Incident details
Operator, cause, commodity and consequences with raw source fields.
HL incident on 2022-07-21 — TX
Operator
Chevron Pipe Line Co
Cause
Other Outside Force Damage
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$0
Incident datetime
2022-07-21 14:20
Report number
Location
TX
Narrative
At approx. 1420 cdt on 21jul22, while conducting an overflight for the pipeline de-oiling operations of 12" south timbalier 130 pipeline, when a 75-ft by 150-ft, light silver sheen was discovered. It was estimated that less than 0.125 gallons of crude oil released to waters while flushing the pipeline before removal. The release was not recoverable naturally dissipated. At approx. 06:30 on 22jul22, divers began inspecting an area of the 12' south timbalier 130 pipeline near the location of the sheen observed on 21jul22 (nrc report #1342172). Divers discovered a buried section of the pipe approximately 150' south of where the pipe was wrapped around a former caisson. Divers hand jetted approximately 12' below natural bottom without finding the source. Decision was made to stop hand jetting for safety reasons and find round pipe upstream and downstream of the problem area to install slip on flanges to bypass the area. During this time, the divers noted the pipe was severed on the seafloor approximately 300' south of the former caisson (125' from the buried pipe). Before de-oiling operations resumed, slip on flanges were installed upstream (south of the sever) and downstream (north of the former caisson) of the area and the line was de-oiled in two separate operations. The pipeline has been inactive since hurricane ida and was de-oiled over the months of july and august 2022. This release is a continued effort to de-oil pipelines damaged in the gulf of mexico by hurricane ida. All pipelines have remained idle before ida to present activities. Chevron pipe line is continuing investigations into the cause of the severed pipeline.
Detailed record list
Report Received Date
2022-08-19 00:00:00
Iyear
2022
Report Number
20220186
Supplemental Number
37310
Report Type
Supplemental Final
Operator Id
2731
Name
Chevron Pipe Line Co
Operator Street Address
1400 Smith Street
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2022-07-21 14:20:00
Time Zone
Central
Daylight Savings Ind
Yes
Location Latitude
29.043667
Location Longitude
-90.191667
Commodity Released Type
Crude Oil
Unintentional Release Bbls
0.1
Recovered Bbls
0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Air Patrol
Operator Type
Contractor Working For The Operator
Incident Identified Datetime
2022-07-21 14:20:00
System Part Involved
Offshore Pipeline, Including Riser And Riser Bend
On Off Shore
Offshore
Status When Identified
Idle
Communication State Fed Ind
Yes
Party Initiated Communication
Operator
Initial Responder Com Datetime
2022-07-21 15:31:00
On Site Datetime
2022-07-21 14:20:00
Confirmed Discovery Datetime
2022-07-21 14:20:00
Nrc Rpt Datetime
2022-07-21 15:31:00
Nrc Rpt Num
1342172
Additional Nrc Report Numbers
1342324
Ignite Ind
No
Upstream Action Taken
Operational Control
Upstream Oprtnl Cntrl Detail
Pipeline Was Idle During Time Of Release And Was In The Process Of Being De-Oiled.
Downstream Action Taken
Operational Control
Downstream Oprtnl Cntrl Detail
Pipeline Was Idle During Time Of Release And Was In The Process Of Being De-Oiled.
Num Pub Evacuated
0
Pipe Fac Name
St130
Segment Name
Psc 3958
Off Water Depth
40
Off Accident Origin
In State Waters
Offshore State Abbreviation
La
Off Instate Area
Bm3
Off Instate Block
Bm3
Offshore County Name
Lafourche
Off Area Accident Type
Below Water, Pipe On Or Above Seabed
Pipe Facility Type
Interstate
Item Involved
Pipe
Pipe Type
Pipe Body
Puddle Weld Ind
No
Pipe Diameter
12
Pipe Wall Thickness
0.5
Pipe Smys
35000
Pipe Specification
Unknown
Pipe Seam Type
Seamless
Pipe Manufacturer
Unknown
Pipe Coating Type
Other
Pipe Coating Details
Mastic
Coating Applied Ind
No
Installation Year
1971
Manufactured Year
Unknown
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Other
Leak Type Other
Line Appears To Be Severed
Wildlife Impact Ind
No
Soil Contamination
No
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
Yes
Ocean Seawater Ind
Yes
Amount Released
0.1
Rel Water Name
Gulf Of Mexico
Could Be Hca
Yes
Commodity Reached Hca
No
Est Cost Oper Paid
0
Est Cost Gas Released
0
Est Cost Prop Damage
0
Est Cost Emergency
2000
Est Cost Environmental
0
Est Cost Other
0
Prpty
2000
Num Persons Hosp Not Ovnght
0
Num Injured Treated By Emt
0
Num Resident Building Affctd
0
Num Business Building Affctd
0
Accident Psig
0.5
Mop Psig
1400
Mop Cfr Section
Component Design Pressure �195.406(A)(2)
Maop Established Date
2017-03-23 00:00:00
Maop Reversal Flow Ind
No
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
No
Scada Functional Ind
No
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
Line was idle for maintenance during time of release
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Other Outside Force Damage
Cause Details
Other Outside Force Damage
Outside Force Type
Other Outside Force Damage
Osf Other Details
Line's Integrity Was Compromised During Hurricane Ida. During Incident Response, A Diver From A Dsv Noted That The Line Was Flat In This Area And Wrapped Around The Caisson. Subsequent Survey Indicated That The Line Was Still Intact. It Is Chevron's Opinion That The Line Was Severed By An Unknown Source After The Survey Was Performed. Approximately 125' North Of The Sever There Are Indications That A Jackup Had Set Down On The Line.
Preparer Name
G****** S* P*****
Preparer Title
Senior Regulatory Coordinator
Preparer Email
P******@c******.com
Preparer Telephone
8328544596
Prepared Date
2022-11-03 00:00:00
Authorizer Name
G****** S* P*****
Authorizer Telephone
8328544596
Authorizer Title
Senior Regulatory Coordinator
Authorizer Email
P******@c******.com
Narrative
At approx. 1420 cdt on 21jul22, while conducting an overflight for the pipeline de-oiling operations of 12" south timbalier 130 pipeline, when a 75-ft by 150-ft, light silver sheen was discovered. It was estimated that less than 0.125 gallons of crude oil released to waters while flushing the pipeline before removal. The release was not recoverable naturally dissipated. At approx. 06:30 on 22jul22, divers began inspecting an area of the 12' south timbalier 130 pipeline near the location of the sheen observed on 21jul22 (nrc report #1342172). Divers discovered a buried section of the pipe approximately 150' south of where the pipe was wrapped around a former caisson. Divers hand jetted approximately 12' below natural bottom without finding the source. Decision was made to stop hand jetting for safety reasons and find round pipe upstream and downstream of the problem area to install slip on flanges to bypass the area. During this time, the divers noted the pipe was severed on the seafloor approximately 300' south of the former caisson (125' from the buried pipe). Before de-oiling operations resumed, slip on flanges were installed upstream (south of the sever) and downstream (north of the former caisson) of the area and the line was de-oiled in two separate operations. The pipeline has been inactive since hurricane ida and was de-oiled over the months of july and august 2022. This release is a continued effort to de-oil pipelines damaged in the gulf of mexico by hurricane ida. All pipelines have remained idle before ida to present activities. Chevron pipe line is continuing investigations into the cause of the severed pipeline.
| Report Received Date | 2022-08-19 00:00:00 |
|---|---|
| Iyear | 2022 |
| Report Number | 20220186 |
| Supplemental Number | 37310 |
| Report Type | Supplemental Final |
| Operator Id | 2731 PHMSA Enforcement |
| Name | Chevron Pipe Line Co |
| Operator Street Address | 1400 Smith Street |
| Operator City Name | Houston |
| Operator State Abbreviation | TX |
| Operator Postal Code | 77002 |
| Local Datetime | 2022-07-21 14:20:00 |
| Time Zone | Central |
| Daylight Savings Ind | Yes |
| Location Latitude | 29.043667 Google Maps OpenStreetMap |
| Location Longitude | -90.191667 Google Maps OpenStreetMap |
| Commodity Released Type | Crude Oil |
| Unintentional Release Bbls | 0.1 |
| Recovered Bbls | 0 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Air Patrol |
| Operator Type | Contractor Working For The Operator |
| Incident Identified Datetime | 2022-07-21 14:20:00 |
| System Part Involved | Offshore Pipeline, Including Riser And Riser Bend |
| On Off Shore | Offshore |
| Status When Identified | Idle |
| Communication State Fed Ind | Yes |
| Party Initiated Communication | Operator |
| Initial Responder Com Datetime | 2022-07-21 15:31:00 |
| On Site Datetime | 2022-07-21 14:20:00 |
| Confirmed Discovery Datetime | 2022-07-21 14:20:00 |
| Nrc Rpt Datetime | 2022-07-21 15:31:00 |
| Nrc Rpt Num | 1342172 NRC Report How to search |
| Additional Nrc Report Numbers | 1342324 |
| Ignite Ind | No |
| Upstream Action Taken | Operational Control |
| Upstream Oprtnl Cntrl Detail | Pipeline Was Idle During Time Of Release And Was In The Process Of Being De-Oiled. |
| Downstream Action Taken | Operational Control |
| Downstream Oprtnl Cntrl Detail | Pipeline Was Idle During Time Of Release And Was In The Process Of Being De-Oiled. |
| Num Pub Evacuated | 0 |
| Pipe Fac Name | St130 |
| Segment Name | Psc 3958 |
| Off Water Depth | 40 |
| Off Accident Origin | In State Waters |
| Offshore State Abbreviation | La |
| Off Instate Area | Bm3 |
| Off Instate Block | Bm3 |
| Offshore County Name | Lafourche |
| Off Area Accident Type | Below Water, Pipe On Or Above Seabed |
| Pipe Facility Type | Interstate |
| Item Involved | Pipe |
| Pipe Type | Pipe Body |
| Puddle Weld Ind | No |
| Pipe Diameter | 12 |
| Pipe Wall Thickness | 0.5 |
| Pipe Smys | 35000 |
| Pipe Specification | Unknown |
| Pipe Seam Type | Seamless |
| Pipe Manufacturer | Unknown |
| Pipe Coating Type | Other |
| Pipe Coating Details | Mastic |
| Coating Applied Ind | No |
| Installation Year | 1971 |
| Manufactured Year | Unknown |
| Material Involved | Carbon Steel |
| Release Type | Leak |
| Leak Type | Other |
| Leak Type Other | Line Appears To Be Severed |
| Wildlife Impact Ind | No |
| Soil Contamination | No |
| Long Term Assessment | No |
| Remediation Ind | No |
| Water Contam Ind | Yes |
| Ocean Seawater Ind | Yes |
| Amount Released | 0.1 |
| Rel Water Name | Gulf Of Mexico |
| Could Be Hca | Yes |
| Commodity Reached Hca | No |
| Est Cost Oper Paid | 0 |
| Est Cost Gas Released | 0 |
| Est Cost Prop Damage | 0 |
| Est Cost Emergency | 2000 |
| Est Cost Environmental | 0 |
| Est Cost Other | 0 |
| Prpty | 2000 |
| Num Persons Hosp Not Ovnght | 0 |
| Num Injured Treated By Emt | 0 |
| Num Resident Building Affctd | 0 |
| Num Business Building Affctd | 0 |
| Accident Psig | 0.5 |
| Mop Psig | 1400 |
| Mop Cfr Section | Component Design Pressure �195.406(A)(2) View CFR 49 §192 |
| Maop Established Date | 2017-03-23 00:00:00 |
| Maop Reversal Flow Ind | No |
| Accident Pressure | Pressure Did Not Exceed Mop |
| Pressure Restriction Ind | No |
| Internal Inspection Ind | Yes |
| Operation Complications Ind | No |
| Pipeline Function | > 20% Smys Regulated Transmission |
| Scada In Place Ind | Yes |
| Scada Operating Ind | No |
| Scada Functional Ind | No |
| Scada Detection Ind | No |
| Scada Conf Ind | No |
| Cpm In Place Ind | No |
| Investigation Status | No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate) |
| Investigation Status Details | Line was idle for maintenance during time of release |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | No |
| Cause | Other Outside Force Damage |
| Cause Details | Other Outside Force Damage |
| Outside Force Type | Other Outside Force Damage |
| Osf Other Details | Line's Integrity Was Compromised During Hurricane Ida. During Incident Response, A Diver From A Dsv Noted That The Line Was Flat In This Area And Wrapped Around The Caisson. Subsequent Survey Indicated That The Line Was Still Intact. It Is Chevron's Opinion That The Line Was Severed By An Unknown Source After The Survey Was Performed. Approximately 125' North Of The Sever There Are Indications That A Jackup Had Set Down On The Line. |
| Preparer Name | G****** S* P***** |
| Preparer Title | Senior Regulatory Coordinator |
| Preparer Email | P******@c******.com |
| Preparer Telephone | 8328544596 |
| Prepared Date | 2022-11-03 00:00:00 |
| Authorizer Name | G****** S* P***** |
| Authorizer Telephone | 8328544596 |
| Authorizer Title | Senior Regulatory Coordinator |
| Authorizer Email | P******@c******.com |
| Narrative | At approx. 1420 cdt on 21jul22, while conducting an overflight for the pipeline de-oiling operations of 12" south timbalier 130 pipeline, when a 75-ft by 150-ft, light silver sheen was discovered. It was estimated that less than 0.125 gallons of crude oil released to waters while flushing the pipeline before removal. The release was not recoverable naturally dissipated. At approx. 06:30 on 22jul22, divers began inspecting an area of the 12' south timbalier 130 pipeline near the location of the sheen observed on 21jul22 (nrc report #1342172). Divers discovered a buried section of the pipe approximately 150' south of where the pipe was wrapped around a former caisson. Divers hand jetted approximately 12' below natural bottom without finding the source. Decision was made to stop hand jetting for safety reasons and find round pipe upstream and downstream of the problem area to install slip on flanges to bypass the area. During this time, the divers noted the pipe was severed on the seafloor approximately 300' south of the former caisson (125' from the buried pipe). Before de-oiling operations resumed, slip on flanges were installed upstream (south of the sever) and downstream (north of the former caisson) of the area and the line was de-oiled in two separate operations. The pipeline has been inactive since hurricane ida and was de-oiled over the months of july and august 2022. This release is a continued effort to de-oil pipelines damaged in the gulf of mexico by hurricane ida. All pipelines have remained idle before ida to present activities. Chevron pipe line is continuing investigations into the cause of the severed pipeline. |