HL incident on 2020-06-10 — TX

Operator
Citgo Refining & Chemical Co. L.p.
Cause
Equipment Failure
Commodity
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$100,000
Incident datetime
2020-06-10 11:00
Report number
Location
TX
Narrative
On april 6, 2020, the e05 ulsd pipeline was isolated, de-inventoried and blinded in preparation for the pipeline's 5-year DOT assessment by hydro-test. The hydro-test for this pipeline was to be conducted in three segments. The east-side segment was completed on april 12th and west-side segment was completed on april 13th. The center segment would not hold pressure after multiple attempts. Different methods of trying to get a good hydro on the line were attempted without success. The decision was made to conduct a ut smart pig on the pipeline on april 11th, and the process to award the contract was started within citgo procurement requirements. The contract was awarded and signed on may 6th. Contract surveyors mobilized on may 8th and the smart pig was successfully conducted on may 13th. On the evening of may 13th, citgo received preliminary results from the pigging contractor that indicated the presence of two underground flanges on this pipeline (one at the 91 area and one at gate 5 area). On may 18th, citgo starting hydro-excavating/pot-holing the areas in question in order to locate the underground flanges for inspection and removal. On may 20th, it was determined that one of the potholes at the 91 area had developed a layer of diesel in it at a depth of ~18 feet below grade. With the e05 pipeline out of service for testing, the source of the leak could not be determined at that time. Hydro-excavation continued at the 91 area to locate the underground flanges, with none of the other potholes indicating any sign of diesel. When the flanges were located at both locations, large excavations, utilizing hydro-excavation techniques, with the proper shoring were installed for the inspection and removal of the flanges. Over time, the excavation at the 91 area was leaching in diesel into the shore box. This material was pumped out periodically into frac tanks for containment. With the flanges exposed on june 10th, a hydro-test was conducted and indicated that the flange at the 91 area was leaking. On the evening of june 10th, notification of all agencies was conducted, with the coast guard and tglo making a site visit that evening. The tceq and rrct contacted US on june 11th and tceq also visited the site. Two dewatering wells and a recovery sump were installed in close proximity to the excavation at the 91 area to lower the groundwater table and prevent hydrocarbon leaching into the shore box. This allowed maintenance to safely enter the shore box to remove the underground flanges. Delineation and remediation activities will be performed per the tceq 30tac spill rules or texas risk reduction program (trrp-13) as required. The flanges at the gate 5 area and 91 area have been removed and replaced with piping sections. An incident investigation was conducted and determined that the root cause for the leak was an out-dated piping design. The e05 - ulsd pipeline was returned to service on 7/31/2020.
Detailed record list
Report Received Date
2020-07-14 00:00:00
Iyear
2020
Report Number
20200203
Supplemental Number
34231
Report Type
Supplemental Final
Operator Id
Name
Citgo Refining & Chemical Co. L.p.
Operator Street Address
1293 Eldridge Parkway
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77077
Local Datetime
2020-06-10 11:00:00
Location Latitude
Location Longitude
Commodity Released Type
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Commodity Subtype
Diesel, Fuel Oil, Kerosene, Jet Fuel
Unintentional Release Bbls
8.5
Recovered Bbls
8.5
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Static Shut-In Test Or Other Pressure Or Leak Test
Incident Identified Datetime
2020-06-10 11:00:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
No
Shutdown Explain
Leak Identified When Line Was Isolated For 5 Yr Assessment
On Site Datetime
2020-06-10 11:00:00
Nrc Rpt Datetime
2020-06-10 18:30:00
Nrc Rpt Num
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Manual
Downstream Valve Type Ind
Manual
Num Pub Evacuated
0
Pipe Fac Name
E05 - Ulsd
Segment Name
E05 91 Area Pig Launcher Area
Onshore State Abbreviation
Tx
Onshore Postal Code
78409
Onshore City Name
Corpus Christi
Onshore County Name
Nueces
Designated Location
Milepost/valve Station
Designated Name
91 Area
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
144
Crossing
No
Pipe Facility Type
Intrastate
Item Involved
Flange Assembly
Installation Year
1976
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Connection Failure
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
Yes
Remediation Ind
Yes
Groundwater Remed Ind
Yes
Soil Remed Ind
Yes
Water Contam Ind
Yes
Groundwater Contam Ind
Yes
Amount Released
1
Rel Water Name
Unknown
Could Be Hca
Yes
Commodity Reached Hca
Yes
High Pop Ind
Yes
High Pop Yes No
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
2000
Est Cost Prop Damage
100000
Est Cost Emergency
3000
Est Cost Environmental
150000
Est Cost Other
0
Prpty
255000
Accident Psig
150
Mop Psig
285
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
17580
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
No
Cpm In Place Ind
No
Investigation Status
No, the facility was not monitored by a controller(s) at the time of the accident
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Equipment Failure
Cause Details
Non-Threaded Connection Failure
Eq Failure Type
Non-Threaded Connection Failure
Other Non Threaded Ind
Other
Other Non Threaded Details
Investigation Determined That Root Cause Was Underground Flange Leak Due To Outdated Piping Design. Citgo Has Not Allowed Underground Slip-On Flanges Within Its Piping Specification (M-200) Since At Least 1995.
Eq Additional Other Ind
Yes
Eq Additional Other Details
Outdated Piping Design
Preparer Name
D**** R* G*****
Preparer Title
Psm Advisor
Preparer Email
D******@c****.com
Preparer Telephone
361-844-5479
Prepared Date
2020-09-03 00:00:00
Authorizer Name
D**** R* G*****
Authorizer Telephone
361-844-5479
Authorizer Title
Psm Advisor
Authorizer Email
D******@c****.com
Narrative
On april 6, 2020, the e05 ulsd pipeline was isolated, de-inventoried and blinded in preparation for the pipeline's 5-year DOT assessment by hydro-test. The hydro-test for this pipeline was to be conducted in three segments. The east-side segment was completed on april 12th and west-side segment was completed on april 13th. The center segment would not hold pressure after multiple attempts. Different methods of trying to get a good hydro on the line were attempted without success. The decision was made to conduct a ut smart pig on the pipeline on april 11th, and the process to award the contract was started within citgo procurement requirements. The contract was awarded and signed on may 6th. Contract surveyors mobilized on may 8th and the smart pig was successfully conducted on may 13th. On the evening of may 13th, citgo received preliminary results from the pigging contractor that indicated the presence of two underground flanges on this pipeline (one at the 91 area and one at gate 5 area). On may 18th, citgo starting hydro-excavating/pot-holing the areas in question in order to locate the underground flanges for inspection and removal. On may 20th, it was determined that one of the potholes at the 91 area had developed a layer of diesel in it at a depth of ~18 feet below grade. With the e05 pipeline out of service for testing, the source of the leak could not be determined at that time. Hydro-excavation continued at the 91 area to locate the underground flanges, with none of the other potholes indicating any sign of diesel. When the flanges were located at both locations, large excavations, utilizing hydro-excavation techniques, with the proper shoring were installed for the inspection and removal of the flanges. Over time, the excavation at the 91 area was leaching in diesel into the shore box. This material was pumped out periodically into frac tanks for containment. With the flanges exposed on june 10th, a hydro-test was conducted and indicated that the flange at the 91 area was leaking. On the evening of june 10th, notification of all agencies was conducted, with the coast guard and tglo making a site visit that evening. The tceq and rrct contacted US on june 11th and tceq also visited the site. Two dewatering wells and a recovery sump were installed in close proximity to the excavation at the 91 area to lower the groundwater table and prevent hydrocarbon leaching into the shore box. This allowed maintenance to safely enter the shore box to remove the underground flanges. Delineation and remediation activities will be performed per the tceq 30tac spill rules or texas risk reduction program (trrp-13) as required. The flanges at the gate 5 area and 91 area have been removed and replaced with piping sections. An incident investigation was conducted and determined that the root cause for the leak was an out-dated piping design. The e05 - ulsd pipeline was returned to service on 7/31/2020.
Report Received Date 2020-07-14 00:00:00
Iyear 2020
Report Number 20200203
Supplemental Number 34231
Report Type Supplemental Final
Operator Id 31023 PHMSA Enforcement
Name Citgo Refining & Chemical Co. L.p.
Operator Street Address 1293 Eldridge Parkway
Operator City Name Houston
Operator State Abbreviation TX
Operator Postal Code 77077
Local Datetime 2020-06-10 11:00:00
Location Latitude 27.8141 Google Maps OpenStreetMap
Location Longitude -97.4765 Google Maps OpenStreetMap
Commodity Released Type Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Commodity Subtype Diesel, Fuel Oil, Kerosene, Jet Fuel
Unintentional Release Bbls 8.5
Recovered Bbls 8.5
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Static Shut-In Test Or Other Pressure Or Leak Test
Incident Identified Datetime 2020-06-10 11:00:00
System Part Involved Onshore Pipeline, Including Valve Sites
On Off Shore Onshore
Shutdown Due Accident Ind No
Shutdown Explain Leak Identified When Line Was Isolated For 5 Yr Assessment
On Site Datetime 2020-06-10 11:00:00
Nrc Rpt Datetime 2020-06-10 18:30:00
Nrc Rpt Num 1279314 NRC Report How to search
Ignite Ind No
Explode Ind No
Upstream Valve Type Ind Manual
Downstream Valve Type Ind Manual
Num Pub Evacuated 0
Pipe Fac Name E05 - Ulsd
Segment Name E05 91 Area Pig Launcher Area
Onshore State Abbreviation Tx
Onshore Postal Code 78409
Onshore City Name Corpus Christi
Onshore County Name Nueces
Designated Location Milepost/valve Station
Designated Name 91 Area
Federal No
Location Type Totally Contained On Operator-Controlled Property
Incident Area Type Underground
Incident Area Subtype Under Soil
Depth Of Cover 144
Crossing No
Pipe Facility Type Intrastate
Item Involved Flange Assembly
Installation Year 1976
Material Involved Carbon Steel
Release Type Leak
Leak Type Connection Failure
Wildlife Impact Ind No
Soil Contamination Yes
Long Term Assessment Yes
Remediation Ind Yes
Groundwater Remed Ind Yes
Soil Remed Ind Yes
Water Contam Ind Yes
Groundwater Contam Ind Yes
Amount Released 1
Rel Water Name Unknown
Could Be Hca Yes
Commodity Reached Hca Yes
High Pop Ind Yes
High Pop Yes No Yes
Est Cost Oper Paid 0
Est Cost Gas Released 2000
Est Cost Prop Damage 100000
Est Cost Emergency 3000
Est Cost Environmental 150000
Est Cost Other 0
Prpty 255000
Accident Psig 150
Mop Psig 285
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Length Segment Isolated 17580
Internal Inspection Ind Yes
Operation Complications Ind No
Pipeline Function > 20% Smys Regulated Transmission
Scada In Place Ind No
Cpm In Place Ind No
Investigation Status No, the facility was not monitored by a controller(s) at the time of the accident
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Equipment Failure
Cause Details Non-Threaded Connection Failure
Eq Failure Type Non-Threaded Connection Failure
Other Non Threaded Ind Other
Other Non Threaded Details Investigation Determined That Root Cause Was Underground Flange Leak Due To Outdated Piping Design. Citgo Has Not Allowed Underground Slip-On Flanges Within Its Piping Specification (M-200) Since At Least 1995.
Eq Additional Other Ind Yes
Eq Additional Other Details Outdated Piping Design
Preparer Name D**** R* G*****
Preparer Title Psm Advisor
Preparer Email D******@c****.com
Preparer Telephone 361-844-5479
Prepared Date 2020-09-03 00:00:00
Authorizer Name D**** R* G*****
Authorizer Telephone 361-844-5479
Authorizer Title Psm Advisor
Authorizer Email D******@c****.com
Narrative On april 6, 2020, the e05 ulsd pipeline was isolated, de-inventoried and blinded in preparation for the pipeline's 5-year DOT assessment by hydro-test. The hydro-test for this pipeline was to be conducted in three segments. The east-side segment was completed on april 12th and west-side segment was completed on april 13th. The center segment would not hold pressure after multiple attempts. Different methods of trying to get a good hydro on the line were attempted without success. The decision was made to conduct a ut smart pig on the pipeline on april 11th, and the process to award the contract was started within citgo procurement requirements. The contract was awarded and signed on may 6th. Contract surveyors mobilized on may 8th and the smart pig was successfully conducted on may 13th. On the evening of may 13th, citgo received preliminary results from the pigging contractor that indicated the presence of two underground flanges on this pipeline (one at the 91 area and one at gate 5 area). On may 18th, citgo starting hydro-excavating/pot-holing the areas in question in order to locate the underground flanges for inspection and removal. On may 20th, it was determined that one of the potholes at the 91 area had developed a layer of diesel in it at a depth of ~18 feet below grade. With the e05 pipeline out of service for testing, the source of the leak could not be determined at that time. Hydro-excavation continued at the 91 area to locate the underground flanges, with none of the other potholes indicating any sign of diesel. When the flanges were located at both locations, large excavations, utilizing hydro-excavation techniques, with the proper shoring were installed for the inspection and removal of the flanges. Over time, the excavation at the 91 area was leaching in diesel into the shore box. This material was pumped out periodically into frac tanks for containment. With the flanges exposed on june 10th, a hydro-test was conducted and indicated that the flange at the 91 area was leaking. On the evening of june 10th, notification of all agencies was conducted, with the coast guard and tglo making a site visit that evening. The tceq and rrct contacted US on june 11th and tceq also visited the site. Two dewatering wells and a recovery sump were installed in close proximity to the excavation at the 91 area to lower the groundwater table and prevent hydrocarbon leaching into the shore box. This allowed maintenance to safely enter the shore box to remove the underground flanges. Delineation and remediation activities will be performed per the tceq 30tac spill rules or texas risk reduction program (trrp-13) as required. The flanges at the gate 5 area and 91 area have been removed and replaced with piping sections. An incident investigation was conducted and determined that the root cause for the leak was an out-dated piping design. The e05 - ulsd pipeline was returned to service on 7/31/2020.

All rights reserved. Copyright © by ClearPHMSA