HL incident on 2016-11-03 — TX

Operator
Tesoro Logistics Northwest Pipeline Llc
Cause
Other Outside Force Damage
Commodity
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$50,000
Incident datetime
2016-11-03 20:41
Report number
Location
TX
Narrative
On november 3, 2016 a driver struck the pocatello to uprr 8" line segments at an overhead railroad crossing. The boom lift on the logging truck hit the bridge and damaged the line releasing approximately 30 gallons of diesel fuel. The line has been repaired, and the spill has been clean up.
Detailed record list
Report Received Date
2016-12-02 00:00:00
Iyear
2016
Report Number
20160399
Supplemental Number
21906
Report Type
Original Final
Operator Id
Name
Tesoro Logistics Northwest Pipeline Llc
Operator Street Address
19100 Ridgewood Parkway
Operator City Name
San Antonio
Operator State Abbreviation
TX
Operator Postal Code
78259
Local Datetime
2016-11-03 19:21:00
Location Latitude
Location Longitude
Commodity Released Type
Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Commodity Subtype
Diesel, Fuel Oil, Kerosene, Jet Fuel
Unintentional Release Bbls
0.71
Recovered Bbls
0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Other
Accident Details
Notification From Idaho Deq
Incident Identified Datetime
2016-11-03 20:41:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
No
Shutdown Explain
The Pipeline Was Shutdown Prior To Incident.
On Site Datetime
2016-11-03 21:00:00
Nrc Rpt Datetime
2016-11-04 12:46:00
Nrc Rpt Num
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Remotely Controlled
Downstream Valve Type Ind
Remotely Controlled
Num Pub Evacuated
0
Pipe Fac Name
Northwest Product System
Segment Name
Pocatello To Uprr
Onshore State Abbreviation
Id
Onshore Postal Code
83201
Onshore City Name
Pocatello
Onshore County Name
Bannock
Designated Location
Milepost/valve Station
Designated Name
Milepost 3.9
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Aboveground
Incident Area Subtype
Overhead Crossing
Crossing
Yes
Railroad Crossing Ind
Yes
Railroad Type
Uncased
Pipe Facility Type
Interstate
Item Involved
Pipe
Pipe Type
Pipe Body
Pipe Diameter
8.625
Pipe Wall Thickness
0.5
Pipe Smys
35000
Pipe Specification
Grade B
Pipe Seam Type
Erw � Unknown Frequency
Pipe Manufacturer
Uss Steel
Pipe Coating Type
Paint
Installation Year
1963
Manufactured Year
1963
Material Involved
Carbon Steel
Release Type
Mechanical Puncture
Puncture Axial
34
Puncture Circum
10
Wildlife Impact Ind
No
Soil Contamination
No
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
Yes
High Pop Ind
Yes
High Pop Yes No
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
80
Est Cost Prop Damage
50000
Est Cost Emergency
23000
Est Cost Environmental
0
Est Cost Other
0
Prpty
73080
Accident Psig
0
Mop Psig
285
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
19237
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
< 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
No
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
Yes
Cpm Operating Ind
No
Cpm Functional Ind
Yes
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
The line was shut in prior to the incident.
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Other Outside Force Damage
Cause Details
Damage By Car, Truck, Or Other Motorized Vehicle/equipment Not Engaged In Excavation
Outside Force Type
Damage By Car, Truck, Or Other Motorized Vehicle/equipment Not Engaged In Excavation
Vehicle Subtype
Third Party
Preparer Name
A***** R********
Preparer Title
Sr. Regulatory Compliance Specialist
Preparer Email
A***************@t******.com
Preparer Telephone
210-626-4262
Prepared Date
2016-12-02 00:00:00
Authorizer Name
A**** M*******
Authorizer Telephone
210-626-6343
Authorizer Title
Director Compliance Logistics
Authorizer Email
A***************@t******.com
Narrative
On november 3, 2016 a driver struck the pocatello to uprr 8" line segments at an overhead railroad crossing. The boom lift on the logging truck hit the bridge and damaged the line releasing approximately 30 gallons of diesel fuel. The line has been repaired, and the spill has been clean up.
Report Received Date 2016-12-02 00:00:00
Iyear 2016
Report Number 20160399
Supplemental Number 21906
Report Type Original Final
Operator Id 39029 PHMSA Enforcement
Name Tesoro Logistics Northwest Pipeline Llc
Operator Street Address 19100 Ridgewood Parkway
Operator City Name San Antonio
Operator State Abbreviation TX
Operator Postal Code 78259
Local Datetime 2016-11-03 19:21:00
Location Latitude 42.887382 Google Maps OpenStreetMap
Location Longitude -112.476571 Google Maps OpenStreetMap
Commodity Released Type Refined And/or Petroleum Product (Non-Hvl) Which Is A Liquid At Ambient Conditions
Commodity Subtype Diesel, Fuel Oil, Kerosene, Jet Fuel
Unintentional Release Bbls 0.71
Recovered Bbls 0
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Other
Accident Details Notification From Idaho Deq
Incident Identified Datetime 2016-11-03 20:41:00
System Part Involved Onshore Pipeline, Including Valve Sites
On Off Shore Onshore
Shutdown Due Accident Ind No
Shutdown Explain The Pipeline Was Shutdown Prior To Incident.
On Site Datetime 2016-11-03 21:00:00
Nrc Rpt Datetime 2016-11-04 12:46:00
Nrc Rpt Num 1163308 NRC Report How to search
Ignite Ind No
Explode Ind No
Upstream Valve Type Ind Remotely Controlled
Downstream Valve Type Ind Remotely Controlled
Num Pub Evacuated 0
Pipe Fac Name Northwest Product System
Segment Name Pocatello To Uprr
Onshore State Abbreviation Id
Onshore Postal Code 83201
Onshore City Name Pocatello
Onshore County Name Bannock
Designated Location Milepost/valve Station
Designated Name Milepost 3.9
Federal No
Location Type Pipeline Right-Of-Way
Incident Area Type Aboveground
Incident Area Subtype Overhead Crossing
Crossing Yes
Railroad Crossing Ind Yes
Railroad Type Uncased
Pipe Facility Type Interstate
Item Involved Pipe
Pipe Type Pipe Body
Pipe Diameter 8.625
Pipe Wall Thickness 0.5
Pipe Smys 35000
Pipe Specification Grade B
Pipe Seam Type Erw � Unknown Frequency
Pipe Manufacturer Uss Steel
Pipe Coating Type Paint
Installation Year 1963
Manufactured Year 1963
Material Involved Carbon Steel
Release Type Mechanical Puncture
Puncture Axial 34
Puncture Circum 10
Wildlife Impact Ind No
Soil Contamination No
Long Term Assessment No
Remediation Ind No
Water Contam Ind No
Could Be Hca Yes
Commodity Reached Hca Yes
High Pop Ind Yes
High Pop Yes No Yes
Est Cost Oper Paid 0
Est Cost Gas Released 80
Est Cost Prop Damage 50000
Est Cost Emergency 23000
Est Cost Environmental 0
Est Cost Other 0
Prpty 73080
Accident Psig 0
Mop Psig 285
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Length Segment Isolated 19237
Internal Inspection Ind Yes
Operation Complications Ind No
Pipeline Function < 20% Smys Regulated Transmission
Scada In Place Ind Yes
Scada Operating Ind No
Scada Functional Ind Yes
Scada Detection Ind No
Scada Conf Ind No
Cpm In Place Ind Yes
Cpm Operating Ind No
Cpm Functional Ind Yes
Cpm Detection Ind No
Cpm Conf Ind No
Investigation Status No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details The line was shut in prior to the incident.
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Other Outside Force Damage
Cause Details Damage By Car, Truck, Or Other Motorized Vehicle/equipment Not Engaged In Excavation
Outside Force Type Damage By Car, Truck, Or Other Motorized Vehicle/equipment Not Engaged In Excavation
Vehicle Subtype Third Party
Preparer Name A***** R********
Preparer Title Sr. Regulatory Compliance Specialist
Preparer Email A***************@t******.com
Preparer Telephone 210-626-4262
Prepared Date 2016-12-02 00:00:00
Authorizer Name A**** M*******
Authorizer Telephone 210-626-6343
Authorizer Title Director Compliance Logistics
Authorizer Email A***************@t******.com
Narrative On november 3, 2016 a driver struck the pocatello to uprr 8" line segments at an overhead railroad crossing. The boom lift on the logging truck hit the bridge and damaged the line releasing approximately 30 gallons of diesel fuel. The line has been repaired, and the spill has been clean up.