HL incident on 2019-11-13 — PA

Operator
Buckeye Partners, Lp
Cause
Equipment Failure
Commodity
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$0
Incident datetime
2019-11-13 11:31
Report number
Location
PA
Narrative
On november 13, 2019, at approximately 11:30, all motor operated valves (movs) and emergency shutdown devices (esds) associated with the 5000 area at buckeye texas processing (btp) closed. At approximately 11:31, buckeye personnel discovered that a pressure relief valve (prv) on a coalescer began venting to atmosphere. After immediately contacting the control center to determine which bullet tank to route product to, the buckeye employee opened the appropriate tank inlet valves which stopped the propane release to the atmosphere. It has been concluded that the movs and esds associated with the 5000 area closed due to the loss of communications. The loss of communications has been attributed to a network switch going bad. The network switch has been replaced and the pipeline was put back into service on november 13, 2019 at approximately 20:20.
Detailed record list
Report Received Date
2019-12-12 00:00:00
Iyear
2019
Report Number
20190378
Supplemental Number
33535
Report Type
Supplemental Final
Operator Id
Name
Buckeye Partners, Lp
Operator Street Address
The Buckeye Building 6161 Hamilton Boulevar
Operator City Name
Allentown
Operator State Abbreviation
PA
Operator Postal Code
18106
Local Datetime
2019-11-13 11:30:00
Location Latitude
Location Longitude
Commodity Released Type
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Commodity Subtype
Other Hvl
Commodity Details
Propane
Unintentional Release Bbls
4.4
Intentional Release Bbls
0
Recovered Bbls
0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Operator Employee
Incident Identified Datetime
2019-11-13 11:31:00
System Part Involved
Onshore Terminal/tank Farm Equipment And Piping
On Off Shore
Onshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2019-11-13 11:30:00
Restart Datetime
2019-11-13 19:25:00
On Site Datetime
2019-11-13 11:31:00
Nrc Rpt Num
Nrc Notification Not Required
Ignite Ind
No
Explode Ind
No
Num Pub Evacuated
0
Pipe Fac Name
Buckeye Texas Processing
Segment Name
5-Lpg-6491
Onshore State Abbreviation
Tx
Onshore Postal Code
78409
Onshore City Name
Corpus Christi
Onshore County Name
Nueces
Designated Location
Milepost/valve Station
Designated Name
Lpg Coalescer
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Aboveground
Incident Area Subtype
Typical Aboveground Facility Piping Or Appurtenance
Crossing
No
Pipe Facility Type
Intrastate
Item Involved
Relief Line And Relief Equipment
Installation Year
2014
Material Involved
Carbon Steel
Release Type
Other
Release Type Details
Relief Device Vented To The Atmosphere
Wildlife Impact Ind
No
Soil Contamination
No
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
Yes
Other Pop Ind
Yes
Other Pop Yes No
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
444
Est Cost Prop Damage
0
Est Cost Emergency
0
Est Cost Environmental
0
Est Cost Other
0
Prpty
444
Accident Psig
275
Mop Psig
340
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Pipeline Function
< 20% Smys Regulated Transmission
Scada In Place Ind
No
Cpm In Place Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
It has been determined that operator error is not associated with this release.
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Equipment Failure
Cause Details
Other Equipment Failure
Eq Failure Type
Other Equipment Failure
Failure Details
Loss Of Communications
Eq Additional Other Ind
Yes
Eq Additional Other Details
Network Switch Went Bad
Preparer Name
V****** G**************
Preparer Title
Process Safetey Engineer
Preparer Email
V***************@b******.com
Preparer Telephone
361-792-3083
Prepared Date
2020-03-30 00:00:00
Authorizer Name
C****** P********
Authorizer Telephone
610-904-4113
Authorizer Title
Director Regulatory Compliance
Authorizer Email
C*********@b******.com
Narrative
On november 13, 2019, at approximately 11:30, all motor operated valves (movs) and emergency shutdown devices (esds) associated with the 5000 area at buckeye texas processing (btp) closed. At approximately 11:31, buckeye personnel discovered that a pressure relief valve (prv) on a coalescer began venting to atmosphere. After immediately contacting the control center to determine which bullet tank to route product to, the buckeye employee opened the appropriate tank inlet valves which stopped the propane release to the atmosphere. It has been concluded that the movs and esds associated with the 5000 area closed due to the loss of communications. The loss of communications has been attributed to a network switch going bad. The network switch has been replaced and the pipeline was put back into service on november 13, 2019 at approximately 20:20.
Report Received Date 2019-12-12 00:00:00
Iyear 2019
Report Number 20190378
Supplemental Number 33535
Report Type Supplemental Final
Operator Id 1845 PHMSA Enforcement
Name Buckeye Partners, Lp
Operator Street Address The Buckeye Building 6161 Hamilton Boulevar
Operator City Name Allentown
Operator State Abbreviation PA
Operator Postal Code 18106
Local Datetime 2019-11-13 11:30:00
Location Latitude 27.816006 Google Maps OpenStreetMap
Location Longitude -97.505322 Google Maps OpenStreetMap
Commodity Released Type Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Commodity Subtype Other Hvl
Commodity Details Propane
Unintentional Release Bbls 4.4
Intentional Release Bbls 0
Recovered Bbls 0
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Local Operating Personnel, Including Contractors
Operator Type Operator Employee
Incident Identified Datetime 2019-11-13 11:31:00
System Part Involved Onshore Terminal/tank Farm Equipment And Piping
On Off Shore Onshore
Shutdown Due Accident Ind Yes
Shutdown Datetime 2019-11-13 11:30:00
Restart Datetime 2019-11-13 19:25:00
On Site Datetime 2019-11-13 11:31:00
Nrc Rpt Num Nrc Notification Not Required NRC Report How to search
Ignite Ind No
Explode Ind No
Num Pub Evacuated 0
Pipe Fac Name Buckeye Texas Processing
Segment Name 5-Lpg-6491
Onshore State Abbreviation Tx
Onshore Postal Code 78409
Onshore City Name Corpus Christi
Onshore County Name Nueces
Designated Location Milepost/valve Station
Designated Name Lpg Coalescer
Federal No
Location Type Totally Contained On Operator-Controlled Property
Incident Area Type Aboveground
Incident Area Subtype Typical Aboveground Facility Piping Or Appurtenance
Crossing No
Pipe Facility Type Intrastate
Item Involved Relief Line And Relief Equipment
Installation Year 2014
Material Involved Carbon Steel
Release Type Other
Release Type Details Relief Device Vented To The Atmosphere
Wildlife Impact Ind No
Soil Contamination No
Long Term Assessment No
Remediation Ind No
Water Contam Ind No
Could Be Hca Yes
Commodity Reached Hca Yes
Other Pop Ind Yes
Other Pop Yes No Yes
Est Cost Oper Paid 0
Est Cost Gas Released 444
Est Cost Prop Damage 0
Est Cost Emergency 0
Est Cost Environmental 0
Est Cost Other 0
Prpty 444
Accident Psig 275
Mop Psig 340
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Pipeline Function < 20% Smys Regulated Transmission
Scada In Place Ind No
Cpm In Place Ind No
Investigation Status No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details It has been determined that operator error is not associated with this release.
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Equipment Failure
Cause Details Other Equipment Failure
Eq Failure Type Other Equipment Failure
Failure Details Loss Of Communications
Eq Additional Other Ind Yes
Eq Additional Other Details Network Switch Went Bad
Preparer Name V****** G**************
Preparer Title Process Safetey Engineer
Preparer Email V***************@b******.com
Preparer Telephone 361-792-3083
Prepared Date 2020-03-30 00:00:00
Authorizer Name C****** P********
Authorizer Telephone 610-904-4113
Authorizer Title Director Regulatory Compliance
Authorizer Email C*********@b******.com
Narrative On november 13, 2019, at approximately 11:30, all motor operated valves (movs) and emergency shutdown devices (esds) associated with the 5000 area at buckeye texas processing (btp) closed. At approximately 11:31, buckeye personnel discovered that a pressure relief valve (prv) on a coalescer began venting to atmosphere. After immediately contacting the control center to determine which bullet tank to route product to, the buckeye employee opened the appropriate tank inlet valves which stopped the propane release to the atmosphere. It has been concluded that the movs and esds associated with the 5000 area closed due to the loss of communications. The loss of communications has been attributed to a network switch going bad. The network switch has been replaced and the pipeline was put back into service on november 13, 2019 at approximately 20:20.