HL incident on 2021-10-27 — TX

Operator
Cr Permian Processing Llc
Cause
Corrosion Failure
Commodity
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$550,000
Incident datetime
2021-10-27 17:32
Report number
Location
TX
Narrative
The company received notification of a suspected leak at the pecos river where the company has 4 lines that cross the pecos river. Field personnel were dispatched to the scene and once the company had confirmed a gas release, we notified the railroad commission of texas incident line and then notified the nrc. The company-controlled access to the rows on each side of the pecos river and started work to determine which line was leaking. The company blew each line down to determine which line was the leaking line. The order the company blew the pipelines down was the 10" gas gathering, 8" gas transmission, 6" ngl and then the 8" ngl loop to lone star. The section of bore pipe that leaked has been removed from the bore and several pipe specimens, including the weld that had the hole, have been sent to a metallurgy lab for failure analysis. A new bore was drilled, and the new segment of pipe was installed and put into service. Ili tools have been run on the entire 8" ngl loop to lone star and the company expedited the data results and should have results 45 to 60 days from the date of the successful ili tool run on 11/18/2021. The ili tool run required no immediate repairs, there is one dent and one corrosion spot we are investigating, and re-inspection has been set to the maximum 5 years according to trrc section 8.101(a)(2). The element materials technology final report indicated failure due to a combination of crevice and general corrosion that occurred on and near girth welds and heat affected zones. The corrosion had created a through-wall penetration that resulted in the pipe leakage. To estimate the leaked quantity, we are assuming that the leak began on 10/16/21. The aerial pipeline patrol report completed on 10/15/21 states that no leaks were observed, we believe it is conservative to assume the leak started the next day. The leak was stopped on the evening of 10/28/21 thus 13 days. Taking into account the observed leak quantities along with the type of failure observed (not a rupture) we believe a 0.5 cm diameter hole is a conservative estimate (the hole observed, and measured post removal supports this analysis.) a 0.5 cm hole with 1100psi differential will flow approximately 650 bbl/d according to our calculation which means a total leaked volume of 8450bbls. Of worth noting is the leaked fluid is a ngl which is a highly volatile liquid, engineering analysis via our process simulation indicates that composition of the ngl flashes 100% to vapor at the atmospheric pressures as long as temperatures remain above 35f. At all times during the leak ambient ground and air temperatures were well over 35f so we do not believe any of the leaked material remained in the ground or water and instead was vaporized to atmosphere.
Detailed record list
Report Received Date
2021-11-22 00:00:00
Iyear
2021
Report Number
20210330
Supplemental Number
36434
Report Type
Supplemental Final
Operator Id
Name
Cr Permian Processing Llc
Operator Street Address
303 Veterans Airpark Lane, Suite 2000
Operator City Name
Midland
Operator State Abbreviation
TX
Operator Postal Code
79705
Local Datetime
2021-10-16 21:00:00
Time Zone
Central
Daylight Savings Ind
Yes
Location Latitude
Location Longitude
Commodity Released Type
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Commodity Subtype
Lpg (Liquefied Petroleum Gas) / Ngl (Natural Gas Liquid)
Unintentional Release Bbls
8450
Intentional Release Bbls
1794.18
Recovered Bbls
0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Notification From Emergency Responder
Incident Identified Datetime
2021-10-27 17:32:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Status When Identified
Normal Operation, Includes Pauses Between Batches And During Maintenance
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2021-10-28 21:00:00
Restart Datetime
2021-10-28 21:00:00
On Site Datetime
2021-10-27 18:25:00
Confirmed Discovery Datetime
2021-10-27 19:36:00
Nrc Rpt Datetime
2021-10-27 19:36:00
Nrc Rpt Num
Additional Nrc Report Numbers
1320777
Ignite Ind
No
Upstream Action Taken
Valve Closure
Upstream Valve Close Datetime
2021-10-28 21:00:00
Upstream Valve Type Ind
Manual
Downstream Action Taken
Valve Closure
Downstream Vlv Close Datetime
2021-10-28 21:00:00
Downstream Valve Type Ind
Manual
Num Pub Evacuated
0
Pipe Fac Name
Ngl Loop To Lone Star
Segment Name
Ngl Loop To Lone Star
Onshore State Abbreviation
Tx
Onshore Postal Code
79772
Onshore City Name
Not Within A Municipality
Onshore County Name
Reeves
Designated Location
Milepost
Designated Name
1.75 Mile
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
240
Crossing
Yes
Water Crossing Ind
Yes
Water Type
Uncased
Water Name
Pecos River
Water Depth
1
Water Subtype
Below Water, Pipe In Bored/drilled Crossing
Crossing 100 Feet
Yes
Pipe Facility Type
Intrastate
Item Involved
Weld, Including Heat-Affected Zone
Pipe Diameter
8
Pipe Wall Thickness
0.322
Pipe Smys
52000
Pipe Specification
Api 5l 45th Ed.
Pipe Seam Type
Erw - High Frequency
Pipe Manufacturer
Pythco
Pipe Coating Type
Fusion Bonded Epoxy(Fbe)
Coating Applied Ind
Yes
Weld Subtype
Pipe Girth Weld
Different Girth Weld Ind
No
Installation Year
2018
Manufactured Year
2017
Material Involved
Carbon Steel
Release Type
Other
Release Type Details
Corrosion Of The Girth Weld Formed A Hole On The Weld.
Wildlife Impact Ind
Yes
Fish Aquatic Impact Ind
Yes
Soil Contamination
Yes
Long Term Assessment
Yes
Remediation Ind
Yes
Surface Water Remed Ind
Yes
Water Contam Ind
Yes
Surface Contam Ind
Yes
Amount Released
8450
Rel Water Name
Pecos River
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
5880
Est Cost Gas Released
414479
Est Cost Prop Damage
550000
Est Cost Emergency
8000
Est Cost Environmental
50000
Est Cost Other
7000
Est Cost Other Details
Expense Related To Investigation
Prpty
1035359
Num Persons Hosp Not Ovnght
0
Num Injured Treated By Emt
0
Num Resident Building Affctd
0
Num Business Building Affctd
0
Accident Psig
1157
Mop Psig
1440
Mop Cfr Section
Component Design Pressure �195.406(A)(2)
Maop Established Date
2018-08-24 00:00:00
Maop Reversal Flow Ind
No
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
27628
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
No
Cpm In Place Ind
No
Investigation Status
No, the facility was not monitored by a controller(s) at the time of the accident
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Corrosion Failure
Cause Details
External Corrosion
Internal External
External Corrosion
Visual Exam Results
Other
Visual Exam Details
Corrosion Appeared To Only Affect The Welds
Other Corrosion Ind
Yes
Corrosion Type Details
The Element Materials Technology Final Report Indicated Failure Due To A Combination Of Crevice And General Corrosion That Occurred On And Near Girth Welds And Heat Affected Zones. The Corrosion Had Created Through-Wall Penetrations That Resulted In The Pipe Leakage. The Full Report Is Attached.
Field Exam Basis Ind
Yes
Underground Location
Yes
Under Cathodic Protection Ind
Yes
Cathodic Pro Start Year
2020
Shielding Evident
Yes
Cathodic Survey Type
Yes
Cp Annual Survey Ind
Yes
Cp Annual Survey Year
2021
Prior Damage
Yes
Collected Data Ind
No
Has Hydrtst Conduc Before Ind
No
Direct Asmnt Conducted
No
Non Destructive Exam Ind
Yes
Exm Radiography Rcnt Year
2018
Exm Radiography Rcnt Ind
Yes
Preparer Name
K**** R****
Preparer Title
Pipeline Safety Compliance Specialist
Preparer Email
K*****@e*****************.com
Preparer Telephone
214-478-3969
Prepared Date
2022-03-07 00:00:00
Authorizer Name
K**** R****
Authorizer Telephone
214-478-3969
Authorizer Title
Pipeline Safety Compliance Specialist
Authorizer Email
K*****@e*****************.com
Narrative
The company received notification of a suspected leak at the pecos river where the company has 4 lines that cross the pecos river. Field personnel were dispatched to the scene and once the company had confirmed a gas release, we notified the railroad commission of texas incident line and then notified the nrc. The company-controlled access to the rows on each side of the pecos river and started work to determine which line was leaking. The company blew each line down to determine which line was the leaking line. The order the company blew the pipelines down was the 10" gas gathering, 8" gas transmission, 6" ngl and then the 8" ngl loop to lone star. The section of bore pipe that leaked has been removed from the bore and several pipe specimens, including the weld that had the hole, have been sent to a metallurgy lab for failure analysis. A new bore was drilled, and the new segment of pipe was installed and put into service. Ili tools have been run on the entire 8" ngl loop to lone star and the company expedited the data results and should have results 45 to 60 days from the date of the successful ili tool run on 11/18/2021. The ili tool run required no immediate repairs, there is one dent and one corrosion spot we are investigating, and re-inspection has been set to the maximum 5 years according to trrc section 8.101(a)(2). The element materials technology final report indicated failure due to a combination of crevice and general corrosion that occurred on and near girth welds and heat affected zones. The corrosion had created a through-wall penetration that resulted in the pipe leakage. To estimate the leaked quantity, we are assuming that the leak began on 10/16/21. The aerial pipeline patrol report completed on 10/15/21 states that no leaks were observed, we believe it is conservative to assume the leak started the next day. The leak was stopped on the evening of 10/28/21 thus 13 days. Taking into account the observed leak quantities along with the type of failure observed (not a rupture) we believe a 0.5 cm diameter hole is a conservative estimate (the hole observed, and measured post removal supports this analysis.) a 0.5 cm hole with 1100psi differential will flow approximately 650 bbl/d according to our calculation which means a total leaked volume of 8450bbls. Of worth noting is the leaked fluid is a ngl which is a highly volatile liquid, engineering analysis via our process simulation indicates that composition of the ngl flashes 100% to vapor at the atmospheric pressures as long as temperatures remain above 35f. At all times during the leak ambient ground and air temperatures were well over 35f so we do not believe any of the leaked material remained in the ground or water and instead was vaporized to atmosphere.
Report Received Date 2021-11-22 00:00:00
Iyear 2021
Report Number 20210330
Supplemental Number 36434
Report Type Supplemental Final
Operator Id 39511 PHMSA Enforcement
Name Cr Permian Processing Llc
Operator Street Address 303 Veterans Airpark Lane, Suite 2000
Operator City Name Midland
Operator State Abbreviation TX
Operator Postal Code 79705
Local Datetime 2021-10-16 21:00:00
Time Zone Central
Daylight Savings Ind Yes
Location Latitude 31.510493 Google Maps OpenStreetMap
Location Longitude -103.503215 Google Maps OpenStreetMap
Commodity Released Type Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Commodity Subtype Lpg (Liquefied Petroleum Gas) / Ngl (Natural Gas Liquid)
Unintentional Release Bbls 8450
Intentional Release Bbls 1794.18
Recovered Bbls 0
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Notification From Emergency Responder
Incident Identified Datetime 2021-10-27 17:32:00
System Part Involved Onshore Pipeline, Including Valve Sites
On Off Shore Onshore
Status When Identified Normal Operation, Includes Pauses Between Batches And During Maintenance
Shutdown Due Accident Ind Yes
Shutdown Datetime 2021-10-28 21:00:00
Restart Datetime 2021-10-28 21:00:00
On Site Datetime 2021-10-27 18:25:00
Confirmed Discovery Datetime 2021-10-27 19:36:00
Nrc Rpt Datetime 2021-10-27 19:36:00
Nrc Rpt Num 1320613 NRC Report How to search
Additional Nrc Report Numbers 1320777
Ignite Ind No
Upstream Action Taken Valve Closure
Upstream Valve Close Datetime 2021-10-28 21:00:00
Upstream Valve Type Ind Manual
Downstream Action Taken Valve Closure
Downstream Vlv Close Datetime 2021-10-28 21:00:00
Downstream Valve Type Ind Manual
Num Pub Evacuated 0
Pipe Fac Name Ngl Loop To Lone Star
Segment Name Ngl Loop To Lone Star
Onshore State Abbreviation Tx
Onshore Postal Code 79772
Onshore City Name Not Within A Municipality
Onshore County Name Reeves
Designated Location Milepost
Designated Name 1.75 Mile
Federal No
Location Type Pipeline Right-Of-Way
Incident Area Type Underground
Incident Area Subtype Under Soil
Depth Of Cover 240
Crossing Yes
Water Crossing Ind Yes
Water Type Uncased
Water Name Pecos River
Water Depth 1
Water Subtype Below Water, Pipe In Bored/drilled Crossing
Crossing 100 Feet Yes
Pipe Facility Type Intrastate
Item Involved Weld, Including Heat-Affected Zone
Pipe Diameter 8
Pipe Wall Thickness 0.322
Pipe Smys 52000
Pipe Specification Api 5l 45th Ed.
Pipe Seam Type Erw - High Frequency
Pipe Manufacturer Pythco
Pipe Coating Type Fusion Bonded Epoxy(Fbe)
Coating Applied Ind Yes
Weld Subtype Pipe Girth Weld
Different Girth Weld Ind No
Installation Year 2018
Manufactured Year 2017
Material Involved Carbon Steel
Release Type Other
Release Type Details Corrosion Of The Girth Weld Formed A Hole On The Weld.
Wildlife Impact Ind Yes
Fish Aquatic Impact Ind Yes
Soil Contamination Yes
Long Term Assessment Yes
Remediation Ind Yes
Surface Water Remed Ind Yes
Water Contam Ind Yes
Surface Contam Ind Yes
Amount Released 8450
Rel Water Name Pecos River
Could Be Hca No
Commodity Reached Hca No
Est Cost Oper Paid 5880
Est Cost Gas Released 414479
Est Cost Prop Damage 550000
Est Cost Emergency 8000
Est Cost Environmental 50000
Est Cost Other 7000
Est Cost Other Details Expense Related To Investigation
Prpty 1035359
Num Persons Hosp Not Ovnght 0
Num Injured Treated By Emt 0
Num Resident Building Affctd 0
Num Business Building Affctd 0
Accident Psig 1157
Mop Psig 1440
Mop Cfr Section Component Design Pressure �195.406(A)(2) View CFR 49 §192
Maop Established Date 2018-08-24 00:00:00
Maop Reversal Flow Ind No
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Length Segment Isolated 27628
Internal Inspection Ind Yes
Operation Complications Ind No
Pipeline Function > 20% Smys Regulated Transmission
Scada In Place Ind No
Cpm In Place Ind No
Investigation Status No, the facility was not monitored by a controller(s) at the time of the accident
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Corrosion Failure
Cause Details External Corrosion
Internal External External Corrosion
Visual Exam Results Other
Visual Exam Details Corrosion Appeared To Only Affect The Welds
Other Corrosion Ind Yes
Corrosion Type Details The Element Materials Technology Final Report Indicated Failure Due To A Combination Of Crevice And General Corrosion That Occurred On And Near Girth Welds And Heat Affected Zones. The Corrosion Had Created Through-Wall Penetrations That Resulted In The Pipe Leakage. The Full Report Is Attached.
Field Exam Basis Ind Yes
Underground Location Yes
Under Cathodic Protection Ind Yes
Cathodic Pro Start Year 2020
Shielding Evident Yes
Cathodic Survey Type Yes
Cp Annual Survey Ind Yes
Cp Annual Survey Year 2021
Prior Damage Yes
Collected Data Ind No
Has Hydrtst Conduc Before Ind No
Direct Asmnt Conducted No
Non Destructive Exam Ind Yes
Exm Radiography Rcnt Year 2018
Exm Radiography Rcnt Ind Yes
Preparer Name K**** R****
Preparer Title Pipeline Safety Compliance Specialist
Preparer Email K*****@e*****************.com
Preparer Telephone 214-478-3969
Prepared Date 2022-03-07 00:00:00
Authorizer Name K**** R****
Authorizer Telephone 214-478-3969
Authorizer Title Pipeline Safety Compliance Specialist
Authorizer Email K*****@e*****************.com
Narrative The company received notification of a suspected leak at the pecos river where the company has 4 lines that cross the pecos river. Field personnel were dispatched to the scene and once the company had confirmed a gas release, we notified the railroad commission of texas incident line and then notified the nrc. The company-controlled access to the rows on each side of the pecos river and started work to determine which line was leaking. The company blew each line down to determine which line was the leaking line. The order the company blew the pipelines down was the 10" gas gathering, 8" gas transmission, 6" ngl and then the 8" ngl loop to lone star. The section of bore pipe that leaked has been removed from the bore and several pipe specimens, including the weld that had the hole, have been sent to a metallurgy lab for failure analysis. A new bore was drilled, and the new segment of pipe was installed and put into service. Ili tools have been run on the entire 8" ngl loop to lone star and the company expedited the data results and should have results 45 to 60 days from the date of the successful ili tool run on 11/18/2021. The ili tool run required no immediate repairs, there is one dent and one corrosion spot we are investigating, and re-inspection has been set to the maximum 5 years according to trrc section 8.101(a)(2). The element materials technology final report indicated failure due to a combination of crevice and general corrosion that occurred on and near girth welds and heat affected zones. The corrosion had created a through-wall penetration that resulted in the pipe leakage. To estimate the leaked quantity, we are assuming that the leak began on 10/16/21. The aerial pipeline patrol report completed on 10/15/21 states that no leaks were observed, we believe it is conservative to assume the leak started the next day. The leak was stopped on the evening of 10/28/21 thus 13 days. Taking into account the observed leak quantities along with the type of failure observed (not a rupture) we believe a 0.5 cm diameter hole is a conservative estimate (the hole observed, and measured post removal supports this analysis.) a 0.5 cm hole with 1100psi differential will flow approximately 650 bbl/d according to our calculation which means a total leaked volume of 8450bbls. Of worth noting is the leaked fluid is a ngl which is a highly volatile liquid, engineering analysis via our process simulation indicates that composition of the ngl flashes 100% to vapor at the atmospheric pressures as long as temperatures remain above 35f. At all times during the leak ambient ground and air temperatures were well over 35f so we do not believe any of the leaked material remained in the ground or water and instead was vaporized to atmosphere.

All rights reserved. Copyright © by ClearPHMSA