Incident details
Operator, cause, commodity and consequences with raw source fields.
HL incident on 2022-06-10 — TX
Operator
Nustar Pipeline Operating Partnership L.p.
Cause
Natural Force Damage
Commodity
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$17,500
Incident datetime
2022-06-10 13:20
Report number
Location
TX
Narrative
At approximately 11:50 am on june 10, 2022, a landowner called the control center and reported fuel on the ground and a diesel odor in a wet area while planting corn. Nustar employees were immediately dispatched to the area to investigate. This is known as line 5, which is a 6-inch interstate refined products line. The line, already shut down per schedule, was immediately blocked in. The leak was confirmed by local personnel onsite upon arrival at 13:20 on june 10, 2022. Agency notifications were made, and repair and cleanup crews were dispatched. The line was excavated on the morning of june 11, 2022, and a pinhole was found, the apparent result of a lightning strike. The metallurgical analysis supported our initial conclusion: "the leak and associated crater contained features consistent with a high energy, short timescale event that resulted in melting and re-solidification. Heat-affected zones containing a narrow band of martensite and adjacent heat-affected zones were observed starting at the outer surface and going all the way down to the hole, which created the leak path. Based on the hole's characteristics, it appears to be a perforation that was apparently created during the high energy event. The event could have resulted from an inadvertent arc generated by a welding tool, or a discharge and arcing between the pipeline and a nearby conductor, (e.G., casing), due to lightning. Based on additional information provided by nustar, lightning storms had been reported prior to the time the leak was discovered, which makes arcing from nearby lightning strikes a logical assumption and the most likely cause for the hole that caused the leak." the line was repaired and returned to service at 01:03 on june 13, 2022. We set up a temporary recovery system at the leak site, and we reclaimed an estimated 102 barrels of free product from the site.
Detailed record list
Report Received Date
2022-07-11 00:00:00
Iyear
2022
Report Number
20220146
Supplemental Number
37657
Report Type
Supplemental Final
Operator Id
10012
Name
Nustar Pipeline Operating Partnership L.p.
Operator Street Address
8111 Westchester Drive
Operator City Name
Dallas
Operator State Abbreviation
TX
Operator Postal Code
75225
Local Datetime
2022-06-10 13:20:00
Time Zone
Central
Daylight Savings Ind
No
Location Latitude
46.62922
Location Longitude
-98.67317
Commodity Released Type
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Commodity Subtype
Diesel, Fuel Oil, Kerosene, Jet Fuel
Unintentional Release Bbls
120
Recovered Bbls
102
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Notification From Public
Incident Identified Datetime
2022-06-10 13:20:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Status When Identified
Normal Operation, Includes Pauses Between Batches And During Maintenance
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2022-06-05 19:56:00
Restart Datetime
2022-06-13 01:03:00
Communication State Fed Ind
Yes
Party Initiated Communication
Operator
Initial Responder Com Datetime
2022-06-10 13:57:00
On Site Datetime
2022-06-10 13:20:00
Confirmed Discovery Datetime
2022-06-10 13:20:00
Nrc Rpt Datetime
2022-06-10 13:57:00
Nrc Rpt Num
1338400
Additional Nrc Report Numbers
1338530
Ignite Ind
No
Upstream Action Taken
Valve Closure
Upstream Valve Close Datetime
2022-06-10 13:20:00
Upstream Valve Type Ind
Automatic
Downstream Action Taken
Valve Closure
Downstream Vlv Close Datetime
2022-06-11 08:32:00
Downstream Valve Type Ind
Remotely Controlled
Notify Qualified Indiv Ind
Yes
Qualified Indiv Notif Datetime
2022-06-10 11:59:00
Oil Spill Removal Org Ind
No
Num Pub Evacuated
0
Pipe Fac Name
Aberdeen To Jamestown
Segment Name
Monango To Jamestown
Onshore State Abbreviation
Nd
Onshore Postal Code
58472
Onshore City Name
Montpelier
Onshore County Name
La Moure
Designated Location
Milepost
Designated Name
149
Federal
No
Location Type
Originated On Operator-Controlled Property, But Then Flowed Or Migrated Off The Property
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
40
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Pipe
Pipe Type
Pipe Body
Puddle Weld Ind
No
Pipe Diameter
6
Pipe Wall Thickness
0.156
Pipe Smys
42000
Pipe Specification
Api 5l - X42
Pipe Seam Type
Erw - High Frequency
Pipe Manufacturer
Textube
Pipe Coating Type
Coal Tar
Coating Applied Ind
Unknown
Installation Year
1965
Manufactured Year
Unknown
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Pinhole
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
Yes
Groundwater Remed Ind
Yes
Soil Remed Ind
Yes
Water Contam Ind
No
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
10000
Est Cost Gas Released
6000
Est Cost Prop Damage
17500
Est Cost Emergency
8000
Est Cost Environmental
100000
Est Cost Other
11500
Est Cost Other Details
Miscellaneous
Prpty
153000
Num Persons Hosp Not Ovnght
0
Num Injured Treated By Emt
0
Num Resident Building Affctd
0
Num Business Building Affctd
0
Accident Psig
398
Mop Psig
1200
Mop Cfr Section
Component Design Pressure �195.406(A)(2)
Maop Established Date
1965-09-12 00:00:00
Maop Reversal Flow Ind
No
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
252384
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
Yes
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
The investigation identified no control room issues the investigation identified no controller issues
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Natural Force Damage
Cause Details
Lightning
Natural Force Type
Lightning
Lightning Subtype
Direct Hit
Nf Extreme Weather Ind
Yes
Nf Other Ind
Yes
Nf Extreme Weather Details
Severe Thunderstorm
Preparer Name
S****** K*** P****
Preparer Title
Pipeline Safety Supervisor
Preparer Email
K*********@n***********.com
Preparer Telephone
13167217053
Prepared Date
2023-02-01 00:00:00
Local Contact Name
J**** H********
Local Contact Email
J**************@n***********.com
Local Contact Telephone
701-730-3539
Authorizer Name
R**** H******
Authorizer Telephone
5732808190
Authorizer Title
General Manager-Pipeline And Terminal Operations
Authorizer Email
R************@n***********.com
Narrative
At approximately 11:50 am on june 10, 2022, a landowner called the control center and reported fuel on the ground and a diesel odor in a wet area while planting corn. Nustar employees were immediately dispatched to the area to investigate. This is known as line 5, which is a 6-inch interstate refined products line. The line, already shut down per schedule, was immediately blocked in. The leak was confirmed by local personnel onsite upon arrival at 13:20 on june 10, 2022. Agency notifications were made, and repair and cleanup crews were dispatched. The line was excavated on the morning of june 11, 2022, and a pinhole was found, the apparent result of a lightning strike. The metallurgical analysis supported our initial conclusion: "the leak and associated crater contained features consistent with a high energy, short timescale event that resulted in melting and re-solidification. Heat-affected zones containing a narrow band of martensite and adjacent heat-affected zones were observed starting at the outer surface and going all the way down to the hole, which created the leak path. Based on the hole's characteristics, it appears to be a perforation that was apparently created during the high energy event. The event could have resulted from an inadvertent arc generated by a welding tool, or a discharge and arcing between the pipeline and a nearby conductor, (e.G., casing), due to lightning. Based on additional information provided by nustar, lightning storms had been reported prior to the time the leak was discovered, which makes arcing from nearby lightning strikes a logical assumption and the most likely cause for the hole that caused the leak." the line was repaired and returned to service at 01:03 on june 13, 2022. We set up a temporary recovery system at the leak site, and we reclaimed an estimated 102 barrels of free product from the site.
| Report Received Date | 2022-07-11 00:00:00 |
|---|---|
| Iyear | 2022 |
| Report Number | 20220146 |
| Supplemental Number | 37657 |
| Report Type | Supplemental Final |
| Operator Id | 10012 PHMSA Enforcement |
| Name | Nustar Pipeline Operating Partnership L.p. |
| Operator Street Address | 8111 Westchester Drive |
| Operator City Name | Dallas |
| Operator State Abbreviation | TX |
| Operator Postal Code | 75225 |
| Local Datetime | 2022-06-10 13:20:00 |
| Time Zone | Central |
| Daylight Savings Ind | No |
| Location Latitude | 46.62922 Google Maps OpenStreetMap |
| Location Longitude | -98.67317 Google Maps OpenStreetMap |
| Commodity Released Type | Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions |
| Commodity Subtype | Diesel, Fuel Oil, Kerosene, Jet Fuel |
| Unintentional Release Bbls | 120 |
| Recovered Bbls | 102 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Notification From Public |
| Incident Identified Datetime | 2022-06-10 13:20:00 |
| System Part Involved | Onshore Pipeline, Including Valve Sites |
| On Off Shore | Onshore |
| Status When Identified | Normal Operation, Includes Pauses Between Batches And During Maintenance |
| Shutdown Due Accident Ind | Yes |
| Shutdown Datetime | 2022-06-05 19:56:00 |
| Restart Datetime | 2022-06-13 01:03:00 |
| Communication State Fed Ind | Yes |
| Party Initiated Communication | Operator |
| Initial Responder Com Datetime | 2022-06-10 13:57:00 |
| On Site Datetime | 2022-06-10 13:20:00 |
| Confirmed Discovery Datetime | 2022-06-10 13:20:00 |
| Nrc Rpt Datetime | 2022-06-10 13:57:00 |
| Nrc Rpt Num | 1338400 NRC Report How to search |
| Additional Nrc Report Numbers | 1338530 |
| Ignite Ind | No |
| Upstream Action Taken | Valve Closure |
| Upstream Valve Close Datetime | 2022-06-10 13:20:00 |
| Upstream Valve Type Ind | Automatic |
| Downstream Action Taken | Valve Closure |
| Downstream Vlv Close Datetime | 2022-06-11 08:32:00 |
| Downstream Valve Type Ind | Remotely Controlled |
| Notify Qualified Indiv Ind | Yes |
| Qualified Indiv Notif Datetime | 2022-06-10 11:59:00 |
| Oil Spill Removal Org Ind | No |
| Num Pub Evacuated | 0 |
| Pipe Fac Name | Aberdeen To Jamestown |
| Segment Name | Monango To Jamestown |
| Onshore State Abbreviation | Nd |
| Onshore Postal Code | 58472 |
| Onshore City Name | Montpelier |
| Onshore County Name | La Moure |
| Designated Location | Milepost |
| Designated Name | 149 |
| Federal | No |
| Location Type | Originated On Operator-Controlled Property, But Then Flowed Or Migrated Off The Property |
| Incident Area Type | Underground |
| Incident Area Subtype | Under Soil |
| Depth Of Cover | 40 |
| Crossing | No |
| Pipe Facility Type | Interstate |
| Item Involved | Pipe |
| Pipe Type | Pipe Body |
| Puddle Weld Ind | No |
| Pipe Diameter | 6 |
| Pipe Wall Thickness | 0.156 |
| Pipe Smys | 42000 |
| Pipe Specification | Api 5l - X42 |
| Pipe Seam Type | Erw - High Frequency |
| Pipe Manufacturer | Textube |
| Pipe Coating Type | Coal Tar |
| Coating Applied Ind | Unknown |
| Installation Year | 1965 |
| Manufactured Year | Unknown |
| Material Involved | Carbon Steel |
| Release Type | Leak |
| Leak Type | Pinhole |
| Wildlife Impact Ind | No |
| Soil Contamination | Yes |
| Long Term Assessment | No |
| Remediation Ind | Yes |
| Groundwater Remed Ind | Yes |
| Soil Remed Ind | Yes |
| Water Contam Ind | No |
| Could Be Hca | No |
| Commodity Reached Hca | No |
| Est Cost Oper Paid | 10000 |
| Est Cost Gas Released | 6000 |
| Est Cost Prop Damage | 17500 |
| Est Cost Emergency | 8000 |
| Est Cost Environmental | 100000 |
| Est Cost Other | 11500 |
| Est Cost Other Details | Miscellaneous |
| Prpty | 153000 |
| Num Persons Hosp Not Ovnght | 0 |
| Num Injured Treated By Emt | 0 |
| Num Resident Building Affctd | 0 |
| Num Business Building Affctd | 0 |
| Accident Psig | 398 |
| Mop Psig | 1200 |
| Mop Cfr Section | Component Design Pressure �195.406(A)(2) View CFR 49 §192 |
| Maop Established Date | 1965-09-12 00:00:00 |
| Maop Reversal Flow Ind | No |
| Accident Pressure | Pressure Did Not Exceed Mop |
| Pressure Restriction Ind | No |
| Length Segment Isolated | 252384 |
| Internal Inspection Ind | Yes |
| Operation Complications Ind | No |
| Pipeline Function | > 20% Smys Regulated Transmission |
| Scada In Place Ind | Yes |
| Scada Operating Ind | Yes |
| Scada Functional Ind | Yes |
| Scada Detection Ind | No |
| Scada Conf Ind | No |
| Cpm In Place Ind | Yes |
| Cpm Operating Ind | Yes |
| Cpm Functional Ind | Yes |
| Cpm Detection Ind | No |
| Cpm Conf Ind | No |
| Investigation Status | No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate) |
| Investigation Status Details | The investigation identified no control room issues the investigation identified no controller issues |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | No |
| Cause | Natural Force Damage |
| Cause Details | Lightning |
| Natural Force Type | Lightning |
| Lightning Subtype | Direct Hit |
| Nf Extreme Weather Ind | Yes |
| Nf Other Ind | Yes |
| Nf Extreme Weather Details | Severe Thunderstorm |
| Preparer Name | S****** K*** P**** |
| Preparer Title | Pipeline Safety Supervisor |
| Preparer Email | K*********@n***********.com |
| Preparer Telephone | 13167217053 |
| Prepared Date | 2023-02-01 00:00:00 |
| Local Contact Name | J**** H******** |
| Local Contact Email | J**************@n***********.com |
| Local Contact Telephone | 701-730-3539 |
| Authorizer Name | R**** H****** |
| Authorizer Telephone | 5732808190 |
| Authorizer Title | General Manager-Pipeline And Terminal Operations |
| Authorizer Email | R************@n***********.com |
| Narrative | At approximately 11:50 am on june 10, 2022, a landowner called the control center and reported fuel on the ground and a diesel odor in a wet area while planting corn. Nustar employees were immediately dispatched to the area to investigate. This is known as line 5, which is a 6-inch interstate refined products line. The line, already shut down per schedule, was immediately blocked in. The leak was confirmed by local personnel onsite upon arrival at 13:20 on june 10, 2022. Agency notifications were made, and repair and cleanup crews were dispatched. The line was excavated on the morning of june 11, 2022, and a pinhole was found, the apparent result of a lightning strike. The metallurgical analysis supported our initial conclusion: "the leak and associated crater contained features consistent with a high energy, short timescale event that resulted in melting and re-solidification. Heat-affected zones containing a narrow band of martensite and adjacent heat-affected zones were observed starting at the outer surface and going all the way down to the hole, which created the leak path. Based on the hole's characteristics, it appears to be a perforation that was apparently created during the high energy event. The event could have resulted from an inadvertent arc generated by a welding tool, or a discharge and arcing between the pipeline and a nearby conductor, (e.G., casing), due to lightning. Based on additional information provided by nustar, lightning storms had been reported prior to the time the leak was discovered, which makes arcing from nearby lightning strikes a logical assumption and the most likely cause for the hole that caused the leak." the line was repaired and returned to service at 01:03 on june 13, 2022. We set up a temporary recovery system at the leak site, and we reclaimed an estimated 102 barrels of free product from the site. |