Incident details
Operator, cause, commodity and consequences with raw source fields.
HL incident on 2022-06-29 — TX
Operator
Mid - Valley Pipeline Co
Cause
Other Outside Force Damage
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$150,000
Incident datetime
2022-06-29 12:34
Report number
Location
TX
Narrative
On 6/29/22 at 12:34, operations received a call informing that a 2nd party row mowing contractor had struck the 22-inch abbeville to denver pipeline with a skid steer with mower. The strike caused gouging damage and a through wall penetration of in the pipe. At 12:35, the control room responded by shutting down the upstream pump and blocking in the line with mainline valves upstream at hornsby station and downstream denver station. At 13:35 mainline valve at denver was opened and downstream pumps were started to pull product away from the leak site. At 13:59 mainline valve at denver was closed again. Approximately, 4800 barrels of crude oil was released and nearby horse creek was impacted. Company personnel and oil spill response contractors were mobilized to contain and recover released product. Company set up an incident response team that worked with all federal and state agencies to ensure response, recovery efforts and pipeline repair and restart were completed appropriately. On 6/30/22 at approximately 12:45, a plidco mechanical clamp was installed and on 7/1/22 at 19:02, the line was restarted. Supplemental report: part g updated to other outside force damage - if damage by car, truck, or other motorized vehicle/equipment not engaged in excavation. The type of vehicle involved in the accident was a cat brush cutter, model brx418 industrial. Since type of vehicle cannot be left blank, motorcycle/atv was selected as the best option. 5mph, motorcycle/atv, off road, 0 and "no" selected for questions 7 through 11 respectively at the recommendation of PHMSA aid to more clearly explain accidents of this nature caused by row mowing activities.
Detailed record list
Report Received Date
2022-07-28 00:00:00
Iyear
2022
Report Number
20220162
Supplemental Number
38128
Report Type
Supplemental Final
Operator Id
12470
Name
Mid - Valley Pipeline Co
Operator Street Address
1300 Main Street
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2022-06-29 12:34:00
Time Zone
Central
Daylight Savings Ind
Yes
Location Latitude
35.389943
Location Longitude
-88.628399
Commodity Released Type
Crude Oil
Unintentional Release Bbls
4345
Recovered Bbls
3339
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Contractor Working For The Operator
Incident Identified Datetime
2022-06-29 12:34:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Status When Identified
Normal Operation, Includes Pauses Between Batches And During Maintenance
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2022-06-29 12:39:00
Restart Datetime
2022-07-01 19:02:00
Communication State Fed Ind
Yes
Party Initiated Communication
Operator
Initial Responder Com Datetime
2022-06-29 16:13:00
On Site Datetime
2022-06-29 13:15:00
Confirmed Discovery Datetime
2022-06-29 12:34:00
Nrc Rpt Datetime
2022-06-29 16:15:00
Nrc Rpt Num
1340161
Additional Nrc Report Numbers
1340355
Ignite Ind
No
Upstream Action Taken
Valve Closure
Upstream Valve Close Datetime
2022-06-29 12:58:00
Upstream Valve Type Ind
Remotely Controlled
Downstream Action Taken
Valve Closure
Downstream Vlv Close Datetime
2022-06-29 13:04:00
Downstream Valve Type Ind
Remotely Controlled
Notify Qualified Indiv Ind
Yes
Qualified Indiv Notif Datetime
2022-06-29 12:38:00
Oil Spill Removal Org Ind
Yes
Osro Activated Datetime
2022-06-29 12:42:00
Osro Arrived On Site Dt
6/29/2022 16:30
Num Pub Evacuated
0
Pipe Fac Name
Abbeville To Denver
Segment Name
27001.02 Abbeville To Denver 22-Inch
Onshore State Abbreviation
Tn
Onshore Postal Code
38340
Onshore City Name
Henderson
Onshore County Name
Chester
Designated Location
Milepost
Designated Name
450
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Underground
Incident Area Subtype
Exposed Due To Loss Of Cover
Depth Of Cover
42
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Pipe
Pipe Type
Pipe Body
Puddle Weld Ind
No
Pipe Diameter
22
Pipe Wall Thickness
0.325
Pipe Smys
52000
Pipe Specification
X-52
Pipe Seam Type
Seamless
Pipe Manufacturer
National Tube Supply Co
Pipe Coating Type
Coal Tar
Coating Applied Ind
Yes
Installation Year
1950
Manufactured Year
Unknown
Material Involved
Carbon Steel
Release Type
Mechanical Puncture
Puncture Axial
7
Puncture Circum
1
Wildlife Impact Ind
Yes
Fish Aquatic Impact Ind
Yes
Terrestrial Impact Ind
Yes
Soil Contamination
Yes
Long Term Assessment
Yes
Remediation Ind
Yes
Surface Water Remed Ind
Yes
Groundwater Remed Ind
Yes
Soil Remed Ind
Yes
Water Contam Ind
Yes
Surface Contam Ind
Yes
Groundwater Contam Ind
Yes
Amount Released
3300
Rel Water Name
Horse Creek
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
40000
Est Cost Gas Released
114684
Est Cost Prop Damage
150000
Est Cost Emergency
2251713
Est Cost Environmental
2095000
Est Cost Other
0
Prpty
4651397
Num Persons Hosp Not Ovnght
0
Num Injured Treated By Emt
0
Num Resident Building Affctd
0
Num Business Building Affctd
0
Accident Psig
300
Mop Psig
956
Mop Cfr Section
Component Design Pressure �195.406(A)(2)
Maop Established Date
2018-10-16 00:00:00
Maop Reversal Flow Ind
No
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
343200
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
Yes
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
A review of the accident determined that there were no control room actions that contributed to the event.
Employee Drug Test Ind
No
Contractor Drug Test Ind
Yes
Num Contractors Tested
1
Num Contractors Failed
0
Cause
Other Outside Force Damage
Cause Details
Damage By Car, Truck, Or Other Motorized Vehicle/equipment Not Engaged In Excavation
Outside Force Type
Damage By Car, Truck, Or Other Motorized Vehicle/equipment Not Engaged In Excavation
Vehicle Subtype
Operator's Contractor
Driver Issued Citation Ind
No
Driver In Control Ind
Yes
Estimated Speed
5
Vehicle Type
Motorcycle/atv
Vehicle Travel From
Off-Road
Vehicle Travel Distance Ft
0
Protections Installed Ind
No
Preparer Name
T*** N*******
Preparer Title
Director - Regulatory Compliance
Preparer Email
T************@e*************.com
Preparer Telephone
713-989-7126
Prepared Date
2023-06-02 00:00:00
Authorizer Name
T*** N*******
Authorizer Telephone
713-989-7126
Authorizer Title
Director - Regulatory Compliance
Authorizer Email
T************@e*************.com
Narrative
On 6/29/22 at 12:34, operations received a call informing that a 2nd party row mowing contractor had struck the 22-inch abbeville to denver pipeline with a skid steer with mower. The strike caused gouging damage and a through wall penetration of in the pipe. At 12:35, the control room responded by shutting down the upstream pump and blocking in the line with mainline valves upstream at hornsby station and downstream denver station. At 13:35 mainline valve at denver was opened and downstream pumps were started to pull product away from the leak site. At 13:59 mainline valve at denver was closed again. Approximately, 4800 barrels of crude oil was released and nearby horse creek was impacted. Company personnel and oil spill response contractors were mobilized to contain and recover released product. Company set up an incident response team that worked with all federal and state agencies to ensure response, recovery efforts and pipeline repair and restart were completed appropriately. On 6/30/22 at approximately 12:45, a plidco mechanical clamp was installed and on 7/1/22 at 19:02, the line was restarted. Supplemental report: part g updated to other outside force damage - if damage by car, truck, or other motorized vehicle/equipment not engaged in excavation. The type of vehicle involved in the accident was a cat brush cutter, model brx418 industrial. Since type of vehicle cannot be left blank, motorcycle/atv was selected as the best option. 5mph, motorcycle/atv, off road, 0 and "no" selected for questions 7 through 11 respectively at the recommendation of PHMSA aid to more clearly explain accidents of this nature caused by row mowing activities.
| Report Received Date | 2022-07-28 00:00:00 |
|---|---|
| Iyear | 2022 |
| Report Number | 20220162 |
| Supplemental Number | 38128 |
| Report Type | Supplemental Final |
| Operator Id | 12470 PHMSA Enforcement |
| Name | Mid - Valley Pipeline Co |
| Operator Street Address | 1300 Main Street |
| Operator City Name | Houston |
| Operator State Abbreviation | TX |
| Operator Postal Code | 77002 |
| Local Datetime | 2022-06-29 12:34:00 |
| Time Zone | Central |
| Daylight Savings Ind | Yes |
| Location Latitude | 35.389943 Google Maps OpenStreetMap |
| Location Longitude | -88.628399 Google Maps OpenStreetMap |
| Commodity Released Type | Crude Oil |
| Unintentional Release Bbls | 4345 |
| Recovered Bbls | 3339 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Local Operating Personnel, Including Contractors |
| Operator Type | Contractor Working For The Operator |
| Incident Identified Datetime | 2022-06-29 12:34:00 |
| System Part Involved | Onshore Pipeline, Including Valve Sites |
| On Off Shore | Onshore |
| Status When Identified | Normal Operation, Includes Pauses Between Batches And During Maintenance |
| Shutdown Due Accident Ind | Yes |
| Shutdown Datetime | 2022-06-29 12:39:00 |
| Restart Datetime | 2022-07-01 19:02:00 |
| Communication State Fed Ind | Yes |
| Party Initiated Communication | Operator |
| Initial Responder Com Datetime | 2022-06-29 16:13:00 |
| On Site Datetime | 2022-06-29 13:15:00 |
| Confirmed Discovery Datetime | 2022-06-29 12:34:00 |
| Nrc Rpt Datetime | 2022-06-29 16:15:00 |
| Nrc Rpt Num | 1340161 NRC Report How to search |
| Additional Nrc Report Numbers | 1340355 |
| Ignite Ind | No |
| Upstream Action Taken | Valve Closure |
| Upstream Valve Close Datetime | 2022-06-29 12:58:00 |
| Upstream Valve Type Ind | Remotely Controlled |
| Downstream Action Taken | Valve Closure |
| Downstream Vlv Close Datetime | 2022-06-29 13:04:00 |
| Downstream Valve Type Ind | Remotely Controlled |
| Notify Qualified Indiv Ind | Yes |
| Qualified Indiv Notif Datetime | 2022-06-29 12:38:00 |
| Oil Spill Removal Org Ind | Yes |
| Osro Activated Datetime | 2022-06-29 12:42:00 |
| Osro Arrived On Site Dt | 6/29/2022 16:30 |
| Num Pub Evacuated | 0 |
| Pipe Fac Name | Abbeville To Denver |
| Segment Name | 27001.02 Abbeville To Denver 22-Inch |
| Onshore State Abbreviation | Tn |
| Onshore Postal Code | 38340 |
| Onshore City Name | Henderson |
| Onshore County Name | Chester |
| Designated Location | Milepost |
| Designated Name | 450 |
| Federal | No |
| Location Type | Pipeline Right-Of-Way |
| Incident Area Type | Underground |
| Incident Area Subtype | Exposed Due To Loss Of Cover |
| Depth Of Cover | 42 |
| Crossing | No |
| Pipe Facility Type | Interstate |
| Item Involved | Pipe |
| Pipe Type | Pipe Body |
| Puddle Weld Ind | No |
| Pipe Diameter | 22 |
| Pipe Wall Thickness | 0.325 |
| Pipe Smys | 52000 |
| Pipe Specification | X-52 |
| Pipe Seam Type | Seamless |
| Pipe Manufacturer | National Tube Supply Co |
| Pipe Coating Type | Coal Tar |
| Coating Applied Ind | Yes |
| Installation Year | 1950 |
| Manufactured Year | Unknown |
| Material Involved | Carbon Steel |
| Release Type | Mechanical Puncture |
| Puncture Axial | 7 |
| Puncture Circum | 1 |
| Wildlife Impact Ind | Yes |
| Fish Aquatic Impact Ind | Yes |
| Terrestrial Impact Ind | Yes |
| Soil Contamination | Yes |
| Long Term Assessment | Yes |
| Remediation Ind | Yes |
| Surface Water Remed Ind | Yes |
| Groundwater Remed Ind | Yes |
| Soil Remed Ind | Yes |
| Water Contam Ind | Yes |
| Surface Contam Ind | Yes |
| Groundwater Contam Ind | Yes |
| Amount Released | 3300 |
| Rel Water Name | Horse Creek |
| Could Be Hca | No |
| Commodity Reached Hca | No |
| Est Cost Oper Paid | 40000 |
| Est Cost Gas Released | 114684 |
| Est Cost Prop Damage | 150000 |
| Est Cost Emergency | 2251713 |
| Est Cost Environmental | 2095000 |
| Est Cost Other | 0 |
| Prpty | 4651397 |
| Num Persons Hosp Not Ovnght | 0 |
| Num Injured Treated By Emt | 0 |
| Num Resident Building Affctd | 0 |
| Num Business Building Affctd | 0 |
| Accident Psig | 300 |
| Mop Psig | 956 |
| Mop Cfr Section | Component Design Pressure �195.406(A)(2) View CFR 49 §192 |
| Maop Established Date | 2018-10-16 00:00:00 |
| Maop Reversal Flow Ind | No |
| Accident Pressure | Pressure Did Not Exceed Mop |
| Pressure Restriction Ind | No |
| Length Segment Isolated | 343200 |
| Internal Inspection Ind | Yes |
| Operation Complications Ind | No |
| Pipeline Function | > 20% Smys Regulated Transmission |
| Scada In Place Ind | Yes |
| Scada Operating Ind | Yes |
| Scada Functional Ind | Yes |
| Scada Detection Ind | No |
| Scada Conf Ind | No |
| Cpm In Place Ind | Yes |
| Cpm Operating Ind | Yes |
| Cpm Functional Ind | Yes |
| Cpm Detection Ind | No |
| Cpm Conf Ind | No |
| Investigation Status | No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate) |
| Investigation Status Details | A review of the accident determined that there were no control room actions that contributed to the event. |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | Yes |
| Num Contractors Tested | 1 |
| Num Contractors Failed | 0 |
| Cause | Other Outside Force Damage |
| Cause Details | Damage By Car, Truck, Or Other Motorized Vehicle/equipment Not Engaged In Excavation |
| Outside Force Type | Damage By Car, Truck, Or Other Motorized Vehicle/equipment Not Engaged In Excavation |
| Vehicle Subtype | Operator's Contractor |
| Driver Issued Citation Ind | No |
| Driver In Control Ind | Yes |
| Estimated Speed | 5 |
| Vehicle Type | Motorcycle/atv |
| Vehicle Travel From | Off-Road |
| Vehicle Travel Distance Ft | 0 |
| Protections Installed Ind | No |
| Preparer Name | T*** N******* |
| Preparer Title | Director - Regulatory Compliance |
| Preparer Email | T************@e*************.com |
| Preparer Telephone | 713-989-7126 |
| Prepared Date | 2023-06-02 00:00:00 |
| Authorizer Name | T*** N******* |
| Authorizer Telephone | 713-989-7126 |
| Authorizer Title | Director - Regulatory Compliance |
| Authorizer Email | T************@e*************.com |
| Narrative | On 6/29/22 at 12:34, operations received a call informing that a 2nd party row mowing contractor had struck the 22-inch abbeville to denver pipeline with a skid steer with mower. The strike caused gouging damage and a through wall penetration of in the pipe. At 12:35, the control room responded by shutting down the upstream pump and blocking in the line with mainline valves upstream at hornsby station and downstream denver station. At 13:35 mainline valve at denver was opened and downstream pumps were started to pull product away from the leak site. At 13:59 mainline valve at denver was closed again. Approximately, 4800 barrels of crude oil was released and nearby horse creek was impacted. Company personnel and oil spill response contractors were mobilized to contain and recover released product. Company set up an incident response team that worked with all federal and state agencies to ensure response, recovery efforts and pipeline repair and restart were completed appropriately. On 6/30/22 at approximately 12:45, a plidco mechanical clamp was installed and on 7/1/22 at 19:02, the line was restarted. Supplemental report: part g updated to other outside force damage - if damage by car, truck, or other motorized vehicle/equipment not engaged in excavation. The type of vehicle involved in the accident was a cat brush cutter, model brx418 industrial. Since type of vehicle cannot be left blank, motorcycle/atv was selected as the best option. 5mph, motorcycle/atv, off road, 0 and "no" selected for questions 7 through 11 respectively at the recommendation of PHMSA aid to more clearly explain accidents of this nature caused by row mowing activities. |