HL incident on 2022-08-08 — TX

Operator
Enterprise Crude Pipeline Llc
Cause
Equipment Failure
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$5,000
Incident datetime
2022-08-08 12:41
Report number
Location
TX
Narrative
On 8/8/2022 at 12:41 an enterprise pipeline technician discovered a crude oil leak on the s1 prover at cushing east terminal. In response the technician notified local control center to stop the movement and isolated the prover. Approximately 10 barrels of oil reached the ground with no off-site impact. Investigation concluded that the prover shaft failed due to a bending overload. No additional information could be determined regarding the source of overload. The shaft has been replaced and prover has returned to service. Nrc#: 1343875 on 08/08/2022 at 13:39 cdst 48hr nrc#: 1344028 on 08/10/2022 at 08:31 cdst
Detailed record list
Report Received Date
2022-09-06 00:00:00
Iyear
2022
Report Number
20220203
Supplemental Number
37443
Report Type
Supplemental Final
Operator Id
Name
Enterprise Crude Pipeline Llc
Operator Street Address
1100 Louisiana Street
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2022-08-08 13:24:00
Time Zone
Central
Daylight Savings Ind
No
Location Latitude
Location Longitude
Commodity Released Type
Crude Oil
Unintentional Release Bbls
10
Recovered Bbls
10
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Ground Patrol By Operator Or Its Contractor
Operator Type
Operator Employee
Incident Identified Datetime
2022-08-08 12:41:00
System Part Involved
Onshore Pump/meter Station Equipment And Piping
On Off Shore
Onshore
Status When Identified
Normal Operation, Includes Pauses Between Batches And During Maintenance
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2022-08-08 12:42:00
Restart Datetime
2022-09-30 10:00:00
Communication State Fed Ind
No
On Site Datetime
2022-08-08 13:20:00
Confirmed Discovery Datetime
2022-08-08 12:41:00
Nrc Rpt Datetime
2022-08-08 13:39:00
Nrc Rpt Num
Additional Nrc Report Numbers
1344028
Ignite Ind
No
Notify Qualified Indiv Ind
Yes
Qualified Indiv Notif Datetime
2022-08-08 12:44:00
Oil Spill Removal Org Ind
Yes
Osro Activated Datetime
2022-08-08 12:54:00
Osro Arrived On Site Dt
8/8/2022 13:20
Num Pub Evacuated
0
Pipe Fac Name
Cushing East
Segment Name
S1 Prover
Onshore State Abbreviation
Ok
Onshore Postal Code
74023
Onshore City Name
Cushing
Onshore County Name
Lincoln
Designated Location
Milepost
Designated Name
0
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Aboveground
Incident Area Subtype
Typical Aboveground Facility Piping Or Appurtenance
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Meter/prover
Installation Year
1993
Manufactured Year
Unknown
Material Involved
Material Other Than Carbon Steel
Material Details
Stainless Steel
Release Type
Leak
Leak Type
Other
Leak Type Other
Mechanical Shaft Failure
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
No
Est Cost Oper Paid
0
Est Cost Gas Released
1000
Est Cost Prop Damage
5000
Est Cost Emergency
300000
Est Cost Environmental
0
Est Cost Other
0
Prpty
306000
Num Persons Hosp Not Ovnght
0
Num Injured Treated By Emt
0
Num Resident Building Affctd
0
Num Business Building Affctd
0
Accident Psig
142
Mop Psig
275
Mop Cfr Section
Component Design Pressure �195.406(A)(2)
Maop Established Date
1995-01-01 00:00:00
Maop Reversal Flow Ind
No
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
No
Cpm In Place Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
Controller did not impact occurrence of release.
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Equipment Failure
Cause Details
Other Equipment Failure
Eq Failure Type
Other Equipment Failure
Failure Details
Fracture Of Prover Hydraulic Cylinder Rod.
Eq Additional Other Ind
Yes
Eq Additional Other Details
Bending Overload
Preparer Name
R*** T********
Preparer Title
Senior Pipeline Compliance Engineer
Preparer Email
R*********@e****.com
Preparer Telephone
713-381-4659
Prepared Date
2022-12-08 00:00:00
Authorizer Name
R*** T********
Authorizer Telephone
713-381-4659
Authorizer Title
Senior Pipeline Compliance Engineer
Authorizer Email
R*********@e****.com
Narrative
On 8/8/2022 at 12:41 an enterprise pipeline technician discovered a crude oil leak on the s1 prover at cushing east terminal. In response the technician notified local control center to stop the movement and isolated the prover. Approximately 10 barrels of oil reached the ground with no off-site impact. Investigation concluded that the prover shaft failed due to a bending overload. No additional information could be determined regarding the source of overload. The shaft has been replaced and prover has returned to service. Nrc#: 1343875 on 08/08/2022 at 13:39 cdst 48hr nrc#: 1344028 on 08/10/2022 at 08:31 cdst
Report Received Date 2022-09-06 00:00:00
Iyear 2022
Report Number 20220203
Supplemental Number 37443
Report Type Supplemental Final
Operator Id 30829 PHMSA Enforcement
Name Enterprise Crude Pipeline Llc
Operator Street Address 1100 Louisiana Street
Operator City Name Houston
Operator State Abbreviation TX
Operator Postal Code 77002
Local Datetime 2022-08-08 13:24:00
Time Zone Central
Daylight Savings Ind No
Location Latitude 35.940804 Google Maps OpenStreetMap
Location Longitude -96.748678 Google Maps OpenStreetMap
Commodity Released Type Crude Oil
Unintentional Release Bbls 10
Recovered Bbls 10
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Ground Patrol By Operator Or Its Contractor
Operator Type Operator Employee
Incident Identified Datetime 2022-08-08 12:41:00
System Part Involved Onshore Pump/meter Station Equipment And Piping
On Off Shore Onshore
Status When Identified Normal Operation, Includes Pauses Between Batches And During Maintenance
Shutdown Due Accident Ind Yes
Shutdown Datetime 2022-08-08 12:42:00
Restart Datetime 2022-09-30 10:00:00
Communication State Fed Ind No
On Site Datetime 2022-08-08 13:20:00
Confirmed Discovery Datetime 2022-08-08 12:41:00
Nrc Rpt Datetime 2022-08-08 13:39:00
Nrc Rpt Num 1343875 NRC Report How to search
Additional Nrc Report Numbers 1344028
Ignite Ind No
Notify Qualified Indiv Ind Yes
Qualified Indiv Notif Datetime 2022-08-08 12:44:00
Oil Spill Removal Org Ind Yes
Osro Activated Datetime 2022-08-08 12:54:00
Osro Arrived On Site Dt 8/8/2022 13:20
Num Pub Evacuated 0
Pipe Fac Name Cushing East
Segment Name S1 Prover
Onshore State Abbreviation Ok
Onshore Postal Code 74023
Onshore City Name Cushing
Onshore County Name Lincoln
Designated Location Milepost
Designated Name 0
Federal No
Location Type Totally Contained On Operator-Controlled Property
Incident Area Type Aboveground
Incident Area Subtype Typical Aboveground Facility Piping Or Appurtenance
Crossing No
Pipe Facility Type Interstate
Item Involved Meter/prover
Installation Year 1993
Manufactured Year Unknown
Material Involved Material Other Than Carbon Steel
Material Details Stainless Steel
Release Type Leak
Leak Type Other
Leak Type Other Mechanical Shaft Failure
Wildlife Impact Ind No
Soil Contamination Yes
Long Term Assessment No
Remediation Ind No
Water Contam Ind No
Could Be Hca Yes
Commodity Reached Hca No
Est Cost Oper Paid 0
Est Cost Gas Released 1000
Est Cost Prop Damage 5000
Est Cost Emergency 300000
Est Cost Environmental 0
Est Cost Other 0
Prpty 306000
Num Persons Hosp Not Ovnght 0
Num Injured Treated By Emt 0
Num Resident Building Affctd 0
Num Business Building Affctd 0
Accident Psig 142
Mop Psig 275
Mop Cfr Section Component Design Pressure �195.406(A)(2) View CFR 49 §192
Maop Established Date 1995-01-01 00:00:00
Maop Reversal Flow Ind No
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Pipeline Function > 20% Smys Regulated Transmission
Scada In Place Ind No
Cpm In Place Ind No
Investigation Status No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details Controller did not impact occurrence of release.
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Equipment Failure
Cause Details Other Equipment Failure
Eq Failure Type Other Equipment Failure
Failure Details Fracture Of Prover Hydraulic Cylinder Rod.
Eq Additional Other Ind Yes
Eq Additional Other Details Bending Overload
Preparer Name R*** T********
Preparer Title Senior Pipeline Compliance Engineer
Preparer Email R*********@e****.com
Preparer Telephone 713-381-4659
Prepared Date 2022-12-08 00:00:00
Authorizer Name R*** T********
Authorizer Telephone 713-381-4659
Authorizer Title Senior Pipeline Compliance Engineer
Authorizer Email R*********@e****.com
Narrative On 8/8/2022 at 12:41 an enterprise pipeline technician discovered a crude oil leak on the s1 prover at cushing east terminal. In response the technician notified local control center to stop the movement and isolated the prover. Approximately 10 barrels of oil reached the ground with no off-site impact. Investigation concluded that the prover shaft failed due to a bending overload. No additional information could be determined regarding the source of overload. The shaft has been replaced and prover has returned to service. Nrc#: 1343875 on 08/08/2022 at 13:39 cdst 48hr nrc#: 1344028 on 08/10/2022 at 08:31 cdst