HL incident on 2016-03-18 — TX

Operator
Summit Midstream Partners, Llc
Cause
Other Outside Force Damage
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$50
Incident datetime
2016-03-18 10:50
Report number
Location
TX
Narrative
A leak was discovered on the stampede pipeline at valve site #5 by a landowner at approximately 10:50 am on 3/18/16 in divide county, north dakota. The leak appears to be caused by an act of vandalism due to a pressure gauge being shot out at the aboveground valve site. The line was shut-in prior to the accident and the leak was discovered when the line was restarted. There were no indications of a pressure drop by the control room. Spill was estimated to be 150 bbls. Remediation of the impacted soil was performed. Supplement / final report: summary a crude oil leak was discovered on the stampede pipeline at valve site #5 by a landowner at approximately 10:50 am on 3/18/16 in divide county, north dakota. The leak was reported by a land owner. Vandalism was the cause of the leak. A local pressure gauge at valve site #5 on the pipeline was punctured by a bullet fired from a gun. Background: the pipeline was blocked in and not flowing when the gauge was shot and initially started leaking. On 3/18/16 the pipeline resumed flow and shortly after the pipeline restarted the control center was notified of the leak. The control center isolated the remote valve at the start of the pipeline at summit's divide station and the remote valve at the end of the pipeline at the global rail facility. At the time of the incident there were no indications of a pressure drop by the control room. Response and agency notification a summit representative was dispatched to the valve site. Upon arrival, the representative found the gauge leaking an isolated the 1/2 inch valve below the gauge to stop the leak. An initial assessment of the area was conducted to determine soil impact. A determination through soil calculation models showed the leak to be minor in nature, 4.7 barrels, and that it would not meet PHMSA telephonic reporting requirements of $50,000 threshold. Instead, the report would be filed under the requirements of PHMSA's 30 day notification. It did however meet the ndic and nddh requirements and a report was filed with state of north dakota. Remediation site remediation was started on 3/18/2016. All affected soil was thought to have been excavated and stored before releasing the contractor on 3/18/2016 end of day. On monday 3/21/2016, the remediation contractor returned to conduct soil testing. Tests concluded that the oil had migrated further out than the original determined. On 3/22/2016 evidence was found that the oil leak followed the path of the pipe and underground. On 3/23/2016 it was determined that testing and cleanup efforts for this spill would exceed $50,000 and a telephonic report was made to the ncr notifying PHMSA of the qualifying spill. The site assessment and spill calculations determined the spill to be 103 barrels. Summit reported 150 barrel which was 1.5 times the estimated spill volume to give PHMSA a worst case estimate. The final spill volume was calculated at 120 barrels and the quantity of soil impacted was 3,825 tons. Repairs and preventative actions the gauge was isolated approximately one hour and fifteen minutes after notification of the leak. Both ends of the pipeline were immediately shut down remotely by the control center. The gauge was removed and the valve was plugged. Subsequently, summit has removed all local pressure gauges from the pipeline to prevent future vandalism on our pipeline.
Detailed record list
Report Received Date
2016-04-18 00:00:00
Iyear
2016
Report Number
20160116
Supplemental Number
21608
Report Type
Supplemental Final
Operator Id
Name
Summit Midstream Partners, Llc
Operator Street Address
910 Louisiana St. Suite 4200
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2016-03-18 10:50:00
Location Latitude
Location Longitude
-103.0229941
Commodity Released Type
Crude Oil
Unintentional Release Bbls
150
Recovered Bbls
150
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Notification From Public
Incident Identified Datetime
2016-03-18 10:50:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2016-03-18 11:08:00
Restart Datetime
2016-03-18 15:57:00
On Site Datetime
2016-03-18 12:04:00
Nrc Rpt Datetime
2016-03-23 16:33:00
Nrc Rpt Num
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Remotely Controlled
Downstream Valve Type Ind
Manual
Num Pub Evacuated
0
Pipe Fac Name
Stampede Lateral
Segment Name
Valve Site #5
Onshore State Abbreviation
Nd
Onshore Postal Code
58795
Onshore City Name
Not Within A Municipality
Onshore County Name
Divide
Designated Location
Milepost/valve Station
Designated Name
Valve Site #5
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Aboveground
Incident Area Subtype
Typical Aboveground Facility Piping Or Appurtenance
Crossing
No
Pipe Facility Type
Intrastate
Item Involved
Other
Item Involved Details
Pressure Gauge
Installation Year
2016
Material Involved
Material Other Than Carbon Steel
Material Details
Pressure Gauge Glass And Housing
Release Type
Leak
Leak Type
Other
Leak Type Other
Pressure Gauge Shot Out
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
Yes
Soil Remed Ind
Yes
Water Contam Ind
No
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
0
Est Cost Gas Released
6000
Est Cost Prop Damage
50
Est Cost Emergency
0
Est Cost Environmental
514000
Est Cost Other
0
Prpty
520050
Accident Psig
120
Mop Psig
1440
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
244015
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
No
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
Yes, specify investigation result(s): (select all that apply)
Invest Schedule Ind
Yes
Invest No Control Room Ind
Yes
Invest No Controller Ind
Yes
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Other Outside Force Damage
Cause Details
Intentional Damage
Outside Force Type
Intentional Damage
Intentional Subtype
Vandalism
Preparer Name
M****** S********
Preparer Title
Director Of Health Safety And Regulatory
Preparer Email
M*********@s**************.com
Preparer Telephone
8324134769
Prepared Date
2016-08-17 00:00:00
Authorizer Name
M****** S********
Authorizer Telephone
8324134769
Authorizer Title
Director Of Health Safety And Regulatory
Authorizer Email
M*********@s**************.com
Narrative
A leak was discovered on the stampede pipeline at valve site #5 by a landowner at approximately 10:50 am on 3/18/16 in divide county, north dakota. The leak appears to be caused by an act of vandalism due to a pressure gauge being shot out at the aboveground valve site. The line was shut-in prior to the accident and the leak was discovered when the line was restarted. There were no indications of a pressure drop by the control room. Spill was estimated to be 150 bbls. Remediation of the impacted soil was performed. Supplement / final report: summary a crude oil leak was discovered on the stampede pipeline at valve site #5 by a landowner at approximately 10:50 am on 3/18/16 in divide county, north dakota. The leak was reported by a land owner. Vandalism was the cause of the leak. A local pressure gauge at valve site #5 on the pipeline was punctured by a bullet fired from a gun. Background: the pipeline was blocked in and not flowing when the gauge was shot and initially started leaking. On 3/18/16 the pipeline resumed flow and shortly after the pipeline restarted the control center was notified of the leak. The control center isolated the remote valve at the start of the pipeline at summit's divide station and the remote valve at the end of the pipeline at the global rail facility. At the time of the incident there were no indications of a pressure drop by the control room. Response and agency notification a summit representative was dispatched to the valve site. Upon arrival, the representative found the gauge leaking an isolated the 1/2 inch valve below the gauge to stop the leak. An initial assessment of the area was conducted to determine soil impact. A determination through soil calculation models showed the leak to be minor in nature, 4.7 barrels, and that it would not meet PHMSA telephonic reporting requirements of $50,000 threshold. Instead, the report would be filed under the requirements of PHMSA's 30 day notification. It did however meet the ndic and nddh requirements and a report was filed with state of north dakota. Remediation site remediation was started on 3/18/2016. All affected soil was thought to have been excavated and stored before releasing the contractor on 3/18/2016 end of day. On monday 3/21/2016, the remediation contractor returned to conduct soil testing. Tests concluded that the oil had migrated further out than the original determined. On 3/22/2016 evidence was found that the oil leak followed the path of the pipe and underground. On 3/23/2016 it was determined that testing and cleanup efforts for this spill would exceed $50,000 and a telephonic report was made to the ncr notifying PHMSA of the qualifying spill. The site assessment and spill calculations determined the spill to be 103 barrels. Summit reported 150 barrel which was 1.5 times the estimated spill volume to give PHMSA a worst case estimate. The final spill volume was calculated at 120 barrels and the quantity of soil impacted was 3,825 tons. Repairs and preventative actions the gauge was isolated approximately one hour and fifteen minutes after notification of the leak. Both ends of the pipeline were immediately shut down remotely by the control center. The gauge was removed and the valve was plugged. Subsequently, summit has removed all local pressure gauges from the pipeline to prevent future vandalism on our pipeline.
Report Received Date 2016-04-18 00:00:00
Iyear 2016
Report Number 20160116
Supplemental Number 21608
Report Type Supplemental Final
Operator Id 39012 PHMSA Enforcement
Name Summit Midstream Partners, Llc
Operator Street Address 910 Louisiana St. Suite 4200
Operator City Name Houston
Operator State Abbreviation TX
Operator Postal Code 77002
Local Datetime 2016-03-18 10:50:00
Location Latitude 48.85108984 Google Maps OpenStreetMap
Location Longitude -103.0229941 Google Maps OpenStreetMap
Commodity Released Type Crude Oil
Unintentional Release Bbls 150
Recovered Bbls 150
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Notification From Public
Incident Identified Datetime 2016-03-18 10:50:00
System Part Involved Onshore Pipeline, Including Valve Sites
On Off Shore Onshore
Shutdown Due Accident Ind Yes
Shutdown Datetime 2016-03-18 11:08:00
Restart Datetime 2016-03-18 15:57:00
On Site Datetime 2016-03-18 12:04:00
Nrc Rpt Datetime 2016-03-23 16:33:00
Nrc Rpt Num 1143560 NRC Report How to search
Ignite Ind No
Explode Ind No
Upstream Valve Type Ind Remotely Controlled
Downstream Valve Type Ind Manual
Num Pub Evacuated 0
Pipe Fac Name Stampede Lateral
Segment Name Valve Site #5
Onshore State Abbreviation Nd
Onshore Postal Code 58795
Onshore City Name Not Within A Municipality
Onshore County Name Divide
Designated Location Milepost/valve Station
Designated Name Valve Site #5
Federal No
Location Type Pipeline Right-Of-Way
Incident Area Type Aboveground
Incident Area Subtype Typical Aboveground Facility Piping Or Appurtenance
Crossing No
Pipe Facility Type Intrastate
Item Involved Other
Item Involved Details Pressure Gauge
Installation Year 2016
Material Involved Material Other Than Carbon Steel
Material Details Pressure Gauge Glass And Housing
Release Type Leak
Leak Type Other
Leak Type Other Pressure Gauge Shot Out
Wildlife Impact Ind No
Soil Contamination Yes
Long Term Assessment No
Remediation Ind Yes
Soil Remed Ind Yes
Water Contam Ind No
Could Be Hca No
Commodity Reached Hca No
Est Cost Oper Paid 0
Est Cost Gas Released 6000
Est Cost Prop Damage 50
Est Cost Emergency 0
Est Cost Environmental 514000
Est Cost Other 0
Prpty 520050
Accident Psig 120
Mop Psig 1440
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Length Segment Isolated 244015
Internal Inspection Ind Yes
Operation Complications Ind No
Pipeline Function > 20% Smys Regulated Transmission
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind No
Scada Conf Ind No
Cpm In Place Ind Yes
Cpm Operating Ind Yes
Cpm Functional Ind No
Cpm Detection Ind No
Cpm Conf Ind No
Investigation Status Yes, specify investigation result(s): (select all that apply)
Invest Schedule Ind Yes
Invest No Control Room Ind Yes
Invest No Controller Ind Yes
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Other Outside Force Damage
Cause Details Intentional Damage
Outside Force Type Intentional Damage
Intentional Subtype Vandalism
Preparer Name M****** S********
Preparer Title Director Of Health Safety And Regulatory
Preparer Email M*********@s**************.com
Preparer Telephone 8324134769
Prepared Date 2016-08-17 00:00:00
Authorizer Name M****** S********
Authorizer Telephone 8324134769
Authorizer Title Director Of Health Safety And Regulatory
Authorizer Email M*********@s**************.com
Narrative A leak was discovered on the stampede pipeline at valve site #5 by a landowner at approximately 10:50 am on 3/18/16 in divide county, north dakota. The leak appears to be caused by an act of vandalism due to a pressure gauge being shot out at the aboveground valve site. The line was shut-in prior to the accident and the leak was discovered when the line was restarted. There were no indications of a pressure drop by the control room. Spill was estimated to be 150 bbls. Remediation of the impacted soil was performed. Supplement / final report: summary a crude oil leak was discovered on the stampede pipeline at valve site #5 by a landowner at approximately 10:50 am on 3/18/16 in divide county, north dakota. The leak was reported by a land owner. Vandalism was the cause of the leak. A local pressure gauge at valve site #5 on the pipeline was punctured by a bullet fired from a gun. Background: the pipeline was blocked in and not flowing when the gauge was shot and initially started leaking. On 3/18/16 the pipeline resumed flow and shortly after the pipeline restarted the control center was notified of the leak. The control center isolated the remote valve at the start of the pipeline at summit's divide station and the remote valve at the end of the pipeline at the global rail facility. At the time of the incident there were no indications of a pressure drop by the control room. Response and agency notification a summit representative was dispatched to the valve site. Upon arrival, the representative found the gauge leaking an isolated the 1/2 inch valve below the gauge to stop the leak. An initial assessment of the area was conducted to determine soil impact. A determination through soil calculation models showed the leak to be minor in nature, 4.7 barrels, and that it would not meet PHMSA telephonic reporting requirements of $50,000 threshold. Instead, the report would be filed under the requirements of PHMSA's 30 day notification. It did however meet the ndic and nddh requirements and a report was filed with state of north dakota. Remediation site remediation was started on 3/18/2016. All affected soil was thought to have been excavated and stored before releasing the contractor on 3/18/2016 end of day. On monday 3/21/2016, the remediation contractor returned to conduct soil testing. Tests concluded that the oil had migrated further out than the original determined. On 3/22/2016 evidence was found that the oil leak followed the path of the pipe and underground. On 3/23/2016 it was determined that testing and cleanup efforts for this spill would exceed $50,000 and a telephonic report was made to the ncr notifying PHMSA of the qualifying spill. The site assessment and spill calculations determined the spill to be 103 barrels. Summit reported 150 barrel which was 1.5 times the estimated spill volume to give PHMSA a worst case estimate. The final spill volume was calculated at 120 barrels and the quantity of soil impacted was 3,825 tons. Repairs and preventative actions the gauge was isolated approximately one hour and fifteen minutes after notification of the leak. Both ends of the pipeline were immediately shut down remotely by the control center. The gauge was removed and the valve was plugged. Subsequently, summit has removed all local pressure gauges from the pipeline to prevent future vandalism on our pipeline.

All rights reserved. Copyright © by ClearPHMSA