Incident details
Operator, cause, commodity and consequences with raw source fields.
HL incident on 2019-07-16 — TX
Operator
Sunoco Partners Marketing & Terminals Lp
Cause
Equipment Failure
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$6,500
Incident datetime
2019-07-16 22:15
Report number
Location
TX
Narrative
At approximately 22:15 on 7/16/19 a release was identified by operating personnel at the texoma manifold sump. While making an inbound delivery switch to tank 1533 the facility line shut down due to overpressure. Preceding the overpressure, valve t385 was given an open command by local control center and indicated an open status shortly after. With open path available the operator then closed off prior delivery line up to make the switch to tank 1533. The pressure relief valves on the line activated flow into the sump and the delivery shutdown. The rate of relief overwhelmed sump pump capacity and it overflowed releasing approximately 4 bbls of crude. Osro crews were dispatched to clean up free product and remove contaminated soil for onsite remediation. Investigation revealed that the valve stem on valve t385 had separated from the gate allowing the stem to move to an open position and trigger open position status in scada. The valve is awaiting replacement and line up has been configured as to bypass this valve in the interim period until replacement. Upon removal the valve will be inspected for determination of cause of stem separation. Supplemental report will be filed after investigation is complete. Supplemental information - the valve was replaced and the failed valve was examined for cause of stem separation from gate. It was determined by visual analysis that the separation between the valve stem and gate was due to metal fatigue.
Detailed record list
Report Received Date
2019-08-15 00:00:00
Iyear
2019
Report Number
20190255
Supplemental Number
32810
Report Type
Supplemental Final
Operator Id
39706
Name
Sunoco Partners Marketing & Terminals Lp
Operator Street Address
1300 Main Street
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2019-07-16 22:15:00
Location Latitude
29.991667
Location Longitude
-93.991388
Commodity Released Type
Crude Oil
Unintentional Release Bbls
4
Recovered Bbls
4
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Operator Employee
Incident Identified Datetime
2019-07-16 22:15:00
System Part Involved
Onshore Terminal/tank Farm Equipment And Piping
On Off Shore
Onshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2019-07-16 22:15:00
Restart Datetime
2019-07-17 00:40:00
On Site Datetime
2019-07-16 22:15:00
Nrc Rpt Num
Nrc Notification Not Required
Ignite Ind
No
Explode Ind
No
Num Pub Evacuated
0
Pipe Fac Name
Nederland Terminal
Segment Name
Texoma Manifold
Onshore State Abbreviation
Tx
Onshore Postal Code
77627
Onshore City Name
Nederland
Onshore County Name
Jefferson
Designated Location
Survey Station No.
Designated Name
0+00
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Aboveground
Incident Area Subtype
Typical Aboveground Facility Piping Or Appurtenance
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Sump
Installation Year
Unknown
Material Involved
Carbon Steel
Release Type
Overfill Or Overflow
Wildlife Impact Ind
No
Soil Contamination
No
Long Term Assessment
No
Remediation Ind
Yes
Soil Remed Ind
Yes
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
Yes
High Pop Ind
Yes
High Pop Yes No
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
200
Est Cost Prop Damage
6500
Est Cost Emergency
9600
Est Cost Environmental
2500
Est Cost Other
0
Prpty
18800
Accident Psig
316
Mop Psig
250
Accident Pressure
Pressure Exceeded 110% Of Mop
Pressure Restriction Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
Yes
Scada Conf Ind
No
Cpm In Place Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
A review of the accident determined that there were no control room actions that contributed to the event.
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Equipment Failure
Cause Details
Other Equipment Failure
Eq Failure Type
Other Equipment Failure
Failure Details
Valve Stem Separated From Gate Causing Valve To Not Open Which Caused Overpressure, Relief Event And Overflow Of Sump.
Eq Additional Other Ind
Yes
Eq Additional Other Details
Metal Fatigue
Preparer Name
T*** N*******
Preparer Title
Sr. Manager - Dot Compliance
Preparer Email
T************@e*************.com
Preparer Telephone
713-989-7126
Preparer Fax
877-917-0448
Prepared Date
2019-10-14 00:00:00
Authorizer Name
T*** N*******
Authorizer Telephone
713-989-7126
Authorizer Title
Sr. Manager - Dot Compliance
Authorizer Email
T************@e*************.com
Narrative
At approximately 22:15 on 7/16/19 a release was identified by operating personnel at the texoma manifold sump. While making an inbound delivery switch to tank 1533 the facility line shut down due to overpressure. Preceding the overpressure, valve t385 was given an open command by local control center and indicated an open status shortly after. With open path available the operator then closed off prior delivery line up to make the switch to tank 1533. The pressure relief valves on the line activated flow into the sump and the delivery shutdown. The rate of relief overwhelmed sump pump capacity and it overflowed releasing approximately 4 bbls of crude. Osro crews were dispatched to clean up free product and remove contaminated soil for onsite remediation. Investigation revealed that the valve stem on valve t385 had separated from the gate allowing the stem to move to an open position and trigger open position status in scada. The valve is awaiting replacement and line up has been configured as to bypass this valve in the interim period until replacement. Upon removal the valve will be inspected for determination of cause of stem separation. Supplemental report will be filed after investigation is complete. Supplemental information - the valve was replaced and the failed valve was examined for cause of stem separation from gate. It was determined by visual analysis that the separation between the valve stem and gate was due to metal fatigue.
| Report Received Date | 2019-08-15 00:00:00 |
|---|---|
| Iyear | 2019 |
| Report Number | 20190255 |
| Supplemental Number | 32810 |
| Report Type | Supplemental Final |
| Operator Id | 39706 PHMSA Enforcement |
| Name | Sunoco Partners Marketing & Terminals Lp |
| Operator Street Address | 1300 Main Street |
| Operator City Name | Houston |
| Operator State Abbreviation | TX |
| Operator Postal Code | 77002 |
| Local Datetime | 2019-07-16 22:15:00 |
| Location Latitude | 29.991667 Google Maps OpenStreetMap |
| Location Longitude | -93.991388 Google Maps OpenStreetMap |
| Commodity Released Type | Crude Oil |
| Unintentional Release Bbls | 4 |
| Recovered Bbls | 4 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Local Operating Personnel, Including Contractors |
| Operator Type | Operator Employee |
| Incident Identified Datetime | 2019-07-16 22:15:00 |
| System Part Involved | Onshore Terminal/tank Farm Equipment And Piping |
| On Off Shore | Onshore |
| Shutdown Due Accident Ind | Yes |
| Shutdown Datetime | 2019-07-16 22:15:00 |
| Restart Datetime | 2019-07-17 00:40:00 |
| On Site Datetime | 2019-07-16 22:15:00 |
| Nrc Rpt Num | Nrc Notification Not Required NRC Report How to search |
| Ignite Ind | No |
| Explode Ind | No |
| Num Pub Evacuated | 0 |
| Pipe Fac Name | Nederland Terminal |
| Segment Name | Texoma Manifold |
| Onshore State Abbreviation | Tx |
| Onshore Postal Code | 77627 |
| Onshore City Name | Nederland |
| Onshore County Name | Jefferson |
| Designated Location | Survey Station No. |
| Designated Name | 0+00 |
| Federal | No |
| Location Type | Totally Contained On Operator-Controlled Property |
| Incident Area Type | Aboveground |
| Incident Area Subtype | Typical Aboveground Facility Piping Or Appurtenance |
| Crossing | No |
| Pipe Facility Type | Interstate |
| Item Involved | Sump |
| Installation Year | Unknown |
| Material Involved | Carbon Steel |
| Release Type | Overfill Or Overflow |
| Wildlife Impact Ind | No |
| Soil Contamination | No |
| Long Term Assessment | No |
| Remediation Ind | Yes |
| Soil Remed Ind | Yes |
| Water Contam Ind | No |
| Could Be Hca | Yes |
| Commodity Reached Hca | Yes |
| High Pop Ind | Yes |
| High Pop Yes No | Yes |
| Est Cost Oper Paid | 0 |
| Est Cost Gas Released | 200 |
| Est Cost Prop Damage | 6500 |
| Est Cost Emergency | 9600 |
| Est Cost Environmental | 2500 |
| Est Cost Other | 0 |
| Prpty | 18800 |
| Accident Psig | 316 |
| Mop Psig | 250 |
| Accident Pressure | Pressure Exceeded 110% Of Mop |
| Pressure Restriction Ind | No |
| Pipeline Function | > 20% Smys Regulated Transmission |
| Scada In Place Ind | Yes |
| Scada Operating Ind | Yes |
| Scada Functional Ind | Yes |
| Scada Detection Ind | Yes |
| Scada Conf Ind | No |
| Cpm In Place Ind | No |
| Investigation Status | No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate) |
| Investigation Status Details | A review of the accident determined that there were no control room actions that contributed to the event. |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | No |
| Cause | Equipment Failure |
| Cause Details | Other Equipment Failure |
| Eq Failure Type | Other Equipment Failure |
| Failure Details | Valve Stem Separated From Gate Causing Valve To Not Open Which Caused Overpressure, Relief Event And Overflow Of Sump. |
| Eq Additional Other Ind | Yes |
| Eq Additional Other Details | Metal Fatigue |
| Preparer Name | T*** N******* |
| Preparer Title | Sr. Manager - Dot Compliance |
| Preparer Email | T************@e*************.com |
| Preparer Telephone | 713-989-7126 |
| Preparer Fax | 877-917-0448 |
| Prepared Date | 2019-10-14 00:00:00 |
| Authorizer Name | T*** N******* |
| Authorizer Telephone | 713-989-7126 |
| Authorizer Title | Sr. Manager - Dot Compliance |
| Authorizer Email | T************@e*************.com |
| Narrative | At approximately 22:15 on 7/16/19 a release was identified by operating personnel at the texoma manifold sump. While making an inbound delivery switch to tank 1533 the facility line shut down due to overpressure. Preceding the overpressure, valve t385 was given an open command by local control center and indicated an open status shortly after. With open path available the operator then closed off prior delivery line up to make the switch to tank 1533. The pressure relief valves on the line activated flow into the sump and the delivery shutdown. The rate of relief overwhelmed sump pump capacity and it overflowed releasing approximately 4 bbls of crude. Osro crews were dispatched to clean up free product and remove contaminated soil for onsite remediation. Investigation revealed that the valve stem on valve t385 had separated from the gate allowing the stem to move to an open position and trigger open position status in scada. The valve is awaiting replacement and line up has been configured as to bypass this valve in the interim period until replacement. Upon removal the valve will be inspected for determination of cause of stem separation. Supplemental report will be filed after investigation is complete. Supplemental information - the valve was replaced and the failed valve was examined for cause of stem separation from gate. It was determined by visual analysis that the separation between the valve stem and gate was due to metal fatigue. |