HL incident on 2020-04-28 — OK

Operator
Oneok Ngl Pipeline, Llc
Cause
Incorrect Operation
Commodity
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$0
Incident datetime
2020-04-28 17:00
Report number
Location
OK
Narrative
On 4/28/2020 an incipient fire occurred while a contractor was completing the final tie-in weld at oneok's eastland ii pump station. The incipient fire occurred as the welder was approximately half-way through his root pass and self-extinguished. The pipeline was isolated by mainline block-valves upstream and downstream of the location and stopples had been set on either side of the work site. A mud plug vapor barrier was installed before performing the final tie-in weld. To make the final tie-in weld the mainline pipe was cut to ensure proper fit. Once the final cut was made a worker moved the mud plug farther into the pipe to enable the welder to make his weld. The mud plug was visually inspected and atmospheric testing downstream of the mud plug was conducted with no hydrocarbons detected. As the welder was in the process of making his weld the incipient fire developed and self-extinguished. Oneok's investigation identified that previous to oneok becoming the operator of this asset in 2015, the previous operator/employer did employ mud plugs as vapor barriers which was carried forward by the employees involved. At the time of the incident, oneok did not have a qualification or procedure for the utilization/installation of mud plugs as vapor barriers. Oneok is working to develop a mud plug vapor barrier procedure and qualifications should the use of a mud plug be required in the future. Oneok is also conducting refresher training on reporting requirements to the field employees to make sure they are aware of the PHMSA and nrc reporting requirements. Oneok's anti-drug and alcohol misuse prevention plan includes the following statements regarding post-accident testing. Anti-drug program: as soon as possible but no later than 32 hours after an accident, the company will drug test each surviving covered employee whose performance of a covered function either contributed to the accident or cannot be completely discounted as a contributing factor to the accident. Alcohol misuse prevention plan: as soon as possible, the company will alcohol test each surviving covered employee whose performance of a covered function either contributed to the accident or cannot be completely discounted as a contributing factor to the accident. The company may decide not to test under this paragraph but such a decision will be based on specific information that the covered employee's performance had no role in the cause(s) or severity of the accident. The reportability of this incident was not identified within that timeframe, thus any testing that would have normally occurred did not take place. Nrc report 1276472 was made on 5/01/20 and the follow up nrc report 1276608 was made on 5/04/20. Report updated 6/08/20 per PHMSA request.-n jones report updated 2/18/2022-n jones corrected part a, question 5-accident location, part b, question 1-pipeline name, part d, question 6-hca information part e, question 2-mop of pipeline and part e, question 9-scada & question-10 leak detection. Part a, question 5 - original gps coordinates used for the accident were incorrect. Originally reported gps: (32.4883300, -98.88111000) are for the eastland I pump station accident occurred at gps location: 32.489106, -98.873557 which is on the oneok 10" pipeline (index #21365) part b, question 1- changed pipeline/facility name from eastland I pump station to oneok #1-10" pipeline. Part d, question 6- changed hca information to "no" location on original report was eastland 1 pump station which is hca location. Accident occurred outside of hca at oneok #1-10" pipeline. Part e, question 2- changed mop to 890 which is the mop of the existing 10" pipeline. Part e, questions 9 & 10- pipeline does have scada and cpm leak detection. Both were in operation at time of accident but isolated from the section where the accident occurred.
Detailed record list
Report Received Date
2020-05-28 00:00:00
Iyear
2020
Report Number
20200149
Supplemental Number
36366
Report Type
Supplemental Final
Operator Id
Name
Oneok Ngl Pipeline, Llc
Operator Street Address
100 West Fifth Street
Operator City Name
Tulsa
Operator State Abbreviation
OK
Operator Postal Code
74103
Local Datetime
2020-04-28 17:00:00
Location Latitude
Location Longitude
Commodity Released Type
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Commodity Subtype
Lpg (Liquefied Petroleum Gas) / Ngl (Natural Gas Liquid)
Unintentional Release Bbls
0.1
Intentional Release Bbls
0
Recovered Bbls
0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Operator Employee
Incident Identified Datetime
2020-04-28 17:00:00
System Part Involved
Onshore Pump/meter Station Equipment And Piping
On Off Shore
Onshore
On Site Datetime
2020-04-28 17:00:00
Confirmed Discovery Datetime
2020-04-28 17:00:00
Nrc Rpt Datetime
2020-05-01 11:22:00
Nrc Rpt Num
Ignite Ind
Yes
Ignite Datetime
2020-04-28 17:00:00
How Extinguished
Other
How Extinguished Other Detail
Fire Immediately Self-Extinguished
Consumed By Fire In Barrels
0.1
Explode Ind
No
Num Pub Evacuated
0
Pipe Fac Name
Oneok West Texas Lpg #1 10" Pipeline
Segment Name
Oneok Index #21365
Onshore State Abbreviation
Tx
Onshore Postal Code
76448
Onshore City Name
Not Within Municipality
Onshore County Name
Eastland
Designated Location
Survey Station No.
Designated Name
745+00
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Underground
Incident Area Subtype
Exposed Due To Excavation
Depth Of Cover
48
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Weld, Including Heat-Affected Zone
Weld Subtype
Other Butt Weld
Installation Year
2020
Manufactured Year
2018
Material Involved
Carbon Steel
Release Type
Other
Release Type Details
Incipient Fire Occurred At Weld And Self-Extinguished, During Welding Of Pipe During Tie-In Work Related To New Construction
Wildlife Impact Ind
No
Soil Contamination
No
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
0
Est Cost Gas Released
1
Est Cost Prop Damage
0
Est Cost Emergency
0
Est Cost Environmental
0
Est Cost Other
250
Est Cost Other Details
Investigation Costs
Prpty
251
Accident Psig
0
Mop Psig
890
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
No
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
No
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
No, the facility was not monitored by a controller(s) at the time of the accident
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Incorrect Operation
Cause Details
Other Incorrect Operation
Operation Type
Other Incorrect Operation
Operation Details
Hydrocarbons Were Present And Not Identified During Tie-In Weld Activities Resulting In An Incipient Fire That Self Extinguished.
Related Inadequate Proc Ind
Yes
Category Type
Construction
Operator Qualification Ind
Yes
Qualified Individuals
Yes, They Were Qualified For The Task(S)
Preparer Name
N*** J****
Preparer Title
Requlatory Compliance Manager
Preparer Email
N*********@o****.com
Preparer Telephone
580-395-6304
Preparer Fax
580-395-2933
Prepared Date
2022-02-20 00:00:00
Authorizer Name
N*** J****
Authorizer Telephone
580-395-6304
Authorizer Title
Regulatory Compliance Manager
Authorizer Email
N*********@o****.com
Narrative
On 4/28/2020 an incipient fire occurred while a contractor was completing the final tie-in weld at oneok's eastland ii pump station. The incipient fire occurred as the welder was approximately half-way through his root pass and self-extinguished. The pipeline was isolated by mainline block-valves upstream and downstream of the location and stopples had been set on either side of the work site. A mud plug vapor barrier was installed before performing the final tie-in weld. To make the final tie-in weld the mainline pipe was cut to ensure proper fit. Once the final cut was made a worker moved the mud plug farther into the pipe to enable the welder to make his weld. The mud plug was visually inspected and atmospheric testing downstream of the mud plug was conducted with no hydrocarbons detected. As the welder was in the process of making his weld the incipient fire developed and self-extinguished. Oneok's investigation identified that previous to oneok becoming the operator of this asset in 2015, the previous operator/employer did employ mud plugs as vapor barriers which was carried forward by the employees involved. At the time of the incident, oneok did not have a qualification or procedure for the utilization/installation of mud plugs as vapor barriers. Oneok is working to develop a mud plug vapor barrier procedure and qualifications should the use of a mud plug be required in the future. Oneok is also conducting refresher training on reporting requirements to the field employees to make sure they are aware of the PHMSA and nrc reporting requirements. Oneok's anti-drug and alcohol misuse prevention plan includes the following statements regarding post-accident testing. Anti-drug program: as soon as possible but no later than 32 hours after an accident, the company will drug test each surviving covered employee whose performance of a covered function either contributed to the accident or cannot be completely discounted as a contributing factor to the accident. Alcohol misuse prevention plan: as soon as possible, the company will alcohol test each surviving covered employee whose performance of a covered function either contributed to the accident or cannot be completely discounted as a contributing factor to the accident. The company may decide not to test under this paragraph but such a decision will be based on specific information that the covered employee's performance had no role in the cause(s) or severity of the accident. The reportability of this incident was not identified within that timeframe, thus any testing that would have normally occurred did not take place. Nrc report 1276472 was made on 5/01/20 and the follow up nrc report 1276608 was made on 5/04/20. Report updated 6/08/20 per PHMSA request.-n jones report updated 2/18/2022-n jones corrected part a, question 5-accident location, part b, question 1-pipeline name, part d, question 6-hca information part e, question 2-mop of pipeline and part e, question 9-scada & question-10 leak detection. Part a, question 5 - original gps coordinates used for the accident were incorrect. Originally reported gps: (32.4883300, -98.88111000) are for the eastland I pump station accident occurred at gps location: 32.489106, -98.873557 which is on the oneok 10" pipeline (index #21365) part b, question 1- changed pipeline/facility name from eastland I pump station to oneok #1-10" pipeline. Part d, question 6- changed hca information to "no" location on original report was eastland 1 pump station which is hca location. Accident occurred outside of hca at oneok #1-10" pipeline. Part e, question 2- changed mop to 890 which is the mop of the existing 10" pipeline. Part e, questions 9 & 10- pipeline does have scada and cpm leak detection. Both were in operation at time of accident but isolated from the section where the accident occurred.
Report Received Date 2020-05-28 00:00:00
Iyear 2020
Report Number 20200149
Supplemental Number 36366
Report Type Supplemental Final
Operator Id 32109 PHMSA Enforcement
Name Oneok Ngl Pipeline, Llc
Operator Street Address 100 West Fifth Street
Operator City Name Tulsa
Operator State Abbreviation OK
Operator Postal Code 74103
Local Datetime 2020-04-28 17:00:00
Location Latitude 32.489106 Google Maps OpenStreetMap
Location Longitude -98.873557 Google Maps OpenStreetMap
Commodity Released Type Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Commodity Subtype Lpg (Liquefied Petroleum Gas) / Ngl (Natural Gas Liquid)
Unintentional Release Bbls 0.1
Intentional Release Bbls 0
Recovered Bbls 0
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Local Operating Personnel, Including Contractors
Operator Type Operator Employee
Incident Identified Datetime 2020-04-28 17:00:00
System Part Involved Onshore Pump/meter Station Equipment And Piping
On Off Shore Onshore
On Site Datetime 2020-04-28 17:00:00
Confirmed Discovery Datetime 2020-04-28 17:00:00
Nrc Rpt Datetime 2020-05-01 11:22:00
Nrc Rpt Num 1276472 NRC Report How to search
Ignite Ind Yes
Ignite Datetime 2020-04-28 17:00:00
How Extinguished Other
How Extinguished Other Detail Fire Immediately Self-Extinguished
Consumed By Fire In Barrels 0.1
Explode Ind No
Num Pub Evacuated 0
Pipe Fac Name Oneok West Texas Lpg #1 10" Pipeline
Segment Name Oneok Index #21365
Onshore State Abbreviation Tx
Onshore Postal Code 76448
Onshore City Name Not Within Municipality
Onshore County Name Eastland
Designated Location Survey Station No.
Designated Name 745+00
Federal No
Location Type Totally Contained On Operator-Controlled Property
Incident Area Type Underground
Incident Area Subtype Exposed Due To Excavation
Depth Of Cover 48
Crossing No
Pipe Facility Type Interstate
Item Involved Weld, Including Heat-Affected Zone
Weld Subtype Other Butt Weld
Installation Year 2020
Manufactured Year 2018
Material Involved Carbon Steel
Release Type Other
Release Type Details Incipient Fire Occurred At Weld And Self-Extinguished, During Welding Of Pipe During Tie-In Work Related To New Construction
Wildlife Impact Ind No
Soil Contamination No
Long Term Assessment No
Remediation Ind No
Water Contam Ind No
Could Be Hca No
Commodity Reached Hca No
Est Cost Oper Paid 0
Est Cost Gas Released 1
Est Cost Prop Damage 0
Est Cost Emergency 0
Est Cost Environmental 0
Est Cost Other 250
Est Cost Other Details Investigation Costs
Prpty 251
Accident Psig 0
Mop Psig 890
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Pipeline Function > 20% Smys Regulated Transmission
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind No
Scada Detection Ind No
Scada Conf Ind No
Cpm In Place Ind Yes
Cpm Operating Ind Yes
Cpm Functional Ind No
Cpm Detection Ind No
Cpm Conf Ind No
Investigation Status No, the facility was not monitored by a controller(s) at the time of the accident
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Incorrect Operation
Cause Details Other Incorrect Operation
Operation Type Other Incorrect Operation
Operation Details Hydrocarbons Were Present And Not Identified During Tie-In Weld Activities Resulting In An Incipient Fire That Self Extinguished.
Related Inadequate Proc Ind Yes
Category Type Construction
Operator Qualification Ind Yes
Qualified Individuals Yes, They Were Qualified For The Task(S)
Preparer Name N*** J****
Preparer Title Requlatory Compliance Manager
Preparer Email N*********@o****.com
Preparer Telephone 580-395-6304
Preparer Fax 580-395-2933
Prepared Date 2022-02-20 00:00:00
Authorizer Name N*** J****
Authorizer Telephone 580-395-6304
Authorizer Title Regulatory Compliance Manager
Authorizer Email N*********@o****.com
Narrative On 4/28/2020 an incipient fire occurred while a contractor was completing the final tie-in weld at oneok's eastland ii pump station. The incipient fire occurred as the welder was approximately half-way through his root pass and self-extinguished. The pipeline was isolated by mainline block-valves upstream and downstream of the location and stopples had been set on either side of the work site. A mud plug vapor barrier was installed before performing the final tie-in weld. To make the final tie-in weld the mainline pipe was cut to ensure proper fit. Once the final cut was made a worker moved the mud plug farther into the pipe to enable the welder to make his weld. The mud plug was visually inspected and atmospheric testing downstream of the mud plug was conducted with no hydrocarbons detected. As the welder was in the process of making his weld the incipient fire developed and self-extinguished. Oneok's investigation identified that previous to oneok becoming the operator of this asset in 2015, the previous operator/employer did employ mud plugs as vapor barriers which was carried forward by the employees involved. At the time of the incident, oneok did not have a qualification or procedure for the utilization/installation of mud plugs as vapor barriers. Oneok is working to develop a mud plug vapor barrier procedure and qualifications should the use of a mud plug be required in the future. Oneok is also conducting refresher training on reporting requirements to the field employees to make sure they are aware of the PHMSA and nrc reporting requirements. Oneok's anti-drug and alcohol misuse prevention plan includes the following statements regarding post-accident testing. Anti-drug program: as soon as possible but no later than 32 hours after an accident, the company will drug test each surviving covered employee whose performance of a covered function either contributed to the accident or cannot be completely discounted as a contributing factor to the accident. Alcohol misuse prevention plan: as soon as possible, the company will alcohol test each surviving covered employee whose performance of a covered function either contributed to the accident or cannot be completely discounted as a contributing factor to the accident. The company may decide not to test under this paragraph but such a decision will be based on specific information that the covered employee's performance had no role in the cause(s) or severity of the accident. The reportability of this incident was not identified within that timeframe, thus any testing that would have normally occurred did not take place. Nrc report 1276472 was made on 5/01/20 and the follow up nrc report 1276608 was made on 5/04/20. Report updated 6/08/20 per PHMSA request.-n jones report updated 2/18/2022-n jones corrected part a, question 5-accident location, part b, question 1-pipeline name, part d, question 6-hca information part e, question 2-mop of pipeline and part e, question 9-scada & question-10 leak detection. Part a, question 5 - original gps coordinates used for the accident were incorrect. Originally reported gps: (32.4883300, -98.88111000) are for the eastland I pump station accident occurred at gps location: 32.489106, -98.873557 which is on the oneok 10" pipeline (index #21365) part b, question 1- changed pipeline/facility name from eastland I pump station to oneok #1-10" pipeline. Part d, question 6- changed hca information to "no" location on original report was eastland 1 pump station which is hca location. Accident occurred outside of hca at oneok #1-10" pipeline. Part e, question 2- changed mop to 890 which is the mop of the existing 10" pipeline. Part e, questions 9 & 10- pipeline does have scada and cpm leak detection. Both were in operation at time of accident but isolated from the section where the accident occurred.

All rights reserved. Copyright © by ClearPHMSA