HL incident on 2022-08-05 — GA
Operator
Colonial Pipeline Co
Cause
Incorrect Operation
Commodity
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$140,000
Incident datetime
2022-08-05 15:25
Report number
Location
GA
Narrative
On 8/3/2022 tank 837 at greensboro junction experienced a communication issue resulting in the loss of the saab (radar gauging system for the tank). A required reading was issued to local operations on august 2020, which made approval from leadership mandatory to receive product into a tank with a standing communication error. On 8/5/2022 the local operator on shift was preparing for a batch change during line 01 receiving and switched into tank 837 without leadership approval. The operator misread that tank had 9,000 bbls of product when in reality it had 9,000 bbls of available space to the safe fill level. At 15:10 gasoline reached the overflow ports and an estimate of 2.5 bbls was released down the side of the tank. The max fill alarm was never received. Local operations responded immediately in coordination with local first responders. The operator was removed from the desk, and his oq qualifications were revoked. Contractors remained on site to complete additional soil delineation. The max-fill alarm, as well as the saab head have been replaced.
Detailed record list
Report Received Date
2022-09-02 00:00:00
Iyear
2022
Report Number
20220202
Supplemental Number
37277
Report Type
Supplemental Final
Operator Id
2552
Name
Colonial Pipeline Co
Operator Street Address
1000 Lake St.
Operator City Name
Alpharetta
Operator State Abbreviation
GA
Operator Postal Code
30009
Local Datetime
2022-08-05 15:10:00
Time Zone
Eastern
Daylight Savings Ind
Yes
Location Latitude
36.07123064
Location Longitude
-79.93686505
Commodity Released Type
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Commodity Subtype
Gasoline (Non-Ethanol)
Unintentional Release Bbls
2.5
Recovered Bbls
0.1
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Operator Employee
Incident Identified Datetime
2022-08-05 15:25:00
System Part Involved
Onshore Breakout Tank Or Storage Vessel, Including Attached Appurtenances
On Off Shore
Onshore
Status When Identified
Normal Operation, Includes Pauses Between Batches And During Maintenance
Shutdown Due Accident Ind
No
Shutdown Explain
Incident Isolated To Tank.
Communication State Fed Ind
Yes
Party Initiated Communication
Operator
Initial Responder Com Datetime
2022-08-05 15:49:00
On Site Datetime
2022-08-05 15:25:00
Confirmed Discovery Datetime
2022-08-05 15:25:00
Nrc Rpt Datetime
2022-08-05 16:36:00
Nrc Rpt Num
1343659
Additional Nrc Report Numbers
1343702
Ignite Ind
No
Notify Qualified Indiv Ind
No
Oil Spill Removal Org Ind
No
Num Pub Evacuated
0
Pipe Fac Name
Greensboro Junction
Segment Name
Greensboro Junction
Onshore State Abbreviation
Nc
Onshore Postal Code
27409
Onshore City Name
Greensboro
Onshore County Name
Guilford
Designated Location
Survey Station No.
Designated Name
1012
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Tank, Including Attached Appurtenances
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Tank/vessel
Tank Vessel Subtype
Other
Tank Vessel Details
Overflow Vents.
Tank Type
Atmospheric
Safe Fill Level
41.1
Safe Fill Level Exceeded Ind
Yes
Api Std Out Of Service Year
2006
Api Std In Service Year
2019
Installation Year
1963
Manufactured Year
1963
Material Involved
Carbon Steel
Release Type
Overfill Or Overflow
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
Yes
Soil Remed Ind
Yes
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
Yes
High Pop Ind
Yes
High Pop Yes No
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
317
Est Cost Prop Damage
140000
Est Cost Emergency
65300
Est Cost Environmental
325000
Est Cost Other
0
Prpty
530617
Num Persons Hosp Not Ovnght
0
Num Injured Treated By Emt
0
Num Resident Building Affctd
0
Num Business Building Affctd
0
Accident Psig
0
Pressure Restriction Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
No
Investigation Status
Yes, specify investigation result(s): (select all that apply)
Invest Schedule Ind
Yes
Invest Incorrect Action Ind
Yes
Employee Drug Test Ind
Yes
Contractor Drug Test Ind
No
Num Employees Tested
1
Num Employees Failed
0
Cause
Incorrect Operation
Cause Details
Tank, Vessel, Or Sump/separator Allowed Or Caused To Overfill Or Overflow
Operation Type
Tank, Vessel, Or Sump/separator Allowed Or Caused To Overfill Or Overflow
Overflow Other Ind
Incorrect Reference Data/calculation
Related Failure Follow Ind
Yes
Category Type
Normal Operating Conditions
Operator Qualification Ind
Yes
Qualified Individuals
Yes, They Were Qualified For The Task(S)
Eqf Control Releaf Ind
Yes
Preparer Name
D***** L******
Preparer Title
Compliance Coordinator
Preparer Email
D*******@c******.com
Preparer Telephone
4438211456
Prepared Date
2022-10-25 00:00:00
Authorizer Name
Q****** F******
Authorizer Telephone
6787622270
Authorizer Title
Director Pipeline Compliance
Authorizer Email
Q*******@c******.com
Narrative
On 8/3/2022 tank 837 at greensboro junction experienced a communication issue resulting in the loss of the saab (radar gauging system for the tank). A required reading was issued to local operations on august 2020, which made approval from leadership mandatory to receive product into a tank with a standing communication error. On 8/5/2022 the local operator on shift was preparing for a batch change during line 01 receiving and switched into tank 837 without leadership approval. The operator misread that tank had 9,000 bbls of product when in reality it had 9,000 bbls of available space to the safe fill level. At 15:10 gasoline reached the overflow ports and an estimate of 2.5 bbls was released down the side of the tank. The max fill alarm was never received. Local operations responded immediately in coordination with local first responders. The operator was removed from the desk, and his oq qualifications were revoked. Contractors remained on site to complete additional soil delineation. The max-fill alarm, as well as the saab head have been replaced.
| Report Received Date | 2022-09-02 00:00:00 |
|---|---|
| Iyear | 2022 |
| Report Number | 20220202 |
| Supplemental Number | 37277 |
| Report Type | Supplemental Final |
| Operator Id | 2552 PHMSA Enforcement |
| Name | Colonial Pipeline Co |
| Operator Street Address | 1000 Lake St. |
| Operator City Name | Alpharetta |
| Operator State Abbreviation | GA |
| Operator Postal Code | 30009 |
| Local Datetime | 2022-08-05 15:10:00 |
| Time Zone | Eastern |
| Daylight Savings Ind | Yes |
| Location Latitude | 36.07123064 Google Maps OpenStreetMap |
| Location Longitude | -79.93686505 Google Maps OpenStreetMap |
| Commodity Released Type | Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions |
| Commodity Subtype | Gasoline (Non-Ethanol) |
| Unintentional Release Bbls | 2.5 |
| Recovered Bbls | 0.1 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Local Operating Personnel, Including Contractors |
| Operator Type | Operator Employee |
| Incident Identified Datetime | 2022-08-05 15:25:00 |
| System Part Involved | Onshore Breakout Tank Or Storage Vessel, Including Attached Appurtenances |
| On Off Shore | Onshore |
| Status When Identified | Normal Operation, Includes Pauses Between Batches And During Maintenance |
| Shutdown Due Accident Ind | No |
| Shutdown Explain | Incident Isolated To Tank. |
| Communication State Fed Ind | Yes |
| Party Initiated Communication | Operator |
| Initial Responder Com Datetime | 2022-08-05 15:49:00 |
| On Site Datetime | 2022-08-05 15:25:00 |
| Confirmed Discovery Datetime | 2022-08-05 15:25:00 |
| Nrc Rpt Datetime | 2022-08-05 16:36:00 |
| Nrc Rpt Num | 1343659 NRC Report How to search |
| Additional Nrc Report Numbers | 1343702 |
| Ignite Ind | No |
| Notify Qualified Indiv Ind | No |
| Oil Spill Removal Org Ind | No |
| Num Pub Evacuated | 0 |
| Pipe Fac Name | Greensboro Junction |
| Segment Name | Greensboro Junction |
| Onshore State Abbreviation | Nc |
| Onshore Postal Code | 27409 |
| Onshore City Name | Greensboro |
| Onshore County Name | Guilford |
| Designated Location | Survey Station No. |
| Designated Name | 1012 |
| Federal | No |
| Location Type | Totally Contained On Operator-Controlled Property |
| Incident Area Type | Tank, Including Attached Appurtenances |
| Crossing | No |
| Pipe Facility Type | Interstate |
| Item Involved | Tank/vessel |
| Tank Vessel Subtype | Other |
| Tank Vessel Details | Overflow Vents. |
| Tank Type | Atmospheric |
| Safe Fill Level | 41.1 |
| Safe Fill Level Exceeded Ind | Yes |
| Api Std Out Of Service Year | 2006 |
| Api Std In Service Year | 2019 |
| Installation Year | 1963 |
| Manufactured Year | 1963 |
| Material Involved | Carbon Steel |
| Release Type | Overfill Or Overflow |
| Wildlife Impact Ind | No |
| Soil Contamination | Yes |
| Long Term Assessment | No |
| Remediation Ind | Yes |
| Soil Remed Ind | Yes |
| Water Contam Ind | No |
| Could Be Hca | Yes |
| Commodity Reached Hca | Yes |
| High Pop Ind | Yes |
| High Pop Yes No | Yes |
| Est Cost Oper Paid | 0 |
| Est Cost Gas Released | 317 |
| Est Cost Prop Damage | 140000 |
| Est Cost Emergency | 65300 |
| Est Cost Environmental | 325000 |
| Est Cost Other | 0 |
| Prpty | 530617 |
| Num Persons Hosp Not Ovnght | 0 |
| Num Injured Treated By Emt | 0 |
| Num Resident Building Affctd | 0 |
| Num Business Building Affctd | 0 |
| Accident Psig | 0 |
| Pressure Restriction Ind | No |
| Pipeline Function | > 20% Smys Regulated Transmission |
| Scada In Place Ind | Yes |
| Scada Operating Ind | Yes |
| Scada Functional Ind | Yes |
| Scada Detection Ind | No |
| Scada Conf Ind | No |
| Cpm In Place Ind | No |
| Investigation Status | Yes, specify investigation result(s): (select all that apply) |
| Invest Schedule Ind | Yes |
| Invest Incorrect Action Ind | Yes |
| Employee Drug Test Ind | Yes |
| Contractor Drug Test Ind | No |
| Num Employees Tested | 1 |
| Num Employees Failed | 0 |
| Cause | Incorrect Operation |
| Cause Details | Tank, Vessel, Or Sump/separator Allowed Or Caused To Overfill Or Overflow |
| Operation Type | Tank, Vessel, Or Sump/separator Allowed Or Caused To Overfill Or Overflow |
| Overflow Other Ind | Incorrect Reference Data/calculation |
| Related Failure Follow Ind | Yes |
| Category Type | Normal Operating Conditions |
| Operator Qualification Ind | Yes |
| Qualified Individuals | Yes, They Were Qualified For The Task(S) |
| Eqf Control Releaf Ind | Yes |
| Preparer Name | D***** L****** |
| Preparer Title | Compliance Coordinator |
| Preparer Email | D*******@c******.com |
| Preparer Telephone | 4438211456 |
| Prepared Date | 2022-10-25 00:00:00 |
| Authorizer Name | Q****** F****** |
| Authorizer Telephone | 6787622270 |
| Authorizer Title | Director Pipeline Compliance |
| Authorizer Email | Q*******@c******.com |
| Narrative | On 8/3/2022 tank 837 at greensboro junction experienced a communication issue resulting in the loss of the saab (radar gauging system for the tank). A required reading was issued to local operations on august 2020, which made approval from leadership mandatory to receive product into a tank with a standing communication error. On 8/5/2022 the local operator on shift was preparing for a batch change during line 01 receiving and switched into tank 837 without leadership approval. The operator misread that tank had 9,000 bbls of product when in reality it had 9,000 bbls of available space to the safe fill level. At 15:10 gasoline reached the overflow ports and an estimate of 2.5 bbls was released down the side of the tank. The max fill alarm was never received. Local operations responded immediately in coordination with local first responders. The operator was removed from the desk, and his oq qualifications were revoked. Contractors remained on site to complete additional soil delineation. The max-fill alarm, as well as the saab head have been replaced. |