Incident details
Operator, cause, commodity and consequences with raw source fields.
HL incident on 2021-11-04 — TX
Operator
Plains Pipeline, L.p.
Cause
Corrosion Failure
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$10,009
Incident datetime
2021-11-04 17:04
Report number
Location
TX
Narrative
Approximately 165 barrels of crude oil were released from the pump 9 discharge station piping at china grove station. The date and time of the release (part a q4) is indicative of the earliest possible time the release could have started, as it was the date/time that the pump had started. The cause of the release was attributed to external corrosion as a result of stay current inference. To prevent future incidents, an interrupted close interval cathodic protection survey will be performed to determine the cause of the stray current and ensure that other facility piping does not have stray current interference. Supplemental narrative: updated the nominal diameter of the failed section of pipe to 10" (part c q3.A). Supplemental narrative (2): the cause of the release was attributed to external corrosion, likely from stay current inference as indicated by the pit morphology. The type of stray current interference is not known (part g1 q2a). To prevent future incidents, a cis survey was conducted and results indicated that the incident location met criteria. Additionally, in 2022, non-destructive testing inspections will be conducted for select pipeline segments within the facility.
Detailed record list
Report Received Date
2021-12-03 00:00:00
Iyear
2021
Report Number
20210340
Supplemental Number
36602
Report Type
Supplemental Final
Operator Id
Name
Plains Pipeline, L.p.
Operator Street Address
333 Clay Street, Suite 1900
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2021-11-04 16:30:00
Time Zone
Central
Daylight Savings Ind
Yes
Location Latitude
32.5320273
Location Longitude
-100.8419713
Commodity Released Type
Crude Oil
Unintentional Release Bbls
165
Recovered Bbls
165
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Notification From Public
Incident Identified Datetime
2021-11-04 17:04:00
System Part Involved
Onshore Terminal/tank Farm Equipment And Piping
On Off Shore
Onshore
Status When Identified
Idle
Communication State Fed Ind
Yes
Party Initiated Communication
Operator
Initial Responder Com Datetime
2021-11-04 18:21:00
On Site Datetime
2021-11-04 17:30:00
Confirmed Discovery Datetime
2021-11-04 17:30:00
Nrc Rpt Num
Nrc Notification Not Required
Ignite Ind
No
Notify Qualified Indiv Ind
Yes
Qualified Indiv Notif Datetime
2021-11-04 17:30:00
Oil Spill Removal Org Ind
No
Num Pub Evacuated
0
Pipe Fac Name
China Grove
Segment Name
China Grove Station Piping - Pump 9 Discharge
Onshore State Abbreviation
Tx
Onshore Postal Code
79526
Onshore City Name
Hermleigh
Onshore County Name
Scurry
Designated Location
Milepost
Designated Name
0+00
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
48
Crossing
No
Pipe Facility Type
Intrastate
Item Involved
Pipe
Pipe Type
Pipe Body
Puddle Weld Ind
No
Pipe Diameter
10
Pipe Wall Thickness
0.188
Pipe Smys
42000
Pipe Specification
Api 5l
Pipe Seam Type
Erw � Unknown Frequency
Pipe Manufacturer
Unknown
Pipe Coating Type
Other
Pipe Coating Details
Mastic
Coating Applied Ind
Unknown
Installation Year
Unknown
Manufactured Year
Unknown
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Pinhole
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
0
Est Cost Gas Released
400
Est Cost Prop Damage
10009
Est Cost Emergency
10563
Est Cost Environmental
16017
Est Cost Other
0
Prpty
36989
Num Persons Hosp Not Ovnght
0
Num Injured Treated By Emt
0
Num Resident Building Affctd
0
Num Business Building Affctd
0
Accident Psig
38
Mop Psig
285
Mop Cfr Section
Component Design Pressure �195.406(A)(2)
Maop Established Date
1993-01-01 00:00:00
Maop Reversal Flow Ind
No
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
No
Investigation Status
Yes, specify investigation result(s): (select all that apply)
Invest Schedule Ind
Yes
Invest No Control Room Ind
Yes
Invest No Controller Ind
Yes
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Corrosion Failure
Cause Details
External Corrosion
Internal External
External Corrosion
Visual Exam Results
Localized Pitting
Stray Current Corrosion Ind
Yes
Stray Current Type
Alternating Current
Stray Current Details
Unknown
Field Exam Basis Ind
Yes
Metallurgical Basis Ind
Yes
Underground Location
Yes
Under Cathodic Protection Ind
Yes
Cathodic Pro Start Year
Unknown
Shielding Evident
No
Cathodic Survey Type
Yes
Cp Annual Survey Ind
Yes
Cp Annual Survey Year
2021
Prior Damage
No
Collected Data Ind
No
Has Hydrtst Conduc Before Ind
No
Direct Asmnt Conducted
No
Non Destructive Exam Ind
No
Preparer Name
N****** G*******
Preparer Title
Hse Compliance Specialist
Preparer Email
N*********@p****.com
Preparer Telephone
7136464376
Prepared Date
2022-04-22 00:00:00
Local Contact Name
N****** G*******
Local Contact Email
N*********@p****.com
Local Contact Telephone
7136464376
Authorizer Name
N***** G*****
Authorizer Telephone
7136464336
Authorizer Title
Hse Mgr Director
Authorizer Email
N******@p****.com
Narrative
Approximately 165 barrels of crude oil were released from the pump 9 discharge station piping at china grove station. The date and time of the release (part a q4) is indicative of the earliest possible time the release could have started, as it was the date/time that the pump had started. The cause of the release was attributed to external corrosion as a result of stay current inference. To prevent future incidents, an interrupted close interval cathodic protection survey will be performed to determine the cause of the stray current and ensure that other facility piping does not have stray current interference. Supplemental narrative: updated the nominal diameter of the failed section of pipe to 10" (part c q3.A). Supplemental narrative (2): the cause of the release was attributed to external corrosion, likely from stay current inference as indicated by the pit morphology. The type of stray current interference is not known (part g1 q2a). To prevent future incidents, a cis survey was conducted and results indicated that the incident location met criteria. Additionally, in 2022, non-destructive testing inspections will be conducted for select pipeline segments within the facility.
| Report Received Date | 2021-12-03 00:00:00 |
|---|---|
| Iyear | 2021 |
| Report Number | 20210340 |
| Supplemental Number | 36602 |
| Report Type | Supplemental Final |
| Operator Id | 300 PHMSA Enforcement |
| Name | Plains Pipeline, L.p. |
| Operator Street Address | 333 Clay Street, Suite 1900 |
| Operator City Name | Houston |
| Operator State Abbreviation | TX |
| Operator Postal Code | 77002 |
| Local Datetime | 2021-11-04 16:30:00 |
| Time Zone | Central |
| Daylight Savings Ind | Yes |
| Location Latitude | 32.5320273 Google Maps OpenStreetMap |
| Location Longitude | -100.8419713 Google Maps OpenStreetMap |
| Commodity Released Type | Crude Oil |
| Unintentional Release Bbls | 165 |
| Recovered Bbls | 165 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Notification From Public |
| Incident Identified Datetime | 2021-11-04 17:04:00 |
| System Part Involved | Onshore Terminal/tank Farm Equipment And Piping |
| On Off Shore | Onshore |
| Status When Identified | Idle |
| Communication State Fed Ind | Yes |
| Party Initiated Communication | Operator |
| Initial Responder Com Datetime | 2021-11-04 18:21:00 |
| On Site Datetime | 2021-11-04 17:30:00 |
| Confirmed Discovery Datetime | 2021-11-04 17:30:00 |
| Nrc Rpt Num | Nrc Notification Not Required NRC Report How to search |
| Ignite Ind | No |
| Notify Qualified Indiv Ind | Yes |
| Qualified Indiv Notif Datetime | 2021-11-04 17:30:00 |
| Oil Spill Removal Org Ind | No |
| Num Pub Evacuated | 0 |
| Pipe Fac Name | China Grove |
| Segment Name | China Grove Station Piping - Pump 9 Discharge |
| Onshore State Abbreviation | Tx |
| Onshore Postal Code | 79526 |
| Onshore City Name | Hermleigh |
| Onshore County Name | Scurry |
| Designated Location | Milepost |
| Designated Name | 0+00 |
| Federal | No |
| Location Type | Totally Contained On Operator-Controlled Property |
| Incident Area Type | Underground |
| Incident Area Subtype | Under Soil |
| Depth Of Cover | 48 |
| Crossing | No |
| Pipe Facility Type | Intrastate |
| Item Involved | Pipe |
| Pipe Type | Pipe Body |
| Puddle Weld Ind | No |
| Pipe Diameter | 10 |
| Pipe Wall Thickness | 0.188 |
| Pipe Smys | 42000 |
| Pipe Specification | Api 5l |
| Pipe Seam Type | Erw � Unknown Frequency |
| Pipe Manufacturer | Unknown |
| Pipe Coating Type | Other |
| Pipe Coating Details | Mastic |
| Coating Applied Ind | Unknown |
| Installation Year | Unknown |
| Manufactured Year | Unknown |
| Material Involved | Carbon Steel |
| Release Type | Leak |
| Leak Type | Pinhole |
| Wildlife Impact Ind | No |
| Soil Contamination | Yes |
| Long Term Assessment | No |
| Remediation Ind | No |
| Water Contam Ind | No |
| Could Be Hca | No |
| Commodity Reached Hca | No |
| Est Cost Oper Paid | 0 |
| Est Cost Gas Released | 400 |
| Est Cost Prop Damage | 10009 |
| Est Cost Emergency | 10563 |
| Est Cost Environmental | 16017 |
| Est Cost Other | 0 |
| Prpty | 36989 |
| Num Persons Hosp Not Ovnght | 0 |
| Num Injured Treated By Emt | 0 |
| Num Resident Building Affctd | 0 |
| Num Business Building Affctd | 0 |
| Accident Psig | 38 |
| Mop Psig | 285 |
| Mop Cfr Section | Component Design Pressure �195.406(A)(2) View CFR 49 §192 |
| Maop Established Date | 1993-01-01 00:00:00 |
| Maop Reversal Flow Ind | No |
| Accident Pressure | Pressure Did Not Exceed Mop |
| Pressure Restriction Ind | No |
| Pipeline Function | > 20% Smys Regulated Transmission |
| Scada In Place Ind | Yes |
| Scada Operating Ind | Yes |
| Scada Functional Ind | Yes |
| Scada Detection Ind | No |
| Scada Conf Ind | No |
| Cpm In Place Ind | No |
| Investigation Status | Yes, specify investigation result(s): (select all that apply) |
| Invest Schedule Ind | Yes |
| Invest No Control Room Ind | Yes |
| Invest No Controller Ind | Yes |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | No |
| Cause | Corrosion Failure |
| Cause Details | External Corrosion |
| Internal External | External Corrosion |
| Visual Exam Results | Localized Pitting |
| Stray Current Corrosion Ind | Yes |
| Stray Current Type | Alternating Current |
| Stray Current Details | Unknown |
| Field Exam Basis Ind | Yes |
| Metallurgical Basis Ind | Yes |
| Underground Location | Yes |
| Under Cathodic Protection Ind | Yes |
| Cathodic Pro Start Year | Unknown |
| Shielding Evident | No |
| Cathodic Survey Type | Yes |
| Cp Annual Survey Ind | Yes |
| Cp Annual Survey Year | 2021 |
| Prior Damage | No |
| Collected Data Ind | No |
| Has Hydrtst Conduc Before Ind | No |
| Direct Asmnt Conducted | No |
| Non Destructive Exam Ind | No |
| Preparer Name | N****** G******* |
| Preparer Title | Hse Compliance Specialist |
| Preparer Email | N*********@p****.com |
| Preparer Telephone | 7136464376 |
| Prepared Date | 2022-04-22 00:00:00 |
| Local Contact Name | N****** G******* |
| Local Contact Email | N*********@p****.com |
| Local Contact Telephone | 7136464376 |
| Authorizer Name | N***** G***** |
| Authorizer Telephone | 7136464336 |
| Authorizer Title | Hse Mgr Director |
| Authorizer Email | N******@p****.com |
| Narrative | Approximately 165 barrels of crude oil were released from the pump 9 discharge station piping at china grove station. The date and time of the release (part a q4) is indicative of the earliest possible time the release could have started, as it was the date/time that the pump had started. The cause of the release was attributed to external corrosion as a result of stay current inference. To prevent future incidents, an interrupted close interval cathodic protection survey will be performed to determine the cause of the stray current and ensure that other facility piping does not have stray current interference. Supplemental narrative: updated the nominal diameter of the failed section of pipe to 10" (part c q3.A). Supplemental narrative (2): the cause of the release was attributed to external corrosion, likely from stay current inference as indicated by the pit morphology. The type of stray current interference is not known (part g1 q2a). To prevent future incidents, a cis survey was conducted and results indicated that the incident location met criteria. Additionally, in 2022, non-destructive testing inspections will be conducted for select pipeline segments within the facility. |