Incident details
Operator, cause, commodity and consequences with raw source fields.
HL incident on 2017-10-14 — LA
Operator
Epl Pipeline, Llc
Cause
Natural Force Damage
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$2,544,300
Incident datetime
2017-10-14 06:50
Report number
Location
LA
Narrative
Notified by operator of a large sheen on the water. Operators currently investigating the cause of the sheen. East division. Call recieved from tim brazer: updated flyover was conducted at 08:00 cdt, and the spill volume is now at 147 gallons, direction current dimensions: 36, 960 feet (7 miles) length, 5280 feet (1 mile) wide, 40% coverage, colors: 10% barely visible, 80% silvery, 10% slightly colored, moving toward the northwest. Update: caller confirmed source is from energy xxi and coming from 10 inch pipeline, currently isolated, sheen has dissipated, located 1.5 miles south of south pass 77a and south pass 57a. Pipeline segment# 15008. Updated nrc# 119-3261. Divers located separated pipe, which is believed to be caused by a mudslide due to the aftermath of hurricane nate. Pipeline was found approximately 250 feet south of original known location. For part a, question #9: the volume calculation for how much commodity was released is based off of the estimated square footage of the sheen multiplied by the estimated coverage determined by the appearance of the sheen. For part e, question #1: platform was brought back online at roughly 7 pm on 10/13. Pump was cycled up to 100 psig from 10/13 at 7:30 pm until shut-in at 6:30 am on 10/14 when sheen was spotted. Max pressure was 100 psig. Scada is not installed on this pipeline section, therefore no scada indications to report. For part g2: the pipeline was found to be buried 10-20 feet below the mud line eliminating the initial thought of an anchor drag. This pipeline is in a mudslide area and found to be approximately 250 ft south of its original location. In october of 2017 10" oil pipeline psn-15008 parted in a mudslide area between platform sp-77a and sp-55a. The scope of work entailed survey boat pipeline locating, and diver recon of the subsurface area, excavation of the pipeline at leak source with approximately 15' mud cover over the pipeline. Deep ditch excavation was required with a 3:1 safety factor on ditch wall utilizing diver's handjet, airlift, and toyo-pump. The diving contractor located leak path and installed a repair spool piece to repair the severed pipeline. Project duration was approximately 5 weeks.
Detailed record list
Report Received Date
2017-11-09 00:00:00
Iyear
2017
Report Number
20170362
Supplemental Number
31523
Report Type
Supplemental Final
Operator Id
31983
Name
Epl Pipeline, Llc
Operator Street Address
1615 Poydras St. Suite 830
Operator City Name
New Orleans
Operator State Abbreviation
LA
Operator Postal Code
70112
Local Datetime
2017-10-14 06:50:00
Location Latitude
28.843
Location Longitude
-89.354
Commodity Released Type
Crude Oil
Unintentional Release Bbls
3.5
Recovered Bbls
0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Other
Accident Details
Offshore Production Operator Employee
Incident Identified Datetime
2017-10-14 06:50:00
System Part Involved
Offshore Pipeline, Including Riser And Riser Bend
On Off Shore
Offshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2017-10-14 06:55:00
Restart Datetime
2017-11-18 13:45:00
On Site Datetime
2017-10-15 09:00:00
Nrc Rpt Datetime
2017-10-14 08:01:00
Nrc Rpt Num
1193233
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Manual
Downstream Valve Type Ind
Manual
Num Pub Evacuated
0
Off Water Depth
240
Off Accident Origin
On The Outer Continental Shelf (Ocs)
Off Ocs Area
South Pass
Off Ocs Block
56
Off Area Accident Type
Below Water, Pipe Buried Or Jetted Below Seabed
Pipe Facility Type
Interstate
Item Involved
Pipe
Pipe Type
Pipe Body
Pipe Diameter
10
Pipe Wall Thickness
0.5
Pipe Smys
35000
Pipe Specification
Api 5l
Pipe Seam Type
Seamless
Pipe Manufacturer
Unknown
Pipe Coating Type
Fusion Bonded Epoxy(Fbe)
Installation Year
2006
Manufactured Year
Unknown
Material Involved
Carbon Steel
Release Type
Rupture
Rupture Orient
Circumferential
Rupture Width
12
Rupture Length
90.7
Wildlife Impact Ind
No
Soil Contamination
No
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
Yes
Ocean Seawater Ind
Yes
Amount Released
3.5
Rel Water Name
Gulf Of Mexico
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
0
Est Cost Gas Released
175
Est Cost Prop Damage
2544300
Est Cost Emergency
0
Est Cost Environmental
0
Est Cost Other
0
Prpty
2544475
Accident Psig
100
Mop Psig
1440
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
46094
Internal Inspection Ind
Yes
Operation Complications Ind
Yes
Excessive Debris Ind
Yes
Low Op Pressure Ind
Yes
Low Flow Ind
Yes
Pipeline Function
=< 20% Smys Regulated Gathering
Scada In Place Ind
No
Cpm In Place Ind
No
Investigation Status
No, the facility was not monitored by a controller(s) at the time of the accident
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Natural Force Damage
Cause Details
Heavy Rains/floods
Natural Force Type
Heavy Rains/floods
Heavy Rains Subtype
Mudslide
Nf Extreme Weather Ind
Yes
Nf Hurricane Ind
Yes
Preparer Name
D***** P***
Preparer Email
D****@r**.com
Preparer Telephone
713-655-8080
Prepared Date
2019-01-21 00:00:00
Authorizer Name
S****** H*****
Authorizer Telephone
713-396-4196
Authorizer Email
S******@e********.com
Narrative
Notified by operator of a large sheen on the water. Operators currently investigating the cause of the sheen. East division. Call recieved from tim brazer: updated flyover was conducted at 08:00 cdt, and the spill volume is now at 147 gallons, direction current dimensions: 36, 960 feet (7 miles) length, 5280 feet (1 mile) wide, 40% coverage, colors: 10% barely visible, 80% silvery, 10% slightly colored, moving toward the northwest. Update: caller confirmed source is from energy xxi and coming from 10 inch pipeline, currently isolated, sheen has dissipated, located 1.5 miles south of south pass 77a and south pass 57a. Pipeline segment# 15008. Updated nrc# 119-3261. Divers located separated pipe, which is believed to be caused by a mudslide due to the aftermath of hurricane nate. Pipeline was found approximately 250 feet south of original known location. For part a, question #9: the volume calculation for how much commodity was released is based off of the estimated square footage of the sheen multiplied by the estimated coverage determined by the appearance of the sheen. For part e, question #1: platform was brought back online at roughly 7 pm on 10/13. Pump was cycled up to 100 psig from 10/13 at 7:30 pm until shut-in at 6:30 am on 10/14 when sheen was spotted. Max pressure was 100 psig. Scada is not installed on this pipeline section, therefore no scada indications to report. For part g2: the pipeline was found to be buried 10-20 feet below the mud line eliminating the initial thought of an anchor drag. This pipeline is in a mudslide area and found to be approximately 250 ft south of its original location. In october of 2017 10" oil pipeline psn-15008 parted in a mudslide area between platform sp-77a and sp-55a. The scope of work entailed survey boat pipeline locating, and diver recon of the subsurface area, excavation of the pipeline at leak source with approximately 15' mud cover over the pipeline. Deep ditch excavation was required with a 3:1 safety factor on ditch wall utilizing diver's handjet, airlift, and toyo-pump. The diving contractor located leak path and installed a repair spool piece to repair the severed pipeline. Project duration was approximately 5 weeks.
| Report Received Date | 2017-11-09 00:00:00 |
|---|---|
| Iyear | 2017 |
| Report Number | 20170362 |
| Supplemental Number | 31523 |
| Report Type | Supplemental Final |
| Operator Id | 31983 PHMSA Enforcement |
| Name | Epl Pipeline, Llc |
| Operator Street Address | 1615 Poydras St. Suite 830 |
| Operator City Name | New Orleans |
| Operator State Abbreviation | LA |
| Operator Postal Code | 70112 |
| Local Datetime | 2017-10-14 06:50:00 |
| Location Latitude | 28.843 Google Maps OpenStreetMap |
| Location Longitude | -89.354 Google Maps OpenStreetMap |
| Commodity Released Type | Crude Oil |
| Unintentional Release Bbls | 3.5 |
| Recovered Bbls | 0 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Other |
| Accident Details | Offshore Production Operator Employee |
| Incident Identified Datetime | 2017-10-14 06:50:00 |
| System Part Involved | Offshore Pipeline, Including Riser And Riser Bend |
| On Off Shore | Offshore |
| Shutdown Due Accident Ind | Yes |
| Shutdown Datetime | 2017-10-14 06:55:00 |
| Restart Datetime | 2017-11-18 13:45:00 |
| On Site Datetime | 2017-10-15 09:00:00 |
| Nrc Rpt Datetime | 2017-10-14 08:01:00 |
| Nrc Rpt Num | 1193233 NRC Report How to search |
| Ignite Ind | No |
| Explode Ind | No |
| Upstream Valve Type Ind | Manual |
| Downstream Valve Type Ind | Manual |
| Num Pub Evacuated | 0 |
| Off Water Depth | 240 |
| Off Accident Origin | On The Outer Continental Shelf (Ocs) |
| Off Ocs Area | South Pass |
| Off Ocs Block | 56 |
| Off Area Accident Type | Below Water, Pipe Buried Or Jetted Below Seabed |
| Pipe Facility Type | Interstate |
| Item Involved | Pipe |
| Pipe Type | Pipe Body |
| Pipe Diameter | 10 |
| Pipe Wall Thickness | 0.5 |
| Pipe Smys | 35000 |
| Pipe Specification | Api 5l |
| Pipe Seam Type | Seamless |
| Pipe Manufacturer | Unknown |
| Pipe Coating Type | Fusion Bonded Epoxy(Fbe) |
| Installation Year | 2006 |
| Manufactured Year | Unknown |
| Material Involved | Carbon Steel |
| Release Type | Rupture |
| Rupture Orient | Circumferential |
| Rupture Width | 12 |
| Rupture Length | 90.7 |
| Wildlife Impact Ind | No |
| Soil Contamination | No |
| Long Term Assessment | No |
| Remediation Ind | No |
| Water Contam Ind | Yes |
| Ocean Seawater Ind | Yes |
| Amount Released | 3.5 |
| Rel Water Name | Gulf Of Mexico |
| Could Be Hca | No |
| Commodity Reached Hca | No |
| Est Cost Oper Paid | 0 |
| Est Cost Gas Released | 175 |
| Est Cost Prop Damage | 2544300 |
| Est Cost Emergency | 0 |
| Est Cost Environmental | 0 |
| Est Cost Other | 0 |
| Prpty | 2544475 |
| Accident Psig | 100 |
| Mop Psig | 1440 |
| Accident Pressure | Pressure Did Not Exceed Mop |
| Pressure Restriction Ind | No |
| Length Segment Isolated | 46094 |
| Internal Inspection Ind | Yes |
| Operation Complications Ind | Yes |
| Excessive Debris Ind | Yes |
| Low Op Pressure Ind | Yes |
| Low Flow Ind | Yes |
| Pipeline Function | =< 20% Smys Regulated Gathering |
| Scada In Place Ind | No |
| Cpm In Place Ind | No |
| Investigation Status | No, the facility was not monitored by a controller(s) at the time of the accident |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | No |
| Cause | Natural Force Damage |
| Cause Details | Heavy Rains/floods |
| Natural Force Type | Heavy Rains/floods |
| Heavy Rains Subtype | Mudslide |
| Nf Extreme Weather Ind | Yes |
| Nf Hurricane Ind | Yes |
| Preparer Name | D***** P*** |
| Preparer Email | D****@r**.com |
| Preparer Telephone | 713-655-8080 |
| Prepared Date | 2019-01-21 00:00:00 |
| Authorizer Name | S****** H***** |
| Authorizer Telephone | 713-396-4196 |
| Authorizer Email | S******@e********.com |
| Narrative | Notified by operator of a large sheen on the water. Operators currently investigating the cause of the sheen. East division. Call recieved from tim brazer: updated flyover was conducted at 08:00 cdt, and the spill volume is now at 147 gallons, direction current dimensions: 36, 960 feet (7 miles) length, 5280 feet (1 mile) wide, 40% coverage, colors: 10% barely visible, 80% silvery, 10% slightly colored, moving toward the northwest. Update: caller confirmed source is from energy xxi and coming from 10 inch pipeline, currently isolated, sheen has dissipated, located 1.5 miles south of south pass 77a and south pass 57a. Pipeline segment# 15008. Updated nrc# 119-3261. Divers located separated pipe, which is believed to be caused by a mudslide due to the aftermath of hurricane nate. Pipeline was found approximately 250 feet south of original known location. For part a, question #9: the volume calculation for how much commodity was released is based off of the estimated square footage of the sheen multiplied by the estimated coverage determined by the appearance of the sheen. For part e, question #1: platform was brought back online at roughly 7 pm on 10/13. Pump was cycled up to 100 psig from 10/13 at 7:30 pm until shut-in at 6:30 am on 10/14 when sheen was spotted. Max pressure was 100 psig. Scada is not installed on this pipeline section, therefore no scada indications to report. For part g2: the pipeline was found to be buried 10-20 feet below the mud line eliminating the initial thought of an anchor drag. This pipeline is in a mudslide area and found to be approximately 250 ft south of its original location. In october of 2017 10" oil pipeline psn-15008 parted in a mudslide area between platform sp-77a and sp-55a. The scope of work entailed survey boat pipeline locating, and diver recon of the subsurface area, excavation of the pipeline at leak source with approximately 15' mud cover over the pipeline. Deep ditch excavation was required with a 3:1 safety factor on ditch wall utilizing diver's handjet, airlift, and toyo-pump. The diving contractor located leak path and installed a repair spool piece to repair the severed pipeline. Project duration was approximately 5 weeks. |