HL incident on 2018-08-31 — TX

Operator
Sunoco Pipeline L.p.
Cause
Excavation Issue
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$1,000
Incident datetime
2018-08-31 14:00
Report number
Location
TX
Narrative
The cherokee to bottleman 6' hdpe pipeline was being excavated to facilitate removal of a lateral dead leg. The pipeline was shut down and valves on either side of the excavation area were closed. The dead leg section had been excavated and while continuing to excavate to the tie in with the 6" cherokee to bottleman mainline the excavator struck the mainline causing a puncture in the hdpe pipe resulting in a 1/2 barrel release. The release was cleaned up and a clamp was installed on the pipeline immediately. After further investigation, it was discovered that the 6" hdpe mainline pipe was laid in a 5 ft wide ditch. The width of the ditch allowed the pipe to bend laterally during backfill which created difficulty in accurately locating the line. Future excavations of and around this pipeline will require additional measures such as potholing to prevent recurrence. Since the date of the release the line has remained in an idled state. Business analysis concluded that further operation of the line is not necessary and as such the line is scheduled to be de-inventoried and placed in out of service status in the 4th quarter of 2018. The line will remain idle until such time.
Detailed record list
Report Received Date
2018-09-30 00:00:00
Iyear
2018
Report Number
20180288
Supplemental Number
31080
Report Type
Supplemental Final
Operator Id
Name
Sunoco Pipeline L.p.
Operator Street Address
1300 Main Street
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2018-08-31 14:00:00
Location Latitude
Location Longitude
Commodity Released Type
Crude Oil
Unintentional Release Bbls
0.5
Recovered Bbls
0.5
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Contractor Working For The Operator
Incident Identified Datetime
2018-08-31 14:00:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
No
Shutdown Explain
Pipeline Was Already Shut Down
On Site Datetime
2018-08-31 14:00:00
Nrc Rpt Num
Nrc Notification Not Required
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Manual
Downstream Valve Type Ind
Manual
Num Pub Evacuated
0
Pipe Fac Name
6" Cherokee To Bottleman
Segment Name
541009 - 6" Cherokee To Bottleman
Onshore State Abbreviation
Ok
Onshore Postal Code
73728
Onshore City Name
Cherokee
Onshore County Name
Alfalfa
Designated Location
Milepost/valve Station
Designated Name
0.9
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
42
Crossing
No
Pipe Facility Type
Intrastate
Item Involved
Pipe
Pipe Type
Pipe Body
Pipe Diameter
6
Pipe Wall Thickness
0.627
Pipe Smys
200
Pipe Specification
Unknown
Pipe Seam Type
Seamless
Pipe Manufacturer
Unknown
Pipe Coating Type
None
Installation Year
Unknown
Manufactured Year
Unknown
Material Involved
Material Other Than Carbon Steel
Material Details
Hdpe Pipe
Release Type
Mechanical Puncture
Puncture Axial
3
Puncture Circum
4
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
Yes
Soil Remed Ind
Yes
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
Yes
Usa Ecological Ind
Yes
Usa Ecological Yes No
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
50
Est Cost Prop Damage
1000
Est Cost Emergency
0
Est Cost Environmental
500
Est Cost Other
0
Prpty
1550
Accident Psig
10
Mop Psig
66
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
11900
Internal Inspection Ind
No
Other Inspection Ind
Yes
Internal Inspection Details
Non Metallic Hdpe Pipe
Operation Complications Ind
Yes
Low Op Pressure Ind
Yes
Low Flow Ind
Yes
Pipeline Function
< 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
Yes
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
Pipeline was shutdown and not operating at the time of the incident.
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Excavation Damage
Cause Details
Excavation Damage By Operator's Contractor (Second Party)
Ex Party Type
Excavation Damage By Operator's Contractor (Second Party)
Notify Cga Dirt
Yes
Pipeline Easement Row Ind
Yes
Excavator Type
Contractor
Excavator Equipment
Backhoe/trackhoe
Work Performed
Liquid Pipeline
One Call Notified Ind
Yes
One Call Ticket Num
1.80823e+13
Locator Type
Utility Owner
Visible Marks
Yes
Root Cause Category
Excavation Issue
Root Cause Type
Improper Excavation Practice Not Listed Above
Preparer Name
T*** N*******
Preparer Title
Sr. Manager - Dot Compliance
Preparer Email
T************@e*************.com
Preparer Telephone
713-989-7126
Preparer Fax
877-917-0448
Prepared Date
2018-10-16 00:00:00
Authorizer Name
T*** N*******
Authorizer Telephone
713-989-7126
Authorizer Title
Sr. Manager - Dot Compliance
Authorizer Email
T************@e*************.com
Narrative
The cherokee to bottleman 6' hdpe pipeline was being excavated to facilitate removal of a lateral dead leg. The pipeline was shut down and valves on either side of the excavation area were closed. The dead leg section had been excavated and while continuing to excavate to the tie in with the 6" cherokee to bottleman mainline the excavator struck the mainline causing a puncture in the hdpe pipe resulting in a 1/2 barrel release. The release was cleaned up and a clamp was installed on the pipeline immediately. After further investigation, it was discovered that the 6" hdpe mainline pipe was laid in a 5 ft wide ditch. The width of the ditch allowed the pipe to bend laterally during backfill which created difficulty in accurately locating the line. Future excavations of and around this pipeline will require additional measures such as potholing to prevent recurrence. Since the date of the release the line has remained in an idled state. Business analysis concluded that further operation of the line is not necessary and as such the line is scheduled to be de-inventoried and placed in out of service status in the 4th quarter of 2018. The line will remain idle until such time.
Report Received Date 2018-09-30 00:00:00
Iyear 2018
Report Number 20180288
Supplemental Number 31080
Report Type Supplemental Final
Operator Id 18718 PHMSA Enforcement
Name Sunoco Pipeline L.p.
Operator Street Address 1300 Main Street
Operator City Name Houston
Operator State Abbreviation TX
Operator Postal Code 77002
Local Datetime 2018-08-31 14:00:00
Location Latitude 36.79827 Google Maps OpenStreetMap
Location Longitude -98.34172 Google Maps OpenStreetMap
Commodity Released Type Crude Oil
Unintentional Release Bbls 0.5
Recovered Bbls 0.5
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Local Operating Personnel, Including Contractors
Operator Type Contractor Working For The Operator
Incident Identified Datetime 2018-08-31 14:00:00
System Part Involved Onshore Pipeline, Including Valve Sites
On Off Shore Onshore
Shutdown Due Accident Ind No
Shutdown Explain Pipeline Was Already Shut Down
On Site Datetime 2018-08-31 14:00:00
Nrc Rpt Num Nrc Notification Not Required NRC Report How to search
Ignite Ind No
Explode Ind No
Upstream Valve Type Ind Manual
Downstream Valve Type Ind Manual
Num Pub Evacuated 0
Pipe Fac Name 6" Cherokee To Bottleman
Segment Name 541009 - 6" Cherokee To Bottleman
Onshore State Abbreviation Ok
Onshore Postal Code 73728
Onshore City Name Cherokee
Onshore County Name Alfalfa
Designated Location Milepost/valve Station
Designated Name 0.9
Federal No
Location Type Pipeline Right-Of-Way
Incident Area Type Underground
Incident Area Subtype Under Soil
Depth Of Cover 42
Crossing No
Pipe Facility Type Intrastate
Item Involved Pipe
Pipe Type Pipe Body
Pipe Diameter 6
Pipe Wall Thickness 0.627
Pipe Smys 200
Pipe Specification Unknown
Pipe Seam Type Seamless
Pipe Manufacturer Unknown
Pipe Coating Type None
Installation Year Unknown
Manufactured Year Unknown
Material Involved Material Other Than Carbon Steel
Material Details Hdpe Pipe
Release Type Mechanical Puncture
Puncture Axial 3
Puncture Circum 4
Wildlife Impact Ind No
Soil Contamination Yes
Long Term Assessment No
Remediation Ind Yes
Soil Remed Ind Yes
Water Contam Ind No
Could Be Hca Yes
Commodity Reached Hca Yes
Usa Ecological Ind Yes
Usa Ecological Yes No Yes
Est Cost Oper Paid 0
Est Cost Gas Released 50
Est Cost Prop Damage 1000
Est Cost Emergency 0
Est Cost Environmental 500
Est Cost Other 0
Prpty 1550
Accident Psig 10
Mop Psig 66
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Length Segment Isolated 11900
Internal Inspection Ind No
Other Inspection Ind Yes
Internal Inspection Details Non Metallic Hdpe Pipe
Operation Complications Ind Yes
Low Op Pressure Ind Yes
Low Flow Ind Yes
Pipeline Function < 20% Smys Regulated Transmission
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind No
Scada Conf Ind No
Cpm In Place Ind Yes
Cpm Operating Ind Yes
Cpm Functional Ind Yes
Cpm Detection Ind No
Cpm Conf Ind No
Investigation Status No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details Pipeline was shutdown and not operating at the time of the incident.
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Excavation Damage
Cause Details Excavation Damage By Operator's Contractor (Second Party)
Ex Party Type Excavation Damage By Operator's Contractor (Second Party)
Notify Cga Dirt Yes
Pipeline Easement Row Ind Yes
Excavator Type Contractor
Excavator Equipment Backhoe/trackhoe
Work Performed Liquid Pipeline
One Call Notified Ind Yes
One Call Ticket Num 1.80823e+13
Locator Type Utility Owner
Visible Marks Yes
Root Cause Category Excavation Issue
Root Cause Type Improper Excavation Practice Not Listed Above
Preparer Name T*** N*******
Preparer Title Sr. Manager - Dot Compliance
Preparer Email T************@e*************.com
Preparer Telephone 713-989-7126
Preparer Fax 877-917-0448
Prepared Date 2018-10-16 00:00:00
Authorizer Name T*** N*******
Authorizer Telephone 713-989-7126
Authorizer Title Sr. Manager - Dot Compliance
Authorizer Email T************@e*************.com
Narrative The cherokee to bottleman 6' hdpe pipeline was being excavated to facilitate removal of a lateral dead leg. The pipeline was shut down and valves on either side of the excavation area were closed. The dead leg section had been excavated and while continuing to excavate to the tie in with the 6" cherokee to bottleman mainline the excavator struck the mainline causing a puncture in the hdpe pipe resulting in a 1/2 barrel release. The release was cleaned up and a clamp was installed on the pipeline immediately. After further investigation, it was discovered that the 6" hdpe mainline pipe was laid in a 5 ft wide ditch. The width of the ditch allowed the pipe to bend laterally during backfill which created difficulty in accurately locating the line. Future excavations of and around this pipeline will require additional measures such as potholing to prevent recurrence. Since the date of the release the line has remained in an idled state. Business analysis concluded that further operation of the line is not necessary and as such the line is scheduled to be de-inventoried and placed in out of service status in the 4th quarter of 2018. The line will remain idle until such time.