HL incident on 2018-06-19 — TX

Operator
Sunoco Pipeline L.p.
Cause
Material Failure Of Pipe Or Weld
Commodity
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$1,268,000
Incident datetime
2018-06-19 18:05
Report number
Location
TX
Narrative
On june 19, 2018 at approximately 18:05 the control center was notified by a private citizen of a petroleum odor in the area of darby creek. Both sunoco pipeline lp (splp) pipelines (8" & 12" refined products) in the area were already shut down due to a planned scheduled outage on june 18, 2018. The control center immediately notified field operations of the report and personnel were dispatched to the area to investigate. After arrival and upon further investigation a petroleum odor and light sheening along the bank of darby creek was noted. Additional response personnel were dispatched and osro contractors arrived on site at approximately 20:45 and deployed boom to contain the sheen by approximately 21:45 and began collection activities. Although there were no operational indications of release from either company pipeline crossing of darby creek, a company incident command team was setup to monitor osro activities and perform further investigations into the product source, including establishing geo-probe monitoring locations, potholing to assess for any indications of product, additional excavation, and pressure testing of the two pipelines. On june 16, 2018, nrc report (1215471) was filed at 13:45 by a private citizen concerning a sheen in darby creek, however splp was not contacted. On june 19, 2018, upon becoming aware of the sheening and responding, splp filed nrc report (1215816) noting that the source of the sheening was undetermined. The 48hr follow up nrc report (1216057) was filed on june 21, 2018 noting the source remained unknown. At approximately 11:45 on june 26, 2018, the splp 12" point breeze to montello pipeline was confirmed as the leak source. Nrc report (1216488) was filed at 13:37 confirming such. The 48hr follow up nrc report (1216699) was filed on june 28, 2018 at 13:14 and provided that an estimated volume of 400 bbls of gasoline was released. The pipeline remained shut down from the scheduled shut down on june 18, 2018 through the remainder of the investigation and repair process. The failed pipe was fully excavated, removed and replaced. The failure was located in an area of disbonded coating on the inner radius of a field bend and appeared to be in a crack located in an area of external corrosion. The failed pipe was preserved and sent to a 3rd party laboratory for metallurgical analysis to fully determine the cause. The 12" point breeze to montello pipeline was refilled on july 1, 2018 at 14:30 and normal operation began at 17:57 that same day. The third party metallurgical analysis report concluded that the leak was due to external corrosion that formed a corrosion trough whose thinned cross section allowed environmentally assisted cracks to initiate and propagate through-wall due to the elevated hoop stress. Two types of environmentally assisted cracking were observed, corrosion fatigue and hydrogen cracking. The area of external corrosion and ultimate failure were located on the inner radius of a field bend under an area of disbonded coal tar coating.
Detailed record list
Report Received Date
2018-07-26 00:00:00
Iyear
2018
Report Number
20180215
Supplemental Number
31167
Report Type
Supplemental Final
Operator Id
Name
Sunoco Pipeline L.p.
Operator Street Address
1300 Main Street
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2018-06-16 13:45:00
Location Latitude
Location Longitude
Commodity Released Type
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Commodity Subtype
Gasoline (Non-Ethanol)
Unintentional Release Bbls
821
Recovered Bbls
530
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Notification From Public
Incident Identified Datetime
2018-06-19 18:05:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2018-06-18 22:49:00
Restart Datetime
2018-07-01 17:57:00
On Site Datetime
2018-06-19 18:41:00
Nrc Rpt Datetime
2018-06-19 20:03:00
Nrc Rpt Num
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Manual
Downstream Valve Type Ind
Manual
Num Pub Evacuated
0
Pipe Fac Name
Point Breeze To Montello
Segment Name
11001 - Point Breeze To Montello 12"
Onshore State Abbreviation
Pa
Onshore Postal Code
19029
Onshore City Name
Essington
Onshore County Name
Delaware
Designated Location
Survey Station No.
Designated Name
340+84
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Underground
Incident Area Subtype
Under Pavement
Depth Of Cover
48
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Pipe
Pipe Type
Pipe Body
Pipe Diameter
12
Pipe Wall Thickness
0.375
Pipe Smys
35000
Pipe Specification
Api 5l, Grade B
Pipe Seam Type
Seamless
Pipe Manufacturer
National Tube
Pipe Coating Type
Coal Tar
Installation Year
1937
Manufactured Year
1937
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Crack
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
Yes
Remediation Ind
Yes
Surface Water Remed Ind
Yes
Groundwater Remed Ind
Yes
Soil Remed Ind
Yes
Water Contam Ind
Yes
Surface Contam Ind
Yes
Groundwater Contam Ind
Yes
Amount Released
246
Rel Water Name
Darby Creek
Could Be Hca
Yes
Commodity Reached Hca
Yes
High Pop Ind
Yes
High Pop Yes No
Yes
Usa Ecological Ind
Yes
Usa Ecological Yes No
Yes
Est Cost Oper Paid
1000000
Est Cost Gas Released
69785
Est Cost Prop Damage
1268000
Est Cost Emergency
1700000
Est Cost Environmental
1200000
Est Cost Other
433000
Est Cost Other Details
Parking Fees
Prpty
5670785
Accident Psig
267
Mop Psig
950
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
7181
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
Yes
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
Yes, specify investigation result(s): (select all that apply)
Invest Schedule Ind
Yes
Invest No Control Room Ind
Yes
Invest No Controller Ind
Yes
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Material Failure Of Pipe Or Weld
Cause Details
Environmental Cracking-Related
Metallurgical Ind
Yes
Failure Type
Environmental Cracking-Related
Stress Subtype
Other
Stress Details
Corrosion Fatigue And Hydrogen Cracking
Additional Pipe Bend Ind
Yes
Additional Crack Ind
Yes
Pwf Additional Other Ind
Yes
Collected Data Ind
Yes
Axial Magnetic Flx Lkg Ind
Yes
Geometry Deformation Ind
Yes
Emat Ind
Yes
Other Tool Tech Ind
Yes
Axial Recent Year
2016
Geometry Recent Year
2016
Emat Recent Year
2016
Other Tool
Spiral And Residual Mfl
Other Recent Year
2016
Has Hydrtst Conduc Before Ind
No
Direct Asmnt Conducted
No
Non Destructive Exam Ind
No
Preparer Name
T*** N*******
Preparer Title
Sr. Manager - Dot Compliance
Preparer Email
T************@e*************.com
Preparer Telephone
713-989-7126
Preparer Fax
877-917-0448
Prepared Date
2018-11-12 00:00:00
Authorizer Name
T*** N*******
Authorizer Telephone
713-989-7126
Authorizer Title
Sr. Manager - Dot Compliance
Authorizer Email
T************@e*************.com
Narrative
On june 19, 2018 at approximately 18:05 the control center was notified by a private citizen of a petroleum odor in the area of darby creek. Both sunoco pipeline lp (splp) pipelines (8" & 12" refined products) in the area were already shut down due to a planned scheduled outage on june 18, 2018. The control center immediately notified field operations of the report and personnel were dispatched to the area to investigate. After arrival and upon further investigation a petroleum odor and light sheening along the bank of darby creek was noted. Additional response personnel were dispatched and osro contractors arrived on site at approximately 20:45 and deployed boom to contain the sheen by approximately 21:45 and began collection activities. Although there were no operational indications of release from either company pipeline crossing of darby creek, a company incident command team was setup to monitor osro activities and perform further investigations into the product source, including establishing geo-probe monitoring locations, potholing to assess for any indications of product, additional excavation, and pressure testing of the two pipelines. On june 16, 2018, nrc report (1215471) was filed at 13:45 by a private citizen concerning a sheen in darby creek, however splp was not contacted. On june 19, 2018, upon becoming aware of the sheening and responding, splp filed nrc report (1215816) noting that the source of the sheening was undetermined. The 48hr follow up nrc report (1216057) was filed on june 21, 2018 noting the source remained unknown. At approximately 11:45 on june 26, 2018, the splp 12" point breeze to montello pipeline was confirmed as the leak source. Nrc report (1216488) was filed at 13:37 confirming such. The 48hr follow up nrc report (1216699) was filed on june 28, 2018 at 13:14 and provided that an estimated volume of 400 bbls of gasoline was released. The pipeline remained shut down from the scheduled shut down on june 18, 2018 through the remainder of the investigation and repair process. The failed pipe was fully excavated, removed and replaced. The failure was located in an area of disbonded coating on the inner radius of a field bend and appeared to be in a crack located in an area of external corrosion. The failed pipe was preserved and sent to a 3rd party laboratory for metallurgical analysis to fully determine the cause. The 12" point breeze to montello pipeline was refilled on july 1, 2018 at 14:30 and normal operation began at 17:57 that same day. The third party metallurgical analysis report concluded that the leak was due to external corrosion that formed a corrosion trough whose thinned cross section allowed environmentally assisted cracks to initiate and propagate through-wall due to the elevated hoop stress. Two types of environmentally assisted cracking were observed, corrosion fatigue and hydrogen cracking. The area of external corrosion and ultimate failure were located on the inner radius of a field bend under an area of disbonded coal tar coating.
Report Received Date 2018-07-26 00:00:00
Iyear 2018
Report Number 20180215
Supplemental Number 31167
Report Type Supplemental Final
Operator Id 18718 PHMSA Enforcement
Name Sunoco Pipeline L.p.
Operator Street Address 1300 Main Street
Operator City Name Houston
Operator State Abbreviation TX
Operator Postal Code 77002
Local Datetime 2018-06-16 13:45:00
Location Latitude 39.86509 Google Maps OpenStreetMap
Location Longitude -75.31148 Google Maps OpenStreetMap
Commodity Released Type Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Commodity Subtype Gasoline (Non-Ethanol)
Unintentional Release Bbls 821
Recovered Bbls 530
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Notification From Public
Incident Identified Datetime 2018-06-19 18:05:00
System Part Involved Onshore Pipeline, Including Valve Sites
On Off Shore Onshore
Shutdown Due Accident Ind Yes
Shutdown Datetime 2018-06-18 22:49:00
Restart Datetime 2018-07-01 17:57:00
On Site Datetime 2018-06-19 18:41:00
Nrc Rpt Datetime 2018-06-19 20:03:00
Nrc Rpt Num 1215816 NRC Report How to search
Ignite Ind No
Explode Ind No
Upstream Valve Type Ind Manual
Downstream Valve Type Ind Manual
Num Pub Evacuated 0
Pipe Fac Name Point Breeze To Montello
Segment Name 11001 - Point Breeze To Montello 12"
Onshore State Abbreviation Pa
Onshore Postal Code 19029
Onshore City Name Essington
Onshore County Name Delaware
Designated Location Survey Station No.
Designated Name 340+84
Federal No
Location Type Pipeline Right-Of-Way
Incident Area Type Underground
Incident Area Subtype Under Pavement
Depth Of Cover 48
Crossing No
Pipe Facility Type Interstate
Item Involved Pipe
Pipe Type Pipe Body
Pipe Diameter 12
Pipe Wall Thickness 0.375
Pipe Smys 35000
Pipe Specification Api 5l, Grade B
Pipe Seam Type Seamless
Pipe Manufacturer National Tube
Pipe Coating Type Coal Tar
Installation Year 1937
Manufactured Year 1937
Material Involved Carbon Steel
Release Type Leak
Leak Type Crack
Wildlife Impact Ind No
Soil Contamination Yes
Long Term Assessment Yes
Remediation Ind Yes
Surface Water Remed Ind Yes
Groundwater Remed Ind Yes
Soil Remed Ind Yes
Water Contam Ind Yes
Surface Contam Ind Yes
Groundwater Contam Ind Yes
Amount Released 246
Rel Water Name Darby Creek
Could Be Hca Yes
Commodity Reached Hca Yes
High Pop Ind Yes
High Pop Yes No Yes
Usa Ecological Ind Yes
Usa Ecological Yes No Yes
Est Cost Oper Paid 1000000
Est Cost Gas Released 69785
Est Cost Prop Damage 1268000
Est Cost Emergency 1700000
Est Cost Environmental 1200000
Est Cost Other 433000
Est Cost Other Details Parking Fees
Prpty 5670785
Accident Psig 267
Mop Psig 950
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Length Segment Isolated 7181
Internal Inspection Ind Yes
Operation Complications Ind No
Pipeline Function > 20% Smys Regulated Transmission
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind No
Scada Conf Ind No
Cpm In Place Ind Yes
Cpm Operating Ind Yes
Cpm Functional Ind Yes
Cpm Detection Ind No
Cpm Conf Ind No
Investigation Status Yes, specify investigation result(s): (select all that apply)
Invest Schedule Ind Yes
Invest No Control Room Ind Yes
Invest No Controller Ind Yes
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Material Failure Of Pipe Or Weld
Cause Details Environmental Cracking-Related
Metallurgical Ind Yes
Failure Type Environmental Cracking-Related
Stress Subtype Other
Stress Details Corrosion Fatigue And Hydrogen Cracking
Additional Pipe Bend Ind Yes
Additional Crack Ind Yes
Pwf Additional Other Ind Yes
Collected Data Ind Yes
Axial Magnetic Flx Lkg Ind Yes
Geometry Deformation Ind Yes
Emat Ind Yes
Other Tool Tech Ind Yes
Axial Recent Year 2016
Geometry Recent Year 2016
Emat Recent Year 2016
Other Tool Spiral And Residual Mfl
Other Recent Year 2016
Has Hydrtst Conduc Before Ind No
Direct Asmnt Conducted No
Non Destructive Exam Ind No
Preparer Name T*** N*******
Preparer Title Sr. Manager - Dot Compliance
Preparer Email T************@e*************.com
Preparer Telephone 713-989-7126
Preparer Fax 877-917-0448
Prepared Date 2018-11-12 00:00:00
Authorizer Name T*** N*******
Authorizer Telephone 713-989-7126
Authorizer Title Sr. Manager - Dot Compliance
Authorizer Email T************@e*************.com
Narrative On june 19, 2018 at approximately 18:05 the control center was notified by a private citizen of a petroleum odor in the area of darby creek. Both sunoco pipeline lp (splp) pipelines (8" & 12" refined products) in the area were already shut down due to a planned scheduled outage on june 18, 2018. The control center immediately notified field operations of the report and personnel were dispatched to the area to investigate. After arrival and upon further investigation a petroleum odor and light sheening along the bank of darby creek was noted. Additional response personnel were dispatched and osro contractors arrived on site at approximately 20:45 and deployed boom to contain the sheen by approximately 21:45 and began collection activities. Although there were no operational indications of release from either company pipeline crossing of darby creek, a company incident command team was setup to monitor osro activities and perform further investigations into the product source, including establishing geo-probe monitoring locations, potholing to assess for any indications of product, additional excavation, and pressure testing of the two pipelines. On june 16, 2018, nrc report (1215471) was filed at 13:45 by a private citizen concerning a sheen in darby creek, however splp was not contacted. On june 19, 2018, upon becoming aware of the sheening and responding, splp filed nrc report (1215816) noting that the source of the sheening was undetermined. The 48hr follow up nrc report (1216057) was filed on june 21, 2018 noting the source remained unknown. At approximately 11:45 on june 26, 2018, the splp 12" point breeze to montello pipeline was confirmed as the leak source. Nrc report (1216488) was filed at 13:37 confirming such. The 48hr follow up nrc report (1216699) was filed on june 28, 2018 at 13:14 and provided that an estimated volume of 400 bbls of gasoline was released. The pipeline remained shut down from the scheduled shut down on june 18, 2018 through the remainder of the investigation and repair process. The failed pipe was fully excavated, removed and replaced. The failure was located in an area of disbonded coating on the inner radius of a field bend and appeared to be in a crack located in an area of external corrosion. The failed pipe was preserved and sent to a 3rd party laboratory for metallurgical analysis to fully determine the cause. The 12" point breeze to montello pipeline was refilled on july 1, 2018 at 14:30 and normal operation began at 17:57 that same day. The third party metallurgical analysis report concluded that the leak was due to external corrosion that formed a corrosion trough whose thinned cross section allowed environmentally assisted cracks to initiate and propagate through-wall due to the elevated hoop stress. Two types of environmentally assisted cracking were observed, corrosion fatigue and hydrogen cracking. The area of external corrosion and ultimate failure were located on the inner radius of a field bend under an area of disbonded coal tar coating.

All rights reserved. Copyright © by ClearPHMSA