Incident details
Operator, cause, commodity and consequences with raw source fields.
HL incident on 2019-05-08 — TX
Operator
Nustar Logistics, L.p.
Cause
Equipment Failure
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$120
Incident datetime
2019-05-08 04:49
Report number
Location
TX
Narrative
During a weather-related power outage, a nustar employee discovered a crude oil leak at nustar's wichita falls pump station while preparing the station for restart. A 3/4-inch steel cooling tubing separated from the station's unit no. 2 outboard bearing. A pressure spike within the unit no. 2 suction piping, caused by the failure of a pump station check valve, contributed to the failure of the tubing fitting. The tubing fitting has been removed and sent to a laboratory for analysis. The tubing fitting and check valve have been replaced. Update - the failure was due to incomplete installation of the tubing in the fitting. Fitting ferrules were inadequately seated on the tubing.
Detailed record list
Report Received Date
2019-06-07 00:00:00
Iyear
2019
Report Number
20190179
Supplemental Number
32497
Report Type
Supplemental Final
Operator Id
31454
Name
Nustar Logistics, L.p.
Operator Street Address
8111 Westchester Drive
Operator City Name
Dallas
Operator State Abbreviation
TX
Operator Postal Code
75225
Local Datetime
2019-05-08 03:51:00
Location Latitude
33.91311
Location Longitude
-98.43587
Commodity Released Type
Crude Oil
Unintentional Release Bbls
0.4
Recovered Bbls
0.4
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Operator Employee
Incident Identified Datetime
2019-05-08 04:49:00
System Part Involved
Onshore Pump/meter Station Equipment And Piping
On Off Shore
Onshore
Shutdown Due Accident Ind
No
Shutdown Explain
The Station Was Down Due To A Weather-Related Power Outage
On Site Datetime
2019-05-08 04:49:00
Nrc Rpt Num
Nrc Notification Not Required
Ignite Ind
No
Explode Ind
No
Num Pub Evacuated
0
Pipe Fac Name
16p Wichita Falls -Mckee Pipeline System
Segment Name
Wichita Falls Pump Station
Onshore State Abbreviation
Tx
Onshore Postal Code
76305
Onshore City Name
Not Within A Municipality
Onshore County Name
Wichita
Designated Location
Milepost/valve Station
Designated Name
0+00
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Aboveground
Incident Area Subtype
Typical Aboveground Facility Piping Or Appurtenance
Crossing
No
Pipe Facility Type
Intrastate
Item Involved
Tubing
Installation Year
Unknown
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Connection Failure
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
0
Est Cost Gas Released
25
Est Cost Prop Damage
120
Est Cost Emergency
1800
Est Cost Environmental
11608
Est Cost Other
2962
Est Cost Other Details
Laboratory Costs
Prpty
16515
Accident Psig
957
Mop Psig
1480
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
Yes
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
Neither nustar controller nor control room issues contributed to the accident. See parts g & h of this report
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Equipment Failure
Cause Details
Defective Or Loose Tubing Or Fitting
Eq Failure Type
Defective Or Loose Tubing Or Fitting
Additional Installation Ind
Yes
Preparer Name
R****** P****
Preparer Title
Pipeline Safety Supervisor
Preparer Email
R************@n***********.com
Preparer Telephone
361-249-9417
Preparer Fax
210-918-7117
Prepared Date
2019-08-01 00:00:00
Authorizer Name
J**** R********
Authorizer Telephone
806-371-1304
Authorizer Title
General Manager
Authorizer Email
J**************@n***********.com
Narrative
During a weather-related power outage, a nustar employee discovered a crude oil leak at nustar's wichita falls pump station while preparing the station for restart. A 3/4-inch steel cooling tubing separated from the station's unit no. 2 outboard bearing. A pressure spike within the unit no. 2 suction piping, caused by the failure of a pump station check valve, contributed to the failure of the tubing fitting. The tubing fitting has been removed and sent to a laboratory for analysis. The tubing fitting and check valve have been replaced. Update - the failure was due to incomplete installation of the tubing in the fitting. Fitting ferrules were inadequately seated on the tubing.
| Report Received Date | 2019-06-07 00:00:00 |
|---|---|
| Iyear | 2019 |
| Report Number | 20190179 |
| Supplemental Number | 32497 |
| Report Type | Supplemental Final |
| Operator Id | 31454 PHMSA Enforcement |
| Name | Nustar Logistics, L.p. |
| Operator Street Address | 8111 Westchester Drive |
| Operator City Name | Dallas |
| Operator State Abbreviation | TX |
| Operator Postal Code | 75225 |
| Local Datetime | 2019-05-08 03:51:00 |
| Location Latitude | 33.91311 Google Maps OpenStreetMap |
| Location Longitude | -98.43587 Google Maps OpenStreetMap |
| Commodity Released Type | Crude Oil |
| Unintentional Release Bbls | 0.4 |
| Recovered Bbls | 0.4 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Local Operating Personnel, Including Contractors |
| Operator Type | Operator Employee |
| Incident Identified Datetime | 2019-05-08 04:49:00 |
| System Part Involved | Onshore Pump/meter Station Equipment And Piping |
| On Off Shore | Onshore |
| Shutdown Due Accident Ind | No |
| Shutdown Explain | The Station Was Down Due To A Weather-Related Power Outage |
| On Site Datetime | 2019-05-08 04:49:00 |
| Nrc Rpt Num | Nrc Notification Not Required NRC Report How to search |
| Ignite Ind | No |
| Explode Ind | No |
| Num Pub Evacuated | 0 |
| Pipe Fac Name | 16p Wichita Falls -Mckee Pipeline System |
| Segment Name | Wichita Falls Pump Station |
| Onshore State Abbreviation | Tx |
| Onshore Postal Code | 76305 |
| Onshore City Name | Not Within A Municipality |
| Onshore County Name | Wichita |
| Designated Location | Milepost/valve Station |
| Designated Name | 0+00 |
| Federal | No |
| Location Type | Totally Contained On Operator-Controlled Property |
| Incident Area Type | Aboveground |
| Incident Area Subtype | Typical Aboveground Facility Piping Or Appurtenance |
| Crossing | No |
| Pipe Facility Type | Intrastate |
| Item Involved | Tubing |
| Installation Year | Unknown |
| Material Involved | Carbon Steel |
| Release Type | Leak |
| Leak Type | Connection Failure |
| Wildlife Impact Ind | No |
| Soil Contamination | Yes |
| Long Term Assessment | No |
| Remediation Ind | No |
| Water Contam Ind | No |
| Could Be Hca | No |
| Commodity Reached Hca | No |
| Est Cost Oper Paid | 0 |
| Est Cost Gas Released | 25 |
| Est Cost Prop Damage | 120 |
| Est Cost Emergency | 1800 |
| Est Cost Environmental | 11608 |
| Est Cost Other | 2962 |
| Est Cost Other Details | Laboratory Costs |
| Prpty | 16515 |
| Accident Psig | 957 |
| Mop Psig | 1480 |
| Accident Pressure | Pressure Did Not Exceed Mop |
| Pressure Restriction Ind | No |
| Pipeline Function | > 20% Smys Regulated Transmission |
| Scada In Place Ind | Yes |
| Scada Operating Ind | Yes |
| Scada Functional Ind | Yes |
| Scada Detection Ind | No |
| Scada Conf Ind | No |
| Cpm In Place Ind | Yes |
| Cpm Operating Ind | Yes |
| Cpm Functional Ind | Yes |
| Cpm Detection Ind | No |
| Cpm Conf Ind | No |
| Investigation Status | No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate) |
| Investigation Status Details | Neither nustar controller nor control room issues contributed to the accident. See parts g & h of this report |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | No |
| Cause | Equipment Failure |
| Cause Details | Defective Or Loose Tubing Or Fitting |
| Eq Failure Type | Defective Or Loose Tubing Or Fitting |
| Additional Installation Ind | Yes |
| Preparer Name | R****** P**** |
| Preparer Title | Pipeline Safety Supervisor |
| Preparer Email | R************@n***********.com |
| Preparer Telephone | 361-249-9417 |
| Preparer Fax | 210-918-7117 |
| Prepared Date | 2019-08-01 00:00:00 |
| Authorizer Name | J**** R******** |
| Authorizer Telephone | 806-371-1304 |
| Authorizer Title | General Manager |
| Authorizer Email | J**************@n***********.com |
| Narrative | During a weather-related power outage, a nustar employee discovered a crude oil leak at nustar's wichita falls pump station while preparing the station for restart. A 3/4-inch steel cooling tubing separated from the station's unit no. 2 outboard bearing. A pressure spike within the unit no. 2 suction piping, caused by the failure of a pump station check valve, contributed to the failure of the tubing fitting. The tubing fitting has been removed and sent to a laboratory for analysis. The tubing fitting and check valve have been replaced. Update - the failure was due to incomplete installation of the tubing in the fitting. Fitting ferrules were inadequately seated on the tubing. |