Incident details
Operator, cause, commodity and consequences with raw source fields.
HL incident on 2018-09-26 — OK
Operator
Oneok Ngl Pipeline, Llc
Cause
Corrosion Failure
Commodity
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$45,000
Incident datetime
2018-09-26 11:29
Report number
Location
OK
Narrative
During the aerial patrol of the oneok creek pipeline on 9/26/2018 the pilot observed what appeared to be ice over the pipeline on the downstream side of slick rd. Local oneok field operator was contacted by the pilot and dispatched to the location. Field operator identified ice, dead vegetation and vapors coming on the right-of-way directly above the pipeline. Pipeline control and operations supervisor were contacted and the pipeline was shut down and the location was isolated. Repair crews excavated the pipeline and discovered a pinhole leak. A plidco mechanical repair clamp was installed and the pipeline returned to service. Oneok's investigation determined the interference causing the leak resulted from a negative cable being installed to the casing, instead of the mainline, by a contractor in september of 2017. The cable was associated with a new ground bed that had been installed in june of 2017 with the rectifier at the location being energized in november of 2017. 12/21/2018 correction - corrected part b, question 10 to show accident occurred on pipeline right of way. N.Jones
Detailed record list
Report Received Date
2018-10-24 00:00:00
Iyear
2018
Report Number
20180324
Supplemental Number
31384
Report Type
Supplemental
Operator Id
32109
Name
Oneok Ngl Pipeline, Llc
Operator Street Address
100 West Fifth Street
Operator City Name
Tulsa
Operator State Abbreviation
OK
Operator Postal Code
74103
Local Datetime
2018-09-26 11:30:00
Location Latitude
35.9000658
Location Longitude
-96.227408
Commodity Released Type
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Commodity Subtype
Lpg (Liquefied Petroleum Gas) / Ngl (Natural Gas Liquid)
Unintentional Release Bbls
2.7
Intentional Release Bbls
373
Recovered Bbls
0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Air Patrol
Operator Type
Contractor Working For The Operator
Incident Identified Datetime
2018-09-26 11:29:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2018-09-26 13:08:00
Restart Datetime
2018-09-29 13:00:00
On Site Datetime
2018-09-26 11:29:00
Nrc Rpt Datetime
2018-09-26 13:15:00
Nrc Rpt Num
1225773
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Manual
Downstream Valve Type Ind
Manual
Num Pub Evacuated
0
Pipe Fac Name
Oneok Creek Pipeline
Segment Name
Creek Plant To Carney Plant 6" (Index 10185)
Onshore State Abbreviation
Ok
Onshore Postal Code
74039
Onshore City Name
Not Within A Municipality
Onshore County Name
Creek
Designated Location
Survey Station No.
Designated Name
2750+69
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
72
Crossing
No
Pipe Facility Type
Intrastate
Item Involved
Pipe
Pipe Type
Pipe Body
Pipe Diameter
6
Pipe Wall Thickness
0.188
Pipe Smys
42000
Pipe Specification
Api 5l
Pipe Seam Type
Erw - High Frequency
Pipe Manufacturer
Textube
Pipe Coating Type
Cold Applied Tape
Installation Year
1986
Manufactured Year
1986
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Pinhole
Wildlife Impact Ind
No
Soil Contamination
No
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
0
Est Cost Gas Released
13220
Est Cost Prop Damage
45000
Est Cost Emergency
200
Est Cost Environmental
0
Est Cost Other
0
Prpty
58420
Accident Psig
760
Mop Psig
1440
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
22705
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
Yes
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
No controller actions had taken place prior to the release
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Corrosion Failure
Cause Details
External Corrosion
Internal External
External Corrosion
Visual Exam Results
Localized Pitting
Other Corrosion Ind
Yes
Corrosion Type Details
Interference Caused By Improper Negative Cable Installation
Field Exam Basis Ind
Yes
Underground Location
Yes
Under Cathodic Protection Ind
Yes
Cathodic Pro Start Year
1986
Shielding Evident
Yes
Cathodic Survey Type
Yes
Cp Annual Survey Ind
Yes
Cp Annual Survey Year
2017
Prior Damage
Yes
Collected Data Ind
Yes
Other Recent Year
2015
Has Hydrtst Conduc Before Ind
No
Direct Asmnt Conducted
No
Non Destructive Exam Ind
No
Preparer Name
N*** J****
Preparer Title
Requlatory Compliance Manager
Preparer Email
N*********@o****.com
Preparer Telephone
580-395-6304
Preparer Fax
580-395-2933
Prepared Date
2018-12-21 00:00:00
Authorizer Name
N*** J****
Authorizer Telephone
580-395-6304
Authorizer Title
Regulatory Compliance Manager
Authorizer Email
N*********@o****.com
Narrative
During the aerial patrol of the oneok creek pipeline on 9/26/2018 the pilot observed what appeared to be ice over the pipeline on the downstream side of slick rd. Local oneok field operator was contacted by the pilot and dispatched to the location. Field operator identified ice, dead vegetation and vapors coming on the right-of-way directly above the pipeline. Pipeline control and operations supervisor were contacted and the pipeline was shut down and the location was isolated. Repair crews excavated the pipeline and discovered a pinhole leak. A plidco mechanical repair clamp was installed and the pipeline returned to service. Oneok's investigation determined the interference causing the leak resulted from a negative cable being installed to the casing, instead of the mainline, by a contractor in september of 2017. The cable was associated with a new ground bed that had been installed in june of 2017 with the rectifier at the location being energized in november of 2017. 12/21/2018 correction - corrected part b, question 10 to show accident occurred on pipeline right of way. N.Jones
| Report Received Date | 2018-10-24 00:00:00 |
|---|---|
| Iyear | 2018 |
| Report Number | 20180324 |
| Supplemental Number | 31384 |
| Report Type | Supplemental |
| Operator Id | 32109 PHMSA Enforcement |
| Name | Oneok Ngl Pipeline, Llc |
| Operator Street Address | 100 West Fifth Street |
| Operator City Name | Tulsa |
| Operator State Abbreviation | OK |
| Operator Postal Code | 74103 |
| Local Datetime | 2018-09-26 11:30:00 |
| Location Latitude | 35.9000658 Google Maps OpenStreetMap |
| Location Longitude | -96.227408 Google Maps OpenStreetMap |
| Commodity Released Type | Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions |
| Commodity Subtype | Lpg (Liquefied Petroleum Gas) / Ngl (Natural Gas Liquid) |
| Unintentional Release Bbls | 2.7 |
| Intentional Release Bbls | 373 |
| Recovered Bbls | 0 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Air Patrol |
| Operator Type | Contractor Working For The Operator |
| Incident Identified Datetime | 2018-09-26 11:29:00 |
| System Part Involved | Onshore Pipeline, Including Valve Sites |
| On Off Shore | Onshore |
| Shutdown Due Accident Ind | Yes |
| Shutdown Datetime | 2018-09-26 13:08:00 |
| Restart Datetime | 2018-09-29 13:00:00 |
| On Site Datetime | 2018-09-26 11:29:00 |
| Nrc Rpt Datetime | 2018-09-26 13:15:00 |
| Nrc Rpt Num | 1225773 NRC Report How to search |
| Ignite Ind | No |
| Explode Ind | No |
| Upstream Valve Type Ind | Manual |
| Downstream Valve Type Ind | Manual |
| Num Pub Evacuated | 0 |
| Pipe Fac Name | Oneok Creek Pipeline |
| Segment Name | Creek Plant To Carney Plant 6" (Index 10185) |
| Onshore State Abbreviation | Ok |
| Onshore Postal Code | 74039 |
| Onshore City Name | Not Within A Municipality |
| Onshore County Name | Creek |
| Designated Location | Survey Station No. |
| Designated Name | 2750+69 |
| Federal | No |
| Location Type | Pipeline Right-Of-Way |
| Incident Area Type | Underground |
| Incident Area Subtype | Under Soil |
| Depth Of Cover | 72 |
| Crossing | No |
| Pipe Facility Type | Intrastate |
| Item Involved | Pipe |
| Pipe Type | Pipe Body |
| Pipe Diameter | 6 |
| Pipe Wall Thickness | 0.188 |
| Pipe Smys | 42000 |
| Pipe Specification | Api 5l |
| Pipe Seam Type | Erw - High Frequency |
| Pipe Manufacturer | Textube |
| Pipe Coating Type | Cold Applied Tape |
| Installation Year | 1986 |
| Manufactured Year | 1986 |
| Material Involved | Carbon Steel |
| Release Type | Leak |
| Leak Type | Pinhole |
| Wildlife Impact Ind | No |
| Soil Contamination | No |
| Long Term Assessment | No |
| Remediation Ind | No |
| Water Contam Ind | No |
| Could Be Hca | No |
| Commodity Reached Hca | No |
| Est Cost Oper Paid | 0 |
| Est Cost Gas Released | 13220 |
| Est Cost Prop Damage | 45000 |
| Est Cost Emergency | 200 |
| Est Cost Environmental | 0 |
| Est Cost Other | 0 |
| Prpty | 58420 |
| Accident Psig | 760 |
| Mop Psig | 1440 |
| Accident Pressure | Pressure Did Not Exceed Mop |
| Pressure Restriction Ind | No |
| Length Segment Isolated | 22705 |
| Internal Inspection Ind | Yes |
| Operation Complications Ind | No |
| Pipeline Function | > 20% Smys Regulated Transmission |
| Scada In Place Ind | Yes |
| Scada Operating Ind | Yes |
| Scada Functional Ind | Yes |
| Scada Detection Ind | No |
| Scada Conf Ind | No |
| Cpm In Place Ind | Yes |
| Cpm Operating Ind | Yes |
| Cpm Functional Ind | Yes |
| Cpm Detection Ind | No |
| Cpm Conf Ind | No |
| Investigation Status | No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate) |
| Investigation Status Details | No controller actions had taken place prior to the release |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | No |
| Cause | Corrosion Failure |
| Cause Details | External Corrosion |
| Internal External | External Corrosion |
| Visual Exam Results | Localized Pitting |
| Other Corrosion Ind | Yes |
| Corrosion Type Details | Interference Caused By Improper Negative Cable Installation |
| Field Exam Basis Ind | Yes |
| Underground Location | Yes |
| Under Cathodic Protection Ind | Yes |
| Cathodic Pro Start Year | 1986 |
| Shielding Evident | Yes |
| Cathodic Survey Type | Yes |
| Cp Annual Survey Ind | Yes |
| Cp Annual Survey Year | 2017 |
| Prior Damage | Yes |
| Collected Data Ind | Yes |
| Other Recent Year | 2015 |
| Has Hydrtst Conduc Before Ind | No |
| Direct Asmnt Conducted | No |
| Non Destructive Exam Ind | No |
| Preparer Name | N*** J**** |
| Preparer Title | Requlatory Compliance Manager |
| Preparer Email | N*********@o****.com |
| Preparer Telephone | 580-395-6304 |
| Preparer Fax | 580-395-2933 |
| Prepared Date | 2018-12-21 00:00:00 |
| Authorizer Name | N*** J**** |
| Authorizer Telephone | 580-395-6304 |
| Authorizer Title | Regulatory Compliance Manager |
| Authorizer Email | N*********@o****.com |
| Narrative | During the aerial patrol of the oneok creek pipeline on 9/26/2018 the pilot observed what appeared to be ice over the pipeline on the downstream side of slick rd. Local oneok field operator was contacted by the pilot and dispatched to the location. Field operator identified ice, dead vegetation and vapors coming on the right-of-way directly above the pipeline. Pipeline control and operations supervisor were contacted and the pipeline was shut down and the location was isolated. Repair crews excavated the pipeline and discovered a pinhole leak. A plidco mechanical repair clamp was installed and the pipeline returned to service. Oneok's investigation determined the interference causing the leak resulted from a negative cable being installed to the casing, instead of the mainline, by a contractor in september of 2017. The cable was associated with a new ground bed that had been installed in june of 2017 with the rectifier at the location being energized in november of 2017. 12/21/2018 correction - corrected part b, question 10 to show accident occurred on pipeline right of way. N.Jones |