HL incident on 2019-05-29 — TX
Operator
Mid - Valley Pipeline Co
Cause
Incorrect Operation
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$0
Incident datetime
2019-05-29 10:35
Report number
Location
TX
Narrative
On 5/29/19 at approximately 10:35 am, operations employee was opening the external floating roof drains on tanks at lima station to drain standing water on the tank roofs. After the draining of tank 112 roof began it was identified that the water draining from the roof contained a sheen. Upon identification the drain was closed. Notifications were made to management and cleanup began. Estimated 8 gallons was released and mixed with water from the roof drain. All free product was recovered and contaminated soil was removed for remediation on site. It was determined that a small amount residual product mixed with the water on the roof and was released when the roof drain was opened. Source of residual product on roof was from warming temperatures that allow paraffin buildup on tank walls to liquify. This paraffin solidifies in the winter months on the tank walls. Tank roof was subsequently inspected by contract API 653 inspector and no issues were identified with the seal or pontoons. To prevent recurrence roof will be inspected prior to opening of roof drains.
Detailed record list
Report Received Date
2019-06-28 00:00:00
Iyear
2019
Report Number
20190208
Supplemental Number
32766
Report Type
Supplemental Final
Operator Id
12470
Name
Mid - Valley Pipeline Co
Operator Street Address
1300 Main Street
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2019-05-29 10:35:00
Location Latitude
40.70666
Location Longitude
-84.12268
Commodity Released Type
Crude Oil
Unintentional Release Bbls
0.19
Recovered Bbls
0.19
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Operator Employee
Incident Identified Datetime
2019-05-29 10:35:00
System Part Involved
Onshore Breakout Tank Or Storage Vessel, Including Attached Appurtenances
On Off Shore
Onshore
Shutdown Due Accident Ind
No
Shutdown Explain
No Product Movement Was Scheduled From The Tank
On Site Datetime
2019-05-29 10:35:00
Nrc Rpt Num
Nrc Notification Not Required
Ignite Ind
No
Explode Ind
No
Num Pub Evacuated
0
Pipe Fac Name
Lima Station
Segment Name
Tank 112
Onshore State Abbreviation
Oh
Onshore Postal Code
45804
Onshore City Name
Lima
Onshore County Name
Allen
Designated Location
Milepost/valve Station
Designated Name
0+00
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Tank, Including Attached Appurtenances
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Tank/vessel
Tank Vessel Subtype
Roof Drain System
Tank Type
Atmospheric
Installation Year
2000
Material Involved
Carbon Steel
Release Type
Other
Release Type Details
Residual Crude Oil/water Mix Released Via Roof Drain System.
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
Yes
Soil Remed Ind
Yes
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
Yes
High Pop Ind
Yes
High Pop Yes No
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
10
Est Cost Prop Damage
0
Est Cost Emergency
5542
Est Cost Environmental
1500
Est Cost Other
0
Prpty
7052
Accident Psig
27.5
Mop Psig
285
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
No
Investigation Status
Yes, specify investigation result(s): (select all that apply)
Invest Schedule Ind
Yes
Invest No Control Room Ind
Yes
Invest No Controller Ind
Yes
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Incorrect Operation
Cause Details
Other Incorrect Operation
Operation Type
Other Incorrect Operation
Operation Details
Roof Drain System Was Opened Prior To Inspecting Roof.
Related Inadequate Proc Ind
Yes
Category Type
Normal Operating Conditions
Operator Qualification Ind
Yes
Qualified Individuals
Yes, They Were Qualified For The Task(S)
Preparer Name
T*** N*******
Preparer Title
Sr. Manager - Dot Compliance
Preparer Email
T************@e*************.com
Preparer Telephone
713-989-7126
Preparer Fax
877-917-0448
Prepared Date
2019-09-30 00:00:00
Authorizer Name
T*** N*******
Authorizer Telephone
713-989-7126
Authorizer Title
Sr. Manager - Dot Compliance
Authorizer Email
T************@e*************.com
Narrative
On 5/29/19 at approximately 10:35 am, operations employee was opening the external floating roof drains on tanks at lima station to drain standing water on the tank roofs. After the draining of tank 112 roof began it was identified that the water draining from the roof contained a sheen. Upon identification the drain was closed. Notifications were made to management and cleanup began. Estimated 8 gallons was released and mixed with water from the roof drain. All free product was recovered and contaminated soil was removed for remediation on site. It was determined that a small amount residual product mixed with the water on the roof and was released when the roof drain was opened. Source of residual product on roof was from warming temperatures that allow paraffin buildup on tank walls to liquify. This paraffin solidifies in the winter months on the tank walls. Tank roof was subsequently inspected by contract API 653 inspector and no issues were identified with the seal or pontoons. To prevent recurrence roof will be inspected prior to opening of roof drains.
| Report Received Date | 2019-06-28 00:00:00 |
|---|---|
| Iyear | 2019 |
| Report Number | 20190208 |
| Supplemental Number | 32766 |
| Report Type | Supplemental Final |
| Operator Id | 12470 PHMSA Enforcement |
| Name | Mid - Valley Pipeline Co |
| Operator Street Address | 1300 Main Street |
| Operator City Name | Houston |
| Operator State Abbreviation | TX |
| Operator Postal Code | 77002 |
| Local Datetime | 2019-05-29 10:35:00 |
| Location Latitude | 40.70666 Google Maps OpenStreetMap |
| Location Longitude | -84.12268 Google Maps OpenStreetMap |
| Commodity Released Type | Crude Oil |
| Unintentional Release Bbls | 0.19 |
| Recovered Bbls | 0.19 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Local Operating Personnel, Including Contractors |
| Operator Type | Operator Employee |
| Incident Identified Datetime | 2019-05-29 10:35:00 |
| System Part Involved | Onshore Breakout Tank Or Storage Vessel, Including Attached Appurtenances |
| On Off Shore | Onshore |
| Shutdown Due Accident Ind | No |
| Shutdown Explain | No Product Movement Was Scheduled From The Tank |
| On Site Datetime | 2019-05-29 10:35:00 |
| Nrc Rpt Num | Nrc Notification Not Required NRC Report How to search |
| Ignite Ind | No |
| Explode Ind | No |
| Num Pub Evacuated | 0 |
| Pipe Fac Name | Lima Station |
| Segment Name | Tank 112 |
| Onshore State Abbreviation | Oh |
| Onshore Postal Code | 45804 |
| Onshore City Name | Lima |
| Onshore County Name | Allen |
| Designated Location | Milepost/valve Station |
| Designated Name | 0+00 |
| Federal | No |
| Location Type | Totally Contained On Operator-Controlled Property |
| Incident Area Type | Tank, Including Attached Appurtenances |
| Crossing | No |
| Pipe Facility Type | Interstate |
| Item Involved | Tank/vessel |
| Tank Vessel Subtype | Roof Drain System |
| Tank Type | Atmospheric |
| Installation Year | 2000 |
| Material Involved | Carbon Steel |
| Release Type | Other |
| Release Type Details | Residual Crude Oil/water Mix Released Via Roof Drain System. |
| Wildlife Impact Ind | No |
| Soil Contamination | Yes |
| Long Term Assessment | No |
| Remediation Ind | Yes |
| Soil Remed Ind | Yes |
| Water Contam Ind | No |
| Could Be Hca | Yes |
| Commodity Reached Hca | Yes |
| High Pop Ind | Yes |
| High Pop Yes No | Yes |
| Est Cost Oper Paid | 0 |
| Est Cost Gas Released | 10 |
| Est Cost Prop Damage | 0 |
| Est Cost Emergency | 5542 |
| Est Cost Environmental | 1500 |
| Est Cost Other | 0 |
| Prpty | 7052 |
| Accident Psig | 27.5 |
| Mop Psig | 285 |
| Accident Pressure | Pressure Did Not Exceed Mop |
| Pressure Restriction Ind | No |
| Pipeline Function | > 20% Smys Regulated Transmission |
| Scada In Place Ind | Yes |
| Scada Operating Ind | Yes |
| Scada Functional Ind | Yes |
| Scada Detection Ind | No |
| Scada Conf Ind | No |
| Cpm In Place Ind | No |
| Investigation Status | Yes, specify investigation result(s): (select all that apply) |
| Invest Schedule Ind | Yes |
| Invest No Control Room Ind | Yes |
| Invest No Controller Ind | Yes |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | No |
| Cause | Incorrect Operation |
| Cause Details | Other Incorrect Operation |
| Operation Type | Other Incorrect Operation |
| Operation Details | Roof Drain System Was Opened Prior To Inspecting Roof. |
| Related Inadequate Proc Ind | Yes |
| Category Type | Normal Operating Conditions |
| Operator Qualification Ind | Yes |
| Qualified Individuals | Yes, They Were Qualified For The Task(S) |
| Preparer Name | T*** N******* |
| Preparer Title | Sr. Manager - Dot Compliance |
| Preparer Email | T************@e*************.com |
| Preparer Telephone | 713-989-7126 |
| Preparer Fax | 877-917-0448 |
| Prepared Date | 2019-09-30 00:00:00 |
| Authorizer Name | T*** N******* |
| Authorizer Telephone | 713-989-7126 |
| Authorizer Title | Sr. Manager - Dot Compliance |
| Authorizer Email | T************@e*************.com |
| Narrative | On 5/29/19 at approximately 10:35 am, operations employee was opening the external floating roof drains on tanks at lima station to drain standing water on the tank roofs. After the draining of tank 112 roof began it was identified that the water draining from the roof contained a sheen. Upon identification the drain was closed. Notifications were made to management and cleanup began. Estimated 8 gallons was released and mixed with water from the roof drain. All free product was recovered and contaminated soil was removed for remediation on site. It was determined that a small amount residual product mixed with the water on the roof and was released when the roof drain was opened. Source of residual product on roof was from warming temperatures that allow paraffin buildup on tank walls to liquify. This paraffin solidifies in the winter months on the tank walls. Tank roof was subsequently inspected by contract API 653 inspector and no issues were identified with the seal or pontoons. To prevent recurrence roof will be inspected prior to opening of roof drains. |