HL incident on 2015-10-12 — TX

Operator
Kinder Morgan Wink Pipeline Llc
Cause
Corrosion Failure
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$12,000
Incident datetime
2015-10-12 11:09
Report number
Location
TX
Narrative
The aerial patrol pilot notified the control center on 10/12/15 of a possible crude oil leak near kinder morgan's mason station. The controller shutdown the pipeline, and field operations investigated the site. A release was discovered on the 20" wink to guadalupe pipeline, 0.5 miles east of mason station at milepost 159. An engineered leak clamp was applied to the pipeline to mitigate the release while the pipeline was shutdown. A b-sleeve was installed as a permanent repair. The pipeline was shutdown longer than anticipated due to a directive from the receiving refinery, which was not related to the kinder morgan pipeline release.
Detailed record list
Report Received Date
2015-11-11 00:00:00
Iyear
2015
Report Number
20150399
Supplemental Number
20893
Report Type
Original
Operator Id
Name
Kinder Morgan Wink Pipeline Llc
Operator Street Address
1001 Louisiana St, Suite 1000
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2015-10-12 11:30:00
Location Latitude
Location Longitude
Commodity Released Type
Crude Oil
Unintentional Release Bbls
17
Recovered Bbls
9
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Air Patrol
Operator Type
Contractor Working For The Operator
Incident Identified Datetime
2015-10-12 11:09:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2015-10-12 11:09:00
Restart Datetime
2015-10-14 15:20:00
On Site Datetime
2015-10-12 11:30:00
Nrc Rpt Datetime
2015-10-12 12:22:00
Nrc Rpt Num
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Automatic
Downstream Valve Type Ind
Automatic
Num Pub Evacuated
0
Pipe Fac Name
20" Wink To El Paso
Segment Name
20" Wink To Guadalupe
Onshore State Abbreviation
Tx
Onshore Postal Code
79770
Onshore City Name
Orla
Onshore County Name
Loving
Designated Location
Milepost/valve Station
Designated Name
Mp 159
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
30
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Pipe
Pipe Type
Pipe Body
Pipe Diameter
20
Pipe Wall Thickness
0.25
Pipe Smys
52000
Pipe Specification
X-52
Pipe Seam Type
Erw - Low Frequency
Pipe Manufacturer
Ygstn
Pipe Coating Type
Coal Tar
Installation Year
1955
Manufactured Year
1955
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Pinhole
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
Yes
Soil Remed Ind
Yes
Water Contam Ind
No
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
0
Est Cost Gas Released
792
Est Cost Prop Damage
12000
Est Cost Emergency
0
Est Cost Environmental
162000
Est Cost Other
0
Prpty
174792
Accident Psig
158
Mop Psig
526
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
21648
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
No
Investigation Status
Yes, specify investigation result(s): (select all that apply)
Invest No Schedule Ind
Yes
Invest No Schedule Ind Details
The Cause Of The Incident Was Not Related To Controller Actions. The Controller Responded Appropriately To The Leak Report, And Did Not Contribute To The Accident.
Invest No Control Room Ind
Yes
Invest No Controller Ind
Yes
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Corrosion Failure
Cause Details
External Corrosion
Internal External
External Corrosion
Visual Exam Results
Localized Pitting
Galvanic Corrosion Ind
Yes
Microbiological Corrosion Ind
Yes
Field Exam Basis Ind
Yes
Underground Location
Yes
Under Cathodic Protection Ind
Yes
Cathodic Pro Start Year
2004
Shielding Evident
Yes
Cathodic Survey Type
Yes
Cp Annual Survey Ind
Yes
Close Interval Survey Ind
Yes
Cp Annual Survey Year
2015
Close Interval Survey Year
2012
Prior Damage
Yes
Collected Data Ind
Yes
Axial Magnetic Flx Lkg Ind
Yes
Ultrasonic Ind
Yes
Geometry Deformation Ind
Yes
Axial Recent Year
2008
Ultrasonic Recent Year
2013
Geometry Recent Year
2013
Has Hydrtst Conduc Before Ind
Yes
Hydrtst Most Rcnt Year
1983
Hydrtst Most Rcnt Pressure
650
Direct Asmnt Conducted
No
Non Destructive Exam Ind
No
Preparer Name
A**** Z*****
Preparer Title
Manager-Regulatory Compliance
Preparer Email
A***********@k***********.com
Preparer Telephone
713-369-9512
Preparer Fax
303-984-3417
Prepared Date
2015-11-11 00:00:00
Authorizer Name
K****** H H***** J*
Authorizer Telephone
713-369-9113
Authorizer Title
Vice President-Source And Transportation
Authorizer Email
K*********@k***********.com
Narrative
The aerial patrol pilot notified the control center on 10/12/15 of a possible crude oil leak near kinder morgan's mason station. The controller shutdown the pipeline, and field operations investigated the site. A release was discovered on the 20" wink to guadalupe pipeline, 0.5 miles east of mason station at milepost 159. An engineered leak clamp was applied to the pipeline to mitigate the release while the pipeline was shutdown. A b-sleeve was installed as a permanent repair. The pipeline was shutdown longer than anticipated due to a directive from the receiving refinery, which was not related to the kinder morgan pipeline release.
Report Received Date 2015-11-11 00:00:00
Iyear 2015
Report Number 20150399
Supplemental Number 20893
Report Type Original
Operator Id 31957 PHMSA Enforcement
Name Kinder Morgan Wink Pipeline Llc
Operator Street Address 1001 Louisiana St, Suite 1000
Operator City Name Houston
Operator State Abbreviation TX
Operator Postal Code 77002
Local Datetime 2015-10-12 11:30:00
Location Latitude 31.80148 Google Maps OpenStreetMap
Location Longitude -103.79509 Google Maps OpenStreetMap
Commodity Released Type Crude Oil
Unintentional Release Bbls 17
Recovered Bbls 9
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Air Patrol
Operator Type Contractor Working For The Operator
Incident Identified Datetime 2015-10-12 11:09:00
System Part Involved Onshore Pipeline, Including Valve Sites
On Off Shore Onshore
Shutdown Due Accident Ind Yes
Shutdown Datetime 2015-10-12 11:09:00
Restart Datetime 2015-10-14 15:20:00
On Site Datetime 2015-10-12 11:30:00
Nrc Rpt Datetime 2015-10-12 12:22:00
Nrc Rpt Num 1130673 NRC Report How to search
Ignite Ind No
Explode Ind No
Upstream Valve Type Ind Automatic
Downstream Valve Type Ind Automatic
Num Pub Evacuated 0
Pipe Fac Name 20" Wink To El Paso
Segment Name 20" Wink To Guadalupe
Onshore State Abbreviation Tx
Onshore Postal Code 79770
Onshore City Name Orla
Onshore County Name Loving
Designated Location Milepost/valve Station
Designated Name Mp 159
Federal No
Location Type Pipeline Right-Of-Way
Incident Area Type Underground
Incident Area Subtype Under Soil
Depth Of Cover 30
Crossing No
Pipe Facility Type Interstate
Item Involved Pipe
Pipe Type Pipe Body
Pipe Diameter 20
Pipe Wall Thickness 0.25
Pipe Smys 52000
Pipe Specification X-52
Pipe Seam Type Erw - Low Frequency
Pipe Manufacturer Ygstn
Pipe Coating Type Coal Tar
Installation Year 1955
Manufactured Year 1955
Material Involved Carbon Steel
Release Type Leak
Leak Type Pinhole
Wildlife Impact Ind No
Soil Contamination Yes
Long Term Assessment No
Remediation Ind Yes
Soil Remed Ind Yes
Water Contam Ind No
Could Be Hca No
Commodity Reached Hca No
Est Cost Oper Paid 0
Est Cost Gas Released 792
Est Cost Prop Damage 12000
Est Cost Emergency 0
Est Cost Environmental 162000
Est Cost Other 0
Prpty 174792
Accident Psig 158
Mop Psig 526
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Length Segment Isolated 21648
Internal Inspection Ind Yes
Operation Complications Ind No
Pipeline Function > 20% Smys Regulated Transmission
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind No
Scada Conf Ind No
Cpm In Place Ind No
Investigation Status Yes, specify investigation result(s): (select all that apply)
Invest No Schedule Ind Yes
Invest No Schedule Ind Details The Cause Of The Incident Was Not Related To Controller Actions. The Controller Responded Appropriately To The Leak Report, And Did Not Contribute To The Accident.
Invest No Control Room Ind Yes
Invest No Controller Ind Yes
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Corrosion Failure
Cause Details External Corrosion
Internal External External Corrosion
Visual Exam Results Localized Pitting
Galvanic Corrosion Ind Yes
Microbiological Corrosion Ind Yes
Field Exam Basis Ind Yes
Underground Location Yes
Under Cathodic Protection Ind Yes
Cathodic Pro Start Year 2004
Shielding Evident Yes
Cathodic Survey Type Yes
Cp Annual Survey Ind Yes
Close Interval Survey Ind Yes
Cp Annual Survey Year 2015
Close Interval Survey Year 2012
Prior Damage Yes
Collected Data Ind Yes
Axial Magnetic Flx Lkg Ind Yes
Ultrasonic Ind Yes
Geometry Deformation Ind Yes
Axial Recent Year 2008
Ultrasonic Recent Year 2013
Geometry Recent Year 2013
Has Hydrtst Conduc Before Ind Yes
Hydrtst Most Rcnt Year 1983
Hydrtst Most Rcnt Pressure 650
Direct Asmnt Conducted No
Non Destructive Exam Ind No
Preparer Name A**** Z*****
Preparer Title Manager-Regulatory Compliance
Preparer Email A***********@k***********.com
Preparer Telephone 713-369-9512
Preparer Fax 303-984-3417
Prepared Date 2015-11-11 00:00:00
Authorizer Name K****** H H***** J*
Authorizer Telephone 713-369-9113
Authorizer Title Vice President-Source And Transportation
Authorizer Email K*********@k***********.com
Narrative The aerial patrol pilot notified the control center on 10/12/15 of a possible crude oil leak near kinder morgan's mason station. The controller shutdown the pipeline, and field operations investigated the site. A release was discovered on the 20" wink to guadalupe pipeline, 0.5 miles east of mason station at milepost 159. An engineered leak clamp was applied to the pipeline to mitigate the release while the pipeline was shutdown. A b-sleeve was installed as a permanent repair. The pipeline was shutdown longer than anticipated due to a directive from the receiving refinery, which was not related to the kinder morgan pipeline release.