GD incident on 2020-11-04 — AL

Operator
Spire Alabama Inc.
Cause
Incorrect Operation
Commodity
Natural Gas
Program
GD
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$20,260
Incident datetime
2020-11-04 12:45
Report number
Location
AL, JEFFERSON
Narrative
Operator crews were in the process of replacing a valve on a 12" steel main at the referenced address. A segment had been disconnected and removed by use of stopper fittings. The remaining in-service main was not secured by using anchors or other methods of reinforcement. Line pressure forced this segment of pipeline loose from an upstream coupling at approximately 12:45 pm on november 4. Gas was stopped at 3:45 pm the same day. At approximately 4:20 pm the operator determined that this event would be reportable due to estimating the unintentional release of gas to exceed 3 million cubic feet.
Detailed record list
Occurred At
2020-11-04 12:45:00
Year
2020
Report Received Date
2020-12-04 00:00:00
Iyear
2020.0
Report Number
20200123.0
Supplemental Number
34593.0
Report Type
Original Final
Operator Id
Name
Spire Alabama Inc.
Operator Street Address
605 Richard Arrington, Jr. Boulevard North
Operator City Name
Birmingham
Operator State Abbreviation
AL
Operator Postal Code
35203
Local Datetime
2020-11-04 16:20:00
Location Street Address
39th Avenue North And Fairmont St
Location City Name
Birmingham
Location County Name
Jefferson
Location State Abbreviation
AL
Location Postal Code
35207
Location Latitude
Location Longitude
Nrc Rpt Datetime
2020-11-04 16:45:00
Nrc Rpt Num
Commodity Released Type
Natural Gas
Unintentional Release
8000.0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Ignite Ind
No
Explode Ind
No
Num Pub Evacuated
10.0
Incident Identified Datetime
2020-11-04 12:45:00
On Site Datetime
2020-11-04 12:45:00
Federal
No
Location Type
Utility Right-Of-Way / Easement
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
72.0
Crossing
No
Pipe Facility Type
Investor Owned
System Part Involved
Main
Installation Year
1959.0
Pipe Diameter
12.0
Pipe Specification
Unknown
Pipe Manufacturer
Unknown
Material Involved
Steel
Steel Seam Type
Other
Steel Seam Type Details
Unknown
Release Type
Leak
Leak Type
Connection Failure
Class Location Type
Class 3 Location
Est Cost Oper Paid
0.0
Est Cost Prop Damage
20260.0
Est Cost Emergency
8001.0
Est Cost Other
0.0
Est Cost Unintentional Release
20880.0
Prpty
49141.0
Commercial Affected
0.0
Industrial Affected
0.0
Residences Affected
10.0
Accident Psig
146.0
Normal Psig
146.0
Mop Psig
150.0
Accident Pressure
Pressure Did Not Exceed Maop
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
Yes
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Operator Employee
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
It was apparent that the incident was not caused by control room actions.
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Incorrect Operation
Cause Details
Other Incorrect Operation
Operation Type
Other Incorrect Operation
Operation Details
Pipe Segment Was Not Effectively Anchored During Construction Replacement.
Related Inadequate Proc Ind
Yes
Category Type
Construction
Operator Qualification Ind
No
Preparer Name
B*** M****
Preparer Title
Pipeline Safety Manager
Preparer Email
B*********@s**********.com
Preparer Telephone
2512889616
Authorizer Name
C**** H********
Authorizer Title
Vice President Operations Services And Sms
Authorizer Telephone
3143492972
Authorizer Email
C**************@s**********.com
Narrative
Operator crews were in the process of replacing a valve on a 12" steel main at the referenced address. A segment had been disconnected and removed by use of stopper fittings. The remaining in-service main was not secured by using anchors or other methods of reinforcement. Line pressure forced this segment of pipeline loose from an upstream coupling at approximately 12:45 pm on november 4. Gas was stopped at 3:45 pm the same day. At approximately 4:20 pm the operator determined that this event would be reportable due to estimating the unintentional release of gas to exceed 3 million cubic feet.
Occurred At 2020-11-04 12:45:00
Year 2020
Report Received Date 2020-12-04 00:00:00
Iyear 2020.0
Report Number 20200123.0
Supplemental Number 34593.0
Report Type Original Final
Operator Id 180 PHMSA Enforcement
Name Spire Alabama Inc.
Operator Street Address 605 Richard Arrington, Jr. Boulevard North
Operator City Name Birmingham
Operator State Abbreviation AL
Operator Postal Code 35203
Local Datetime 2020-11-04 16:20:00
Location Street Address 39th Avenue North And Fairmont St
Location City Name Birmingham
Location County Name Jefferson
Location State Abbreviation AL
Location Postal Code 35207
Location Latitude 33.561626 Google Maps OpenStreetMap
Location Longitude -86.814843 Google Maps OpenStreetMap
Nrc Rpt Datetime 2020-11-04 16:45:00
Nrc Rpt Num 1291420 NRC Report How to search
Commodity Released Type Natural Gas
Unintentional Release 8000.0
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Ignite Ind No
Explode Ind No
Num Pub Evacuated 10.0
Incident Identified Datetime 2020-11-04 12:45:00
On Site Datetime 2020-11-04 12:45:00
Federal No
Location Type Utility Right-Of-Way / Easement
Incident Area Type Underground
Incident Area Subtype Under Soil
Depth Of Cover 72.0
Crossing No
Pipe Facility Type Investor Owned
System Part Involved Main
Installation Year 1959.0
Pipe Diameter 12.0
Pipe Specification Unknown
Pipe Manufacturer Unknown
Material Involved Steel
Steel Seam Type Other
Steel Seam Type Details Unknown
Release Type Leak
Leak Type Connection Failure
Class Location Type Class 3 Location
Est Cost Oper Paid 0.0
Est Cost Prop Damage 20260.0
Est Cost Emergency 8001.0
Est Cost Other 0.0
Est Cost Unintentional Release 20880.0
Prpty 49141.0
Commercial Affected 0.0
Industrial Affected 0.0
Residences Affected 10.0
Accident Psig 146.0
Normal Psig 146.0
Mop Psig 150.0
Accident Pressure Pressure Did Not Exceed Maop
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind No
Scada Conf Ind Yes
Accident Identifier Local Operating Personnel, Including Contractors
Operator Type Operator Employee
Investigation Status No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details It was apparent that the incident was not caused by control room actions.
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Incorrect Operation
Cause Details Other Incorrect Operation
Operation Type Other Incorrect Operation
Operation Details Pipe Segment Was Not Effectively Anchored During Construction Replacement.
Related Inadequate Proc Ind Yes
Category Type Construction
Operator Qualification Ind No
Preparer Name B*** M****
Preparer Title Pipeline Safety Manager
Preparer Email B*********@s**********.com
Preparer Telephone 2512889616
Authorizer Name C**** H********
Authorizer Title Vice President Operations Services And Sms
Authorizer Telephone 3143492972
Authorizer Email C**************@s**********.com
Narrative Operator crews were in the process of replacing a valve on a 12" steel main at the referenced address. A segment had been disconnected and removed by use of stopper fittings. The remaining in-service main was not secured by using anchors or other methods of reinforcement. Line pressure forced this segment of pipeline loose from an upstream coupling at approximately 12:45 pm on november 4. Gas was stopped at 3:45 pm the same day. At approximately 4:20 pm the operator determined that this event would be reportable due to estimating the unintentional release of gas to exceed 3 million cubic feet.