 2682 in reference to the incident. At the time of this writing, the repair of the station piping is scheduled and the root cause failure analysis will be conducted pending the removal of the damaged piping segment. The resulting information related to the cause of the leak, preventative and mitigative measures (p&m), and costs associated with repairing the station piping will be submitted via supplemental report(s). Supplemental report filed on november 2, 2022: during the root cause failure analysis (rcfa) of midland station's station piping row 4 fill line, cpl determined the cause of the leak to be internal corrosion from under-deposit microbiologically influenced corrosion (mic) that resulted in a through-wall corrosion at the 8 o'clock position of the midland station's station piping row 4 fill line. In the investigation of a previous failure, cpl found that stagnant conditions existing prior to 2019 allowed water and solid to drop out in the station piping, and the presence of bacteria caused mic corrosion cells to form. Cpl finds that this failure is related to the previous failure of the midland station's station piping row 4 fill line that occurred on 08/29/2021. Ongoing p&m measures were previously schedule and are in progress. The replacement of this segment is complete. No further actions are required. Supplemental report filed on november 14, 2022: updated part c. 1 from 'interstate' to 'intrastate.'
Detailed record list
Report Received Date
2022-09-13 00:00:00
Iyear
2022
Report Number
20220211
Supplemental Number
37352
Report Type
Supplemental Final
Operator Id
31888
Name
Centurion Pipeline L.p.
Operator Street Address
1300 Main Street
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2022-08-15 07:35:00
Time Zone
Central
Daylight Savings Ind
Yes
Location Latitude
32.004372
Location Longitude
-102.044083
Commodity Released Type
Crude Oil
Unintentional Release Bbls
0.6
Recovered Bbls
0.6
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Operator Employee
Incident Identified Datetime
2022-08-15 07:35:00
System Part Involved
Onshore Terminal/tank Farm Equipment And Piping
On Off Shore
Onshore
Status When Identified
Idle
Communication State Fed Ind
No
On Site Datetime
2022-08-15 07:35:00
Confirmed Discovery Datetime
2022-08-15 07:45:00
Nrc Rpt Num
Nrc Notification Not Required
Ignite Ind
No
Notify Qualified Indiv Ind
Yes
Qualified Indiv Notif Datetime
2022-08-15 07:46:00
Oil Spill Removal Org Ind
No
Num Pub Evacuated
0
Pipe Fac Name
Midland Station
Segment Name
Row 4 Fill Line
Onshore State Abbreviation
Tx
Onshore Postal Code
79706
Onshore City Name
Not Within A Municipality
Onshore County Name
Midland
Designated Location
Milepost
Designated Name
Midland Sta.
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
24
Crossing
No
Pipe Facility Type
Intrastate
Item Involved
Pipe
Pipe Type
Pipe Body
Puddle Weld Ind
No
Pipe Diameter
8
Pipe Wall Thickness
0.322
Pipe Smys
52000
Pipe Specification
Api 5l X-52
Pipe Seam Type
Erw � Unknown Frequency
Pipe Manufacturer
Unknown
Pipe Coating Type
Coal Tar
Coating Applied Ind
Unknown
Installation Year
2012
Manufactured Year
Unknown
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Pinhole
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
Yes
Soil Remed Ind
Yes
Water Contam Ind
No
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
0
Est Cost Gas Released
46
Est Cost Prop Damage
1200
Est Cost Emergency
3100
Est Cost Environmental
300
Est Cost Other
0
Prpty
4646
Num Persons Hosp Not Ovnght
0
Num Injured Treated By Emt
0
Num Resident Building Affctd
0
Num Business Building Affctd
0
Accident Psig
1
Mop Psig
720
Mop Cfr Section
Subpart E Pressure Test �195.406(A)(3)
Maop Established Date
2021-06-16 00:00:00
Maop Reversal Flow Ind
No
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
No
Cpm In Place Ind
No
Investigation Status
Yes, specify investigation result(s): (select all that apply)
Invest Schedule Ind
Yes
Invest No Control Room Ind
Yes
Invest No Controller Ind
Yes
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Corrosion Failure
Cause Details
Internal Corrosion
Internal External
Internal Corrosion
Int Visual Exam Results
Localized Pitting
Int Water Acid Ind
Yes
Int Field Exam Basis Ind
Yes
Int Low Point Pipe Loc Ind
Yes
Corrosion Inhibitors
Yes
Corrosion Lining
No
Cleaning Dewatering
Not Applicable - Not Mainline Pipe
Corrosion Coupons
Not Applicable - Not Mainline Pipe
Collected Data Ind
No
Has Hydrtst Conduc Before Ind
No
Direct Asmnt Conducted
No
Non Destructive Exam Ind
No
Preparer Name
Y**** T*
Preparer Title
Pipeline Compliance Program Advisor
Preparer Email
Y******@c**********.com
Preparer Telephone
346-803-2718
Prepared Date
2022-11-14 00:00:00
Authorizer Name
T***** D*****
Authorizer Telephone
832-808-9234
Authorizer Title
Compliance Manager
Authorizer Email
T************@c**********.com
Narrative
On august 15, 2022, at approximately 07:35 cst, a centurion pipeline, l.P. (cpl) employee discovered a leak in cpl's midland station near midland, texas. Cpl determined the source of the leak to be station piping and promptly isolated the leak. However, 0.65 barrels of crude oil was released. The contaminated soil will be remediated on site. No injuries, fatalities, or fires were associated with this incident. Cpl reported the leak to the texas railroad commission, office of pipeline safety at 08:16 cst on august 15, 2022, and was issued incident number 2682 in reference to the incident. At the time of this writing, the repair of the station piping is scheduled and the root cause failure analysis will be conducted pending the removal of the damaged piping segment. The resulting information related to the cause of the leak, preventative and mitigative measures (p&m), and costs associated with repairing the station piping will be submitted via supplemental report(s). Supplemental report filed on november 2, 2022: during the root cause failure analysis (rcfa) of midland station's station piping row 4 fill line, cpl determined the cause of the leak to be internal corrosion from under-deposit microbiologically influenced corrosion (mic) that resulted in a through-wall corrosion at the 8 o'clock position of the midland station's station piping row 4 fill line. In the investigation of a previous failure, cpl found that stagnant conditions existing prior to 2019 allowed water and solid to drop out in the station piping, and the presence of bacteria caused mic corrosion cells to form. Cpl finds that this failure is related to the previous failure of the midland station's station piping row 4 fill line that occurred on 08/29/2021. Ongoing p&m measures were previously schedule and are in progress. The replacement of this segment is complete. No further actions are required. Supplemental report filed on november 14, 2022: updated part c. 1 from 'interstate' to 'intrastate.'
| Report Received Date | 2022-09-13 00:00:00 |
|---|---|
| Iyear | 2022 |
| Report Number | 20220211 |
| Supplemental Number | 37352 |
| Report Type | Supplemental Final |
| Operator Id | 31888 PHMSA Enforcement |
| Name | Centurion Pipeline L.p. |
| Operator Street Address | 1300 Main Street |
| Operator City Name | Houston |
| Operator State Abbreviation | TX |
| Operator Postal Code | 77002 |
| Local Datetime | 2022-08-15 07:35:00 |
| Time Zone | Central |
| Daylight Savings Ind | Yes |
| Location Latitude | 32.004372 Google Maps OpenStreetMap |
| Location Longitude | -102.044083 Google Maps OpenStreetMap |
| Commodity Released Type | Crude Oil |
| Unintentional Release Bbls | 0.6 |
| Recovered Bbls | 0.6 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Local Operating Personnel, Including Contractors |
| Operator Type | Operator Employee |
| Incident Identified Datetime | 2022-08-15 07:35:00 |
| System Part Involved | Onshore Terminal/tank Farm Equipment And Piping |
| On Off Shore | Onshore |
| Status When Identified | Idle |
| Communication State Fed Ind | No |
| On Site Datetime | 2022-08-15 07:35:00 |
| Confirmed Discovery Datetime | 2022-08-15 07:45:00 |
| Nrc Rpt Num | Nrc Notification Not Required NRC Report How to search |
| Ignite Ind | No |
| Notify Qualified Indiv Ind | Yes |
| Qualified Indiv Notif Datetime | 2022-08-15 07:46:00 |
| Oil Spill Removal Org Ind | No |
| Num Pub Evacuated | 0 |
| Pipe Fac Name | Midland Station |
| Segment Name | Row 4 Fill Line |
| Onshore State Abbreviation | Tx |
| Onshore Postal Code | 79706 |
| Onshore City Name | Not Within A Municipality |
| Onshore County Name | Midland |
| Designated Location | Milepost |
| Designated Name | Midland Sta. |
| Federal | No |
| Location Type | Totally Contained On Operator-Controlled Property |
| Incident Area Type | Underground |
| Incident Area Subtype | Under Soil |
| Depth Of Cover | 24 |
| Crossing | No |
| Pipe Facility Type | Intrastate |
| Item Involved | Pipe |
| Pipe Type | Pipe Body |
| Puddle Weld Ind | No |
| Pipe Diameter | 8 |
| Pipe Wall Thickness | 0.322 |
| Pipe Smys | 52000 |
| Pipe Specification | Api 5l X-52 |
| Pipe Seam Type | Erw � Unknown Frequency |
| Pipe Manufacturer | Unknown |
| Pipe Coating Type | Coal Tar |
| Coating Applied Ind | Unknown |
| Installation Year | 2012 |
| Manufactured Year | Unknown |
| Material Involved | Carbon Steel |
| Release Type | Leak |
| Leak Type | Pinhole |
| Wildlife Impact Ind | No |
| Soil Contamination | Yes |
| Long Term Assessment | No |
| Remediation Ind | Yes |
| Soil Remed Ind | Yes |
| Water Contam Ind | No |
| Could Be Hca | No |
| Commodity Reached Hca | No |
| Est Cost Oper Paid | 0 |
| Est Cost Gas Released | 46 |
| Est Cost Prop Damage | 1200 |
| Est Cost Emergency | 3100 |
| Est Cost Environmental | 300 |
| Est Cost Other | 0 |
| Prpty | 4646 |
| Num Persons Hosp Not Ovnght | 0 |
| Num Injured Treated By Emt | 0 |
| Num Resident Building Affctd | 0 |
| Num Business Building Affctd | 0 |
| Accident Psig | 1 |
| Mop Psig | 720 |
| Mop Cfr Section | Subpart E Pressure Test �195.406(A)(3) View CFR 49 §192 |
| Maop Established Date | 2021-06-16 00:00:00 |
| Maop Reversal Flow Ind | No |
| Accident Pressure | Pressure Did Not Exceed Mop |
| Pressure Restriction Ind | No |
| Pipeline Function | > 20% Smys Regulated Transmission |
| Scada In Place Ind | No |
| Cpm In Place Ind | No |
| Investigation Status | Yes, specify investigation result(s): (select all that apply) |
| Invest Schedule Ind | Yes |
| Invest No Control Room Ind | Yes |
| Invest No Controller Ind | Yes |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | No |
| Cause | Corrosion Failure |
| Cause Details | Internal Corrosion |
| Internal External | Internal Corrosion |
| Int Visual Exam Results | Localized Pitting |
| Int Water Acid Ind | Yes |
| Int Field Exam Basis Ind | Yes |
| Int Low Point Pipe Loc Ind | Yes |
| Corrosion Inhibitors | Yes |
| Corrosion Lining | No |
| Cleaning Dewatering | Not Applicable - Not Mainline Pipe |
| Corrosion Coupons | Not Applicable - Not Mainline Pipe |
| Collected Data Ind | No |
| Has Hydrtst Conduc Before Ind | No |
| Direct Asmnt Conducted | No |
| Non Destructive Exam Ind | No |
| Preparer Name | Y**** T* |
| Preparer Title | Pipeline Compliance Program Advisor |
| Preparer Email | Y******@c**********.com |
| Preparer Telephone | 346-803-2718 |
| Prepared Date | 2022-11-14 00:00:00 |
| Authorizer Name | T***** D***** |
| Authorizer Telephone | 832-808-9234 |
| Authorizer Title | Compliance Manager |
| Authorizer Email | T************@c**********.com |
| Narrative | On august 15, 2022, at approximately 07:35 cst, a centurion pipeline, l.P. (cpl) employee discovered a leak in cpl's midland station near midland, texas. Cpl determined the source of the leak to be station piping and promptly isolated the leak. However, 0.65 barrels of crude oil was released. The contaminated soil will be remediated on site. No injuries, fatalities, or fires were associated with this incident. Cpl reported the leak to the texas railroad commission, office of pipeline safety at 08:16 cst on august 15, 2022, and was issued incident number 2682 in reference to the incident. At the time of this writing, the repair of the station piping is scheduled and the root cause failure analysis will be conducted pending the removal of the damaged piping segment. The resulting information related to the cause of the leak, preventative and mitigative measures (p&m), and costs associated with repairing the station piping will be submitted via supplemental report(s). Supplemental report filed on november 2, 2022: during the root cause failure analysis (rcfa) of midland station's station piping row 4 fill line, cpl determined the cause of the leak to be internal corrosion from under-deposit microbiologically influenced corrosion (mic) that resulted in a through-wall corrosion at the 8 o'clock position of the midland station's station piping row 4 fill line. In the investigation of a previous failure, cpl found that stagnant conditions existing prior to 2019 allowed water and solid to drop out in the station piping, and the presence of bacteria caused mic corrosion cells to form. Cpl finds that this failure is related to the previous failure of the midland station's station piping row 4 fill line that occurred on 08/29/2021. Ongoing p&m measures were previously schedule and are in progress. The replacement of this segment is complete. No further actions are required. Supplemental report filed on november 14, 2022: updated part c. 1 from 'interstate' to 'intrastate.' |