Incident details
Operator, cause, commodity and consequences with raw source fields.
HL incident on 2022-06-29 — TX
Operator
Enterprise Crude Pipeline Llc
Cause
Incorrect Operation
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$0
Incident datetime
2022-06-29 17:00
Report number
Location
TX
Narrative
On 6/29/2022 at 5:02 pm cst, in preparation for maintenance, operator visually checked the 1" vent line for product. However, the operator only checked the upstream side of the check valve, which was empty, and the operator did not check the downstream side where the pipeline still had product. Once the blind was removed, approximately 0.62 barrels of crude released to the containment area. The leak was stopped by bolting up the flanges; oil was cleaned up from the containment area. To prevent recurrence, an operator was retrained on "first line breaks".
Detailed record list
Report Received Date
2022-07-28 00:00:00
Iyear
2022
Report Number
20220164
Supplemental Number
36911
Report Type
Original Final
Operator Id
30829
Name
Enterprise Crude Pipeline Llc
Operator Street Address
1100 Louisiana Street
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2022-06-29 17:00:00
Time Zone
Central
Daylight Savings Ind
Yes
Location Latitude
29.743056
Location Longitude
-95.128333
Commodity Released Type
Crude Oil
Unintentional Release Bbls
0.62
Recovered Bbls
0.62
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Operator Employee
Incident Identified Datetime
2022-06-29 17:00:00
System Part Involved
Onshore Terminal/tank Farm Equipment And Piping
On Off Shore
Onshore
Status When Identified
Normal Operation, Includes Pauses Between Batches And During Maintenance
Shutdown Due Accident Ind
No
Shutdown Explain
Shut Down Due To A Maintenance Activity
Communication State Fed Ind
No
On Site Datetime
2022-06-29 17:00:00
Confirmed Discovery Datetime
2022-06-29 17:00:00
Nrc Rpt Num
Nrc Notification Not Required
Ignite Ind
No
Notify Qualified Indiv Ind
Yes
Qualified Indiv Notif Datetime
2022-06-29 17:05:00
Oil Spill Removal Org Ind
No
Num Pub Evacuated
0
Pipe Fac Name
Houston Ship Channel
Segment Name
Manifold 400
Onshore State Abbreviation
Tx
Onshore Postal Code
77015
Onshore City Name
Houston
Onshore County Name
Harris
Designated Location
Milepost
Designated Name
Manifold 400
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Aboveground
Incident Area Subtype
Typical Aboveground Facility Piping Or Appurtenance
Crossing
No
Pipe Facility Type
Intrastate
Item Involved
Flange Assembly
Installation Year
Unknown
Manufactured Year
Unknown
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Other
Leak Type Other
Slip Blind Removal Process
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
No
Est Cost Oper Paid
0
Est Cost Gas Released
67
Est Cost Prop Damage
0
Est Cost Emergency
3000
Est Cost Environmental
0
Est Cost Other
0
Prpty
3067
Num Persons Hosp Not Ovnght
0
Num Injured Treated By Emt
0
Num Resident Building Affctd
0
Num Business Building Affctd
0
Accident Psig
0
Mop Psig
285
Mop Cfr Section
Component Design Pressure �195.406(A)(2)
Maop Established Date
2002-01-01 00:00:00
Maop Reversal Flow Ind
No
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
No
Cpm In Place Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
The controller was not involved in an accident.
Employee Drug Test Ind
Yes
Contractor Drug Test Ind
No
Num Employees Tested
1
Num Employees Failed
0
Cause
Incorrect Operation
Cause Details
Other Incorrect Operation
Operation Type
Other Incorrect Operation
Operation Details
Operator Did Not Check The Downstream Side Of The Check Valve Prior To Removing The Blind.
Related Failure Follow Ind
Yes
Category Type
Routine Maintenance
Operator Qualification Ind
Yes
Qualified Individuals
Yes, They Were Qualified For The Task(S)
Preparer Name
Y******* B**
Preparer Title
Pipeline Compliance Engineer
Preparer Email
Y***@e****.com
Preparer Telephone
713-381-5650
Prepared Date
2022-07-28 00:00:00
Local Contact Name
Y******* B**
Local Contact Email
Y***@e****.com
Local Contact Telephone
713-381-5650
Authorizer Name
Y******* B**
Authorizer Telephone
713-381-5650
Authorizer Title
Pipeline Compliance Engineer
Authorizer Email
Y***@e****.com
Narrative
On 6/29/2022 at 5:02 pm cst, in preparation for maintenance, operator visually checked the 1" vent line for product. However, the operator only checked the upstream side of the check valve, which was empty, and the operator did not check the downstream side where the pipeline still had product. Once the blind was removed, approximately 0.62 barrels of crude released to the containment area. The leak was stopped by bolting up the flanges; oil was cleaned up from the containment area. To prevent recurrence, an operator was retrained on "first line breaks".
| Report Received Date | 2022-07-28 00:00:00 |
|---|---|
| Iyear | 2022 |
| Report Number | 20220164 |
| Supplemental Number | 36911 |
| Report Type | Original Final |
| Operator Id | 30829 PHMSA Enforcement |
| Name | Enterprise Crude Pipeline Llc |
| Operator Street Address | 1100 Louisiana Street |
| Operator City Name | Houston |
| Operator State Abbreviation | TX |
| Operator Postal Code | 77002 |
| Local Datetime | 2022-06-29 17:00:00 |
| Time Zone | Central |
| Daylight Savings Ind | Yes |
| Location Latitude | 29.743056 Google Maps OpenStreetMap |
| Location Longitude | -95.128333 Google Maps OpenStreetMap |
| Commodity Released Type | Crude Oil |
| Unintentional Release Bbls | 0.62 |
| Recovered Bbls | 0.62 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Local Operating Personnel, Including Contractors |
| Operator Type | Operator Employee |
| Incident Identified Datetime | 2022-06-29 17:00:00 |
| System Part Involved | Onshore Terminal/tank Farm Equipment And Piping |
| On Off Shore | Onshore |
| Status When Identified | Normal Operation, Includes Pauses Between Batches And During Maintenance |
| Shutdown Due Accident Ind | No |
| Shutdown Explain | Shut Down Due To A Maintenance Activity |
| Communication State Fed Ind | No |
| On Site Datetime | 2022-06-29 17:00:00 |
| Confirmed Discovery Datetime | 2022-06-29 17:00:00 |
| Nrc Rpt Num | Nrc Notification Not Required NRC Report How to search |
| Ignite Ind | No |
| Notify Qualified Indiv Ind | Yes |
| Qualified Indiv Notif Datetime | 2022-06-29 17:05:00 |
| Oil Spill Removal Org Ind | No |
| Num Pub Evacuated | 0 |
| Pipe Fac Name | Houston Ship Channel |
| Segment Name | Manifold 400 |
| Onshore State Abbreviation | Tx |
| Onshore Postal Code | 77015 |
| Onshore City Name | Houston |
| Onshore County Name | Harris |
| Designated Location | Milepost |
| Designated Name | Manifold 400 |
| Federal | No |
| Location Type | Totally Contained On Operator-Controlled Property |
| Incident Area Type | Aboveground |
| Incident Area Subtype | Typical Aboveground Facility Piping Or Appurtenance |
| Crossing | No |
| Pipe Facility Type | Intrastate |
| Item Involved | Flange Assembly |
| Installation Year | Unknown |
| Manufactured Year | Unknown |
| Material Involved | Carbon Steel |
| Release Type | Leak |
| Leak Type | Other |
| Leak Type Other | Slip Blind Removal Process |
| Wildlife Impact Ind | No |
| Soil Contamination | Yes |
| Long Term Assessment | No |
| Remediation Ind | No |
| Water Contam Ind | No |
| Could Be Hca | Yes |
| Commodity Reached Hca | No |
| Est Cost Oper Paid | 0 |
| Est Cost Gas Released | 67 |
| Est Cost Prop Damage | 0 |
| Est Cost Emergency | 3000 |
| Est Cost Environmental | 0 |
| Est Cost Other | 0 |
| Prpty | 3067 |
| Num Persons Hosp Not Ovnght | 0 |
| Num Injured Treated By Emt | 0 |
| Num Resident Building Affctd | 0 |
| Num Business Building Affctd | 0 |
| Accident Psig | 0 |
| Mop Psig | 285 |
| Mop Cfr Section | Component Design Pressure �195.406(A)(2) View CFR 49 §192 |
| Maop Established Date | 2002-01-01 00:00:00 |
| Maop Reversal Flow Ind | No |
| Accident Pressure | Pressure Did Not Exceed Mop |
| Pressure Restriction Ind | No |
| Pipeline Function | > 20% Smys Regulated Transmission |
| Scada In Place Ind | No |
| Cpm In Place Ind | No |
| Investigation Status | No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate) |
| Investigation Status Details | The controller was not involved in an accident. |
| Employee Drug Test Ind | Yes |
| Contractor Drug Test Ind | No |
| Num Employees Tested | 1 |
| Num Employees Failed | 0 |
| Cause | Incorrect Operation |
| Cause Details | Other Incorrect Operation |
| Operation Type | Other Incorrect Operation |
| Operation Details | Operator Did Not Check The Downstream Side Of The Check Valve Prior To Removing The Blind. |
| Related Failure Follow Ind | Yes |
| Category Type | Routine Maintenance |
| Operator Qualification Ind | Yes |
| Qualified Individuals | Yes, They Were Qualified For The Task(S) |
| Preparer Name | Y******* B** |
| Preparer Title | Pipeline Compliance Engineer |
| Preparer Email | Y***@e****.com |
| Preparer Telephone | 713-381-5650 |
| Prepared Date | 2022-07-28 00:00:00 |
| Local Contact Name | Y******* B** |
| Local Contact Email | Y***@e****.com |
| Local Contact Telephone | 713-381-5650 |
| Authorizer Name | Y******* B** |
| Authorizer Telephone | 713-381-5650 |
| Authorizer Title | Pipeline Compliance Engineer |
| Authorizer Email | Y***@e****.com |
| Narrative | On 6/29/2022 at 5:02 pm cst, in preparation for maintenance, operator visually checked the 1" vent line for product. However, the operator only checked the upstream side of the check valve, which was empty, and the operator did not check the downstream side where the pipeline still had product. Once the blind was removed, approximately 0.62 barrels of crude released to the containment area. The leak was stopped by bolting up the flanges; oil was cleaned up from the containment area. To prevent recurrence, an operator was retrained on "first line breaks". |
External Resources
PHMSA pipeline safety insights.
Product
Features
Company