HL incident on 2018-04-29 — OK

Operator
Blue Racer Midstream, Llc
Cause
Natural Force Damage
Commodity
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$707,640
Incident datetime
2018-04-29 16:05
Report number
Location
OK
Narrative
On sunday april 29, 2018, at approximately 4:05 p.M., low pressure was detected by the blue racer midstream ("brm") gas control indicating a leak of over 3 million barrels at the natrium plant ("alarm 1"). This reading was well beyond the pipeline's normal operating volume which ranges between approximately 6,000 and 8,000 barrels per day. The brm gas control operator ("controller") on duty at the time contacted the controllers at the natrium plant ("inlet") and at enterprise to verify the alarm readings. The controller at the inlet stated they were still flowing but pressure had dropped off and the controller at enterprise stated they lost flow and the valve was closed at the moffitt station ("outlet"). Brm controller then contacted field operations supervisor and, out of an abundance of caution, shut in the line until field operations could be deployed and inspect the meters at the inlet. Shortly thereafter at 4:15 p.M., field operators were deployed to the inlet of g-150 to begin verifying the meter reading (source of alarm 1). At around the same time, there was a second leak alarm on the static side of the line at the outlet stating leak volume was 421 trillion barrels - also a reading well beyond the pipeline's normal operating volume ("alarm 2"). Additional field operators were then deployed to the outlet location to verify the meter readings there. The pipeline remained shut in. Field operators then proceeded to inspect, starting at the inlet and outlet locations, and manually close the mainline valves until the cause of the alarms could be determined. At 9:21 p.M., field supervisors called in to brm gas control saying g-150 would remain shut down through the night and that field operators will continue to monitor field pressures and investigate the potential causes of the pressure drop. On monday april 30, 2018, at approximately 7:30 a.M., a contract helicopter was dispatched to overfly the g-150 pipeline. Their flight path began at the north end of the line at the outlet, where they visually inspected the right of way below, and ended at the southern end of the pipeline. At approximately 8:35 a.M., at an approximate location of 39.54497n and -80.40507w, the flight crew discovered evidence of a liquid propane leak in the right of way and, shortly thereafter, communicated the approximate location to the brm regulatory compliance manager. Field operation crews were immediately dispatched to the location to confirm the release and arrived on scene at approximately 9:30 a.M. Upon confirmation of the release, brm employees from field operations, environmental, engineering, and compliance began an initial assessment and determined the release site was in a non-hca and the release did not pose an immediate or potential danger to the surrounding area. Environmental personnel took soil and water samples while field operations continued to monitor the release site. On april 30, 2018, at 9:41 a.M., the regulatory compliance manager notified the nrc pursuant to 49 cfr 195.52(b), being nrc report number 1210711. Subsequently, on may 2, 2018, at 8:39 a.M., within the prescribed 48 hours as prescribed by regulation, a subsequent report was provided to the nrc amending the estimated release volume from "unknown" to "approximately 3,000 barrels", being nrc report number 1210923. There was not a need for evacuations and there were no injuries or property damage reported.
Detailed record list
Report Received Date
2018-05-23 00:00:00
Iyear
2018
Report Number
20180141
Supplemental Number
30726
Report Type
Supplemental Final
Operator Id
Name
Blue Racer Midstream, Llc
Operator Street Address
One Williams Center
Operator City Name
Tulsa
Operator State Abbreviation
OK
Operator Postal Code
74172
Local Datetime
2018-04-29 16:05:00
Location Latitude
Location Longitude
Commodity Released Type
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Commodity Subtype
Other Hvl
Commodity Details
Liquid Propane
Unintentional Release Bbls
2658
Intentional Release Bbls
1480
Recovered Bbls
0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Cpm Leak Detection System Or Scada-Based Information (Such As Alarm(S), Alert(S), Event(S), And/or Volume Calculations)
Incident Identified Datetime
2018-04-29 16:05:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2018-04-29 16:15:00
Restart Datetime
2018-05-29 19:45:00
On Site Datetime
2018-04-30 09:30:00
Nrc Rpt Datetime
2018-04-30 09:41:00
Nrc Rpt Num
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Remotely Controlled
Downstream Valve Type Ind
Automatic
Num Pub Evacuated
0
Pipe Fac Name
G-150
Segment Name
G-150
Onshore State Abbreviation
Wv
Onshore Postal Code
26041
Onshore City Name
Not Within A Municipality
Onshore County Name
Marshall County
Designated Location
Survey Station No.
Designated Name
911+42
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
96
Crossing
No
Pipe Facility Type
Intrastate
Item Involved
Pipe
Pipe Type
Pipe Body
Pipe Diameter
8
Pipe Wall Thickness
0.322
Pipe Smys
52000
Pipe Specification
Api5l Psl2 X52
Pipe Seam Type
Erw � Unknown Frequency
Pipe Manufacturer
Ipsco
Pipe Coating Type
Fusion Bonded Epoxy(Fbe)
Installation Year
2012
Manufactured Year
2011
Material Involved
Carbon Steel
Release Type
Rupture
Rupture Orient
Circumferential
Rupture Width
0.5
Rupture Length
4
Wildlife Impact Ind
No
Soil Contamination
No
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
0
Est Cost Gas Released
65371
Est Cost Prop Damage
707640
Est Cost Emergency
11102
Est Cost Environmental
0
Est Cost Other
0
Prpty
784113
Accident Psig
1080
Mop Psig
1080
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
173712
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
Yes
Scada Conf Ind
Yes
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
Yes
Cpm Detection Ind
Yes
Cpm Conf Ind
Yes
Investigation Status
Yes, specify investigation result(s): (select all that apply)
Invest No Control Room Ind
Yes
Invest No Controller Ind
Yes
Employee Drug Test Ind
Yes
Contractor Drug Test Ind
No
Num Employees Tested
4
Num Employees Failed
0
Cause
Natural Force Damage
Cause Details
Earth Movement, Not Due To Heavy Rains/floods
Natural Force Type
Earth Movement, Not Due To Heavy Rains/floods
Earth Subtype
Landslide
Nf Extreme Weather Ind
No
Preparer Name
D***** A* G*****
Preparer Title
Regulatory Compliance Manager
Preparer Email
D******@b*****************.com
Preparer Telephone
3045472110
Preparer Fax
3045472139
Prepared Date
2018-07-31 00:00:00
Authorizer Name
S***** G****
Authorizer Telephone
2145803700
Authorizer Title
Svp Of Engineering And Operations
Authorizer Email
S*****@b*****************.com
Narrative
On sunday april 29, 2018, at approximately 4:05 p.M., low pressure was detected by the blue racer midstream ("brm") gas control indicating a leak of over 3 million barrels at the natrium plant ("alarm 1"). This reading was well beyond the pipeline's normal operating volume which ranges between approximately 6,000 and 8,000 barrels per day. The brm gas control operator ("controller") on duty at the time contacted the controllers at the natrium plant ("inlet") and at enterprise to verify the alarm readings. The controller at the inlet stated they were still flowing but pressure had dropped off and the controller at enterprise stated they lost flow and the valve was closed at the moffitt station ("outlet"). Brm controller then contacted field operations supervisor and, out of an abundance of caution, shut in the line until field operations could be deployed and inspect the meters at the inlet. Shortly thereafter at 4:15 p.M., field operators were deployed to the inlet of g-150 to begin verifying the meter reading (source of alarm 1). At around the same time, there was a second leak alarm on the static side of the line at the outlet stating leak volume was 421 trillion barrels - also a reading well beyond the pipeline's normal operating volume ("alarm 2"). Additional field operators were then deployed to the outlet location to verify the meter readings there. The pipeline remained shut in. Field operators then proceeded to inspect, starting at the inlet and outlet locations, and manually close the mainline valves until the cause of the alarms could be determined. At 9:21 p.M., field supervisors called in to brm gas control saying g-150 would remain shut down through the night and that field operators will continue to monitor field pressures and investigate the potential causes of the pressure drop. On monday april 30, 2018, at approximately 7:30 a.M., a contract helicopter was dispatched to overfly the g-150 pipeline. Their flight path began at the north end of the line at the outlet, where they visually inspected the right of way below, and ended at the southern end of the pipeline. At approximately 8:35 a.M., at an approximate location of 39.54497n and -80.40507w, the flight crew discovered evidence of a liquid propane leak in the right of way and, shortly thereafter, communicated the approximate location to the brm regulatory compliance manager. Field operation crews were immediately dispatched to the location to confirm the release and arrived on scene at approximately 9:30 a.M. Upon confirmation of the release, brm employees from field operations, environmental, engineering, and compliance began an initial assessment and determined the release site was in a non-hca and the release did not pose an immediate or potential danger to the surrounding area. Environmental personnel took soil and water samples while field operations continued to monitor the release site. On april 30, 2018, at 9:41 a.M., the regulatory compliance manager notified the nrc pursuant to 49 cfr 195.52(b), being nrc report number 1210711. Subsequently, on may 2, 2018, at 8:39 a.M., within the prescribed 48 hours as prescribed by regulation, a subsequent report was provided to the nrc amending the estimated release volume from "unknown" to "approximately 3,000 barrels", being nrc report number 1210923. There was not a need for evacuations and there were no injuries or property damage reported.
Report Received Date 2018-05-23 00:00:00
Iyear 2018
Report Number 20180141
Supplemental Number 30726
Report Type Supplemental Final
Operator Id 39010 PHMSA Enforcement
Name Blue Racer Midstream, Llc
Operator Street Address One Williams Center
Operator City Name Tulsa
Operator State Abbreviation OK
Operator Postal Code 74172
Local Datetime 2018-04-29 16:05:00
Location Latitude 39.91542 Google Maps OpenStreetMap
Location Longitude -80.67974 Google Maps OpenStreetMap
Commodity Released Type Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Commodity Subtype Other Hvl
Commodity Details Liquid Propane
Unintentional Release Bbls 2658
Intentional Release Bbls 1480
Recovered Bbls 0
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Cpm Leak Detection System Or Scada-Based Information (Such As Alarm(S), Alert(S), Event(S), And/or Volume Calculations)
Incident Identified Datetime 2018-04-29 16:05:00
System Part Involved Onshore Pipeline, Including Valve Sites
On Off Shore Onshore
Shutdown Due Accident Ind Yes
Shutdown Datetime 2018-04-29 16:15:00
Restart Datetime 2018-05-29 19:45:00
On Site Datetime 2018-04-30 09:30:00
Nrc Rpt Datetime 2018-04-30 09:41:00
Nrc Rpt Num 1210711 NRC Report How to search
Ignite Ind No
Explode Ind No
Upstream Valve Type Ind Remotely Controlled
Downstream Valve Type Ind Automatic
Num Pub Evacuated 0
Pipe Fac Name G-150
Segment Name G-150
Onshore State Abbreviation Wv
Onshore Postal Code 26041
Onshore City Name Not Within A Municipality
Onshore County Name Marshall County
Designated Location Survey Station No.
Designated Name 911+42
Federal No
Location Type Pipeline Right-Of-Way
Incident Area Type Underground
Incident Area Subtype Under Soil
Depth Of Cover 96
Crossing No
Pipe Facility Type Intrastate
Item Involved Pipe
Pipe Type Pipe Body
Pipe Diameter 8
Pipe Wall Thickness 0.322
Pipe Smys 52000
Pipe Specification Api5l Psl2 X52
Pipe Seam Type Erw � Unknown Frequency
Pipe Manufacturer Ipsco
Pipe Coating Type Fusion Bonded Epoxy(Fbe)
Installation Year 2012
Manufactured Year 2011
Material Involved Carbon Steel
Release Type Rupture
Rupture Orient Circumferential
Rupture Width 0.5
Rupture Length 4
Wildlife Impact Ind No
Soil Contamination No
Long Term Assessment No
Remediation Ind No
Water Contam Ind No
Could Be Hca No
Commodity Reached Hca No
Est Cost Oper Paid 0
Est Cost Gas Released 65371
Est Cost Prop Damage 707640
Est Cost Emergency 11102
Est Cost Environmental 0
Est Cost Other 0
Prpty 784113
Accident Psig 1080
Mop Psig 1080
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Length Segment Isolated 173712
Internal Inspection Ind Yes
Operation Complications Ind No
Pipeline Function > 20% Smys Regulated Transmission
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind Yes
Scada Conf Ind Yes
Cpm In Place Ind Yes
Cpm Operating Ind Yes
Cpm Functional Ind Yes
Cpm Detection Ind Yes
Cpm Conf Ind Yes
Investigation Status Yes, specify investigation result(s): (select all that apply)
Invest No Control Room Ind Yes
Invest No Controller Ind Yes
Employee Drug Test Ind Yes
Contractor Drug Test Ind No
Num Employees Tested 4
Num Employees Failed 0
Cause Natural Force Damage
Cause Details Earth Movement, Not Due To Heavy Rains/floods
Natural Force Type Earth Movement, Not Due To Heavy Rains/floods
Earth Subtype Landslide
Nf Extreme Weather Ind No
Preparer Name D***** A* G*****
Preparer Title Regulatory Compliance Manager
Preparer Email D******@b*****************.com
Preparer Telephone 3045472110
Preparer Fax 3045472139
Prepared Date 2018-07-31 00:00:00
Authorizer Name S***** G****
Authorizer Telephone 2145803700
Authorizer Title Svp Of Engineering And Operations
Authorizer Email S*****@b*****************.com
Narrative On sunday april 29, 2018, at approximately 4:05 p.M., low pressure was detected by the blue racer midstream ("brm") gas control indicating a leak of over 3 million barrels at the natrium plant ("alarm 1"). This reading was well beyond the pipeline's normal operating volume which ranges between approximately 6,000 and 8,000 barrels per day. The brm gas control operator ("controller") on duty at the time contacted the controllers at the natrium plant ("inlet") and at enterprise to verify the alarm readings. The controller at the inlet stated they were still flowing but pressure had dropped off and the controller at enterprise stated they lost flow and the valve was closed at the moffitt station ("outlet"). Brm controller then contacted field operations supervisor and, out of an abundance of caution, shut in the line until field operations could be deployed and inspect the meters at the inlet. Shortly thereafter at 4:15 p.M., field operators were deployed to the inlet of g-150 to begin verifying the meter reading (source of alarm 1). At around the same time, there was a second leak alarm on the static side of the line at the outlet stating leak volume was 421 trillion barrels - also a reading well beyond the pipeline's normal operating volume ("alarm 2"). Additional field operators were then deployed to the outlet location to verify the meter readings there. The pipeline remained shut in. Field operators then proceeded to inspect, starting at the inlet and outlet locations, and manually close the mainline valves until the cause of the alarms could be determined. At 9:21 p.M., field supervisors called in to brm gas control saying g-150 would remain shut down through the night and that field operators will continue to monitor field pressures and investigate the potential causes of the pressure drop. On monday april 30, 2018, at approximately 7:30 a.M., a contract helicopter was dispatched to overfly the g-150 pipeline. Their flight path began at the north end of the line at the outlet, where they visually inspected the right of way below, and ended at the southern end of the pipeline. At approximately 8:35 a.M., at an approximate location of 39.54497n and -80.40507w, the flight crew discovered evidence of a liquid propane leak in the right of way and, shortly thereafter, communicated the approximate location to the brm regulatory compliance manager. Field operation crews were immediately dispatched to the location to confirm the release and arrived on scene at approximately 9:30 a.M. Upon confirmation of the release, brm employees from field operations, environmental, engineering, and compliance began an initial assessment and determined the release site was in a non-hca and the release did not pose an immediate or potential danger to the surrounding area. Environmental personnel took soil and water samples while field operations continued to monitor the release site. On april 30, 2018, at 9:41 a.M., the regulatory compliance manager notified the nrc pursuant to 49 cfr 195.52(b), being nrc report number 1210711. Subsequently, on may 2, 2018, at 8:39 a.M., within the prescribed 48 hours as prescribed by regulation, a subsequent report was provided to the nrc amending the estimated release volume from "unknown" to "approximately 3,000 barrels", being nrc report number 1210923. There was not a need for evacuations and there were no injuries or property damage reported.

All rights reserved. Copyright © by ClearPHMSA