HL incident on 2017-08-16 — TX

Operator
Enterprise Crude Pipeline Llc
Cause
Incorrect Operation
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$150
Incident datetime
2017-08-16 12:00
Report number
Location
TX
Narrative
On 08/16/17 a contractor entered wood station without authorization from enterprise operations to remove their chemical injection equipment. In the process of removing the equipment, the injection tubing was removed from the injection point. At the time of removal, the pipeline was not running and no product was released. The contractor left the site without capping the tubing and returned a few hours later to find crude oil actively leaking from the disconnected tubing. The contractor then notified enterprise of the release. Approximately 10 barrels made contact with the ground and another 15 was contained within a containment tub.
Detailed record list
Report Received Date
2017-09-12 00:00:00
Iyear
2017
Report Number
20170285
Supplemental Number
22632
Report Type
Original Final
Operator Id
Name
Enterprise Crude Pipeline Llc
Operator Street Address
1100 Louisiana Street
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2017-08-16 09:00:00
Location Latitude
Location Longitude
Commodity Released Type
Crude Oil
Unintentional Release Bbls
25
Recovered Bbls
25
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Notification From Third Party That Caused The Accident
Incident Identified Datetime
2017-08-16 12:00:00
System Part Involved
Onshore Pump/meter Station Equipment And Piping
On Off Shore
Onshore
Shutdown Due Accident Ind
No
Shutdown Explain
The Isolation Valve Was Closed
On Site Datetime
2017-08-16 12:45:00
Nrc Rpt Num
Nrc Notification Not Required
Ignite Ind
No
Explode Ind
No
Num Pub Evacuated
0
Pipe Fac Name
C 16 Wood Station
Segment Name
Chemical Injection
Onshore State Abbreviation
Tx
Onshore Postal Code
79360
Onshore City Name
Seminole
Onshore County Name
Gaines
Designated Location
Milepost/valve Station
Designated Name
Wood Stat.
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Aboveground
Incident Area Subtype
Typical Aboveground Facility Piping Or Appurtenance
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Tubing
Installation Year
2015
Material Involved
Material Other Than Carbon Steel
Material Details
Stainless Steel
Release Type
Leak
Leak Type
Other
Leak Type Other
Tubing Was Removed
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
0
Est Cost Gas Released
450
Est Cost Prop Damage
150
Est Cost Emergency
20000
Est Cost Environmental
0
Est Cost Other
0
Prpty
20600
Accident Psig
5
Mop Psig
1211
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
Yes
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
Controller nor control room were a contributing factor
Employee Drug Test Ind
No
Contractor Drug Test Ind
Yes
Num Contractors Tested
1
Num Contractors Failed
0
Cause
Incorrect Operation
Cause Details
Other Incorrect Operation
Operation Type
Other Incorrect Operation
Operation Details
Chemical Injection Tubing Removed
Related Failure Follow Ind
Yes
Category Type
Routine Maintenance
Operator Qualification Ind
Yes
Qualified Individuals
Yes, They Were Qualified For The Task(S)
Preparer Name
C**** A******
Preparer Email
C*******@e****.com
Preparer Telephone
713-381-6426
Prepared Date
2017-09-12 00:00:00
Authorizer Name
C**** A******
Authorizer Telephone
713-381-6426
Authorizer Title
Pipeline Compliance
Authorizer Email
C*******@e****.com
Narrative
On 08/16/17 a contractor entered wood station without authorization from enterprise operations to remove their chemical injection equipment. In the process of removing the equipment, the injection tubing was removed from the injection point. At the time of removal, the pipeline was not running and no product was released. The contractor left the site without capping the tubing and returned a few hours later to find crude oil actively leaking from the disconnected tubing. The contractor then notified enterprise of the release. Approximately 10 barrels made contact with the ground and another 15 was contained within a containment tub.
Report Received Date 2017-09-12 00:00:00
Iyear 2017
Report Number 20170285
Supplemental Number 22632
Report Type Original Final
Operator Id 30829 PHMSA Enforcement
Name Enterprise Crude Pipeline Llc
Operator Street Address 1100 Louisiana Street
Operator City Name Houston
Operator State Abbreviation TX
Operator Postal Code 77002
Local Datetime 2017-08-16 09:00:00
Location Latitude 32.75599 Google Maps OpenStreetMap
Location Longitude -102.719168 Google Maps OpenStreetMap
Commodity Released Type Crude Oil
Unintentional Release Bbls 25
Recovered Bbls 25
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Notification From Third Party That Caused The Accident
Incident Identified Datetime 2017-08-16 12:00:00
System Part Involved Onshore Pump/meter Station Equipment And Piping
On Off Shore Onshore
Shutdown Due Accident Ind No
Shutdown Explain The Isolation Valve Was Closed
On Site Datetime 2017-08-16 12:45:00
Nrc Rpt Num Nrc Notification Not Required NRC Report How to search
Ignite Ind No
Explode Ind No
Num Pub Evacuated 0
Pipe Fac Name C 16 Wood Station
Segment Name Chemical Injection
Onshore State Abbreviation Tx
Onshore Postal Code 79360
Onshore City Name Seminole
Onshore County Name Gaines
Designated Location Milepost/valve Station
Designated Name Wood Stat.
Federal No
Location Type Totally Contained On Operator-Controlled Property
Incident Area Type Aboveground
Incident Area Subtype Typical Aboveground Facility Piping Or Appurtenance
Crossing No
Pipe Facility Type Interstate
Item Involved Tubing
Installation Year 2015
Material Involved Material Other Than Carbon Steel
Material Details Stainless Steel
Release Type Leak
Leak Type Other
Leak Type Other Tubing Was Removed
Wildlife Impact Ind No
Soil Contamination Yes
Long Term Assessment No
Remediation Ind No
Water Contam Ind No
Could Be Hca No
Commodity Reached Hca No
Est Cost Oper Paid 0
Est Cost Gas Released 450
Est Cost Prop Damage 150
Est Cost Emergency 20000
Est Cost Environmental 0
Est Cost Other 0
Prpty 20600
Accident Psig 5
Mop Psig 1211
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Pipeline Function > 20% Smys Regulated Transmission
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind No
Scada Conf Ind No
Cpm In Place Ind Yes
Cpm Operating Ind Yes
Cpm Functional Ind Yes
Cpm Detection Ind No
Cpm Conf Ind No
Investigation Status No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details Controller nor control room were a contributing factor
Employee Drug Test Ind No
Contractor Drug Test Ind Yes
Num Contractors Tested 1
Num Contractors Failed 0
Cause Incorrect Operation
Cause Details Other Incorrect Operation
Operation Type Other Incorrect Operation
Operation Details Chemical Injection Tubing Removed
Related Failure Follow Ind Yes
Category Type Routine Maintenance
Operator Qualification Ind Yes
Qualified Individuals Yes, They Were Qualified For The Task(S)
Preparer Name C**** A******
Preparer Email C*******@e****.com
Preparer Telephone 713-381-6426
Prepared Date 2017-09-12 00:00:00
Authorizer Name C**** A******
Authorizer Telephone 713-381-6426
Authorizer Title Pipeline Compliance
Authorizer Email C*******@e****.com
Narrative On 08/16/17 a contractor entered wood station without authorization from enterprise operations to remove their chemical injection equipment. In the process of removing the equipment, the injection tubing was removed from the injection point. At the time of removal, the pipeline was not running and no product was released. The contractor left the site without capping the tubing and returned a few hours later to find crude oil actively leaking from the disconnected tubing. The contractor then notified enterprise of the release. Approximately 10 barrels made contact with the ground and another 15 was contained within a containment tub.