Incident details
Operator, cause, commodity and consequences with raw source fields.
GD incident on 2022-01-08 — WV
Operator
Dominion Energy West Virginia
Cause
Equipment Failure
Commodity
Natural Gas
Program
GD
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$0
Incident datetime
2022-01-08 11:00
Report number
Location
WV, GILMER
Narrative
On 1/8/2022, dewv personnel were monitoring system pressures because of cold weather. In the course of doing this, they identified a pressure increase from 8 ounces to 10 ounces at 11:00 hours; and another increase from 10 ounces to 35 ounces at 12:00 hours. The pressure returned to 8 ounces at 13:00 hours, which is believed to be from an increase in temperature relieving moisture and ice from the regulators. During the event, a leak was discovered on a mainline. Three regulating stations that feed the system were shut in, creating an outage for 162 customers. The mainline leak was repaired, the system was leak surveyed with no additional hazardous leaks found, and safety checks and restoration of customers were initiated beginning on the morning of 1/9/2022.
Detailed record list
Occurred At
2022-01-08 11:00:00
Year
2022
Report Received Date
2022-02-07 00:00:00
Iyear
2022.0
Report Number
20220008.0
Supplemental Number
36717.0
Report Type
Supplemental Final
Operator Id
7348
Name
Dominion Energy West Virginia
Operator Street Address
781 Chestnut Ridge Rd
Operator City Name
Morgantown
Operator State Abbreviation
WV
Operator Postal Code
26505
Local Datetime
2022-01-08 20:00:00
Time Zone
Eastern
Daylight Savings Ind
No
Location Street Address
305 Powell Street
Location City Name
Glenville
Location County Name
Gilmer
Location State Abbreviation
WV
Location Postal Code
26351
Location Latitude
38.932673
Location Longitude
-80.83713
Flow Cont Main Valve Ind
Yes
Nrc Rpt Datetime
2022-01-08 21:10:00
Nrc Rpt Num
1326175
Additional Nrc Report Numbers
1326260
Commodity Released Type
Natural Gas
Unintentional Release
7446.0
Intentional Release
4265.0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Ignite Ind
No
Num Pub Evacuated
0.0
Incident Identified Datetime
2022-01-08 11:00:00
Communication State Fed Ind
Yes
Party Initiated Communication
Local/state/federal Emergency Responder
Initial Responder Com Datetime
2022-01-08 12:00:00
On Site Datetime
2022-01-08 12:30:00
Federal
No
Location Type
Public Property
Incident Area Type
Underground
Incident Area Subtype
Under Pavement
Depth Of Cover
30.0
Other Underground Facilities
No
Crossing
No
Pipe Facility Type
Investor Owned
System Part Involved
Main
Installation Year
1947.0
Pipe Diameter
3.0
Pipe Specification
Unknown
Pipe Manufacturer
Unknown
Material Involved
Steel
Steel Seam Type
Other
Steel Seam Type Details
Unknown
Release Type
Leak
Leak Type
Pinhole
Class Location Type
Class 3 Location
Est Cost Oper Paid
116531.0
Est Cost Prop Damage
0.0
Est Cost Emergency
66638.0
Est Cost Other
0.0
Gas Cost In Mcf
3.361
Est Cost Unintentional Release
25026.0
Est Cost Intentional Release
14335.0
Prpty
222530.0
Commercial Affected
51.0
Industrial Affected
0.0
Residences Affected
111.0
Num Persons Hosp Not Ovnght
0.0
Num Injured Treated By Emt
0.0
Num Resident Building Affctd
111.0
Num Business Building Affctd
51.0
Accident Psig
2.18
Normal Psig
0.5
Mop Psig
0.75
Mop Cfr Section
192.623
Maop Established Date
1947-11-08 00:00:00
Accident Pressure
Pressure Exceeded The Applicable Allowance In 192.201
Gas Odorized System Type
Odorized By Others
Gas Odorized Lvl Not Msrd Ind
Yes
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
Yes
Scada Conf Ind
Yes
Accident Identifier
Scada-Based Information (Such As Alarm(S), Alert(S), Event(S), And/or Volume Or Pack Calculations)
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
Operations personnel were already monitoring system pressures due to cold weather and were aware of the event.
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Equipment Failure
Cause Details
Malfunction Of Control/relief Equipment
Eq Failure Type
Malfunction Of Control/relief Equipment
Pressure Regulator Ind
Yes
Nf Temperature Ind
Yes
Nf Snow Ice Ind
Yes
Preparer Name
C****** M********
Preparer Title
Gas Pipeline Compliance Analyst
Preparer Email
C******************@d*************.com
Preparer Telephone
3046769284
Local Contact Name
C****** M********
Local Contact Email
C******************@d*************.com
Local Contact Telephone
3046769284
Authorizer Name
C**** H****
Authorizer Title
Manager- Gas Operations Pipeline Integrity
Authorizer Telephone
3304379557
Authorizer Email
C************@d*************.com
Narrative
On 1/8/2022, dewv personnel were monitoring system pressures because of cold weather. In the course of doing this, they identified a pressure increase from 8 ounces to 10 ounces at 11:00 hours; and another increase from 10 ounces to 35 ounces at 12:00 hours. The pressure returned to 8 ounces at 13:00 hours, which is believed to be from an increase in temperature relieving moisture and ice from the regulators. During the event, a leak was discovered on a mainline. Three regulating stations that feed the system were shut in, creating an outage for 162 customers. The mainline leak was repaired, the system was leak surveyed with no additional hazardous leaks found, and safety checks and restoration of customers were initiated beginning on the morning of 1/9/2022.
| Occurred At | 2022-01-08 11:00:00 |
|---|---|
| Year | 2022 |
| Report Received Date | 2022-02-07 00:00:00 |
| Iyear | 2022.0 |
| Report Number | 20220008.0 |
| Supplemental Number | 36717.0 |
| Report Type | Supplemental Final |
| Operator Id | 7348 PHMSA Enforcement |
| Name | Dominion Energy West Virginia |
| Operator Street Address | 781 Chestnut Ridge Rd |
| Operator City Name | Morgantown |
| Operator State Abbreviation | WV |
| Operator Postal Code | 26505 |
| Local Datetime | 2022-01-08 20:00:00 |
| Time Zone | Eastern |
| Daylight Savings Ind | No |
| Location Street Address | 305 Powell Street |
| Location City Name | Glenville |
| Location County Name | Gilmer |
| Location State Abbreviation | WV |
| Location Postal Code | 26351 |
| Location Latitude | 38.932673 Google Maps OpenStreetMap |
| Location Longitude | -80.83713 Google Maps OpenStreetMap |
| Flow Cont Main Valve Ind | Yes |
| Nrc Rpt Datetime | 2022-01-08 21:10:00 |
| Nrc Rpt Num | 1326175 NRC Report How to search |
| Additional Nrc Report Numbers | 1326260 |
| Commodity Released Type | Natural Gas |
| Unintentional Release | 7446.0 |
| Intentional Release | 4265.0 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Ignite Ind | No |
| Num Pub Evacuated | 0.0 |
| Incident Identified Datetime | 2022-01-08 11:00:00 |
| Communication State Fed Ind | Yes |
| Party Initiated Communication | Local/state/federal Emergency Responder |
| Initial Responder Com Datetime | 2022-01-08 12:00:00 |
| On Site Datetime | 2022-01-08 12:30:00 |
| Federal | No |
| Location Type | Public Property |
| Incident Area Type | Underground |
| Incident Area Subtype | Under Pavement |
| Depth Of Cover | 30.0 |
| Other Underground Facilities | No |
| Crossing | No |
| Pipe Facility Type | Investor Owned |
| System Part Involved | Main |
| Installation Year | 1947.0 |
| Pipe Diameter | 3.0 |
| Pipe Specification | Unknown |
| Pipe Manufacturer | Unknown |
| Material Involved | Steel |
| Steel Seam Type | Other |
| Steel Seam Type Details | Unknown |
| Release Type | Leak |
| Leak Type | Pinhole |
| Class Location Type | Class 3 Location |
| Est Cost Oper Paid | 116531.0 |
| Est Cost Prop Damage | 0.0 |
| Est Cost Emergency | 66638.0 |
| Est Cost Other | 0.0 |
| Gas Cost In Mcf | 3.361 |
| Est Cost Unintentional Release | 25026.0 |
| Est Cost Intentional Release | 14335.0 |
| Prpty | 222530.0 |
| Commercial Affected | 51.0 |
| Industrial Affected | 0.0 |
| Residences Affected | 111.0 |
| Num Persons Hosp Not Ovnght | 0.0 |
| Num Injured Treated By Emt | 0.0 |
| Num Resident Building Affctd | 111.0 |
| Num Business Building Affctd | 51.0 |
| Accident Psig | 2.18 |
| Normal Psig | 0.5 |
| Mop Psig | 0.75 |
| Mop Cfr Section | 192.623 View CFR 49 §192 |
| Maop Established Date | 1947-11-08 00:00:00 |
| Accident Pressure | Pressure Exceeded The Applicable Allowance In 192.201 |
| Gas Odorized System Type | Odorized By Others |
| Gas Odorized Lvl Not Msrd Ind | Yes |
| Scada In Place Ind | Yes |
| Scada Operating Ind | Yes |
| Scada Functional Ind | Yes |
| Scada Detection Ind | Yes |
| Scada Conf Ind | Yes |
| Accident Identifier | Scada-Based Information (Such As Alarm(S), Alert(S), Event(S), And/or Volume Or Pack Calculations) |
| Investigation Status | No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate) |
| Investigation Status Details | Operations personnel were already monitoring system pressures due to cold weather and were aware of the event. |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | No |
| Cause | Equipment Failure |
| Cause Details | Malfunction Of Control/relief Equipment |
| Eq Failure Type | Malfunction Of Control/relief Equipment |
| Pressure Regulator Ind | Yes |
| Nf Temperature Ind | Yes |
| Nf Snow Ice Ind | Yes |
| Preparer Name | C****** M******** |
| Preparer Title | Gas Pipeline Compliance Analyst |
| Preparer Email | C******************@d*************.com |
| Preparer Telephone | 3046769284 |
| Local Contact Name | C****** M******** |
| Local Contact Email | C******************@d*************.com |
| Local Contact Telephone | 3046769284 |
| Authorizer Name | C**** H**** |
| Authorizer Title | Manager- Gas Operations Pipeline Integrity |
| Authorizer Telephone | 3304379557 |
| Authorizer Email | C************@d*************.com |
| Narrative | On 1/8/2022, dewv personnel were monitoring system pressures because of cold weather. In the course of doing this, they identified a pressure increase from 8 ounces to 10 ounces at 11:00 hours; and another increase from 10 ounces to 35 ounces at 12:00 hours. The pressure returned to 8 ounces at 13:00 hours, which is believed to be from an increase in temperature relieving moisture and ice from the regulators. During the event, a leak was discovered on a mainline. Three regulating stations that feed the system were shut in, creating an outage for 162 customers. The mainline leak was repaired, the system was leak surveyed with no additional hazardous leaks found, and safety checks and restoration of customers were initiated beginning on the morning of 1/9/2022. |