Incident details
Operator, cause, commodity and consequences with raw source fields.
HL incident on 2015-07-22 — TX
Operator
Ultramar Inc
Cause
Corrosion Failure
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$0
Incident datetime
2015-07-22 12:00
Report number
Location
TX
Narrative
On july 22, 2015 at 1100 hours, a third party pipeline operator discovered a leak on a common right-of-way. Valero was notified of a possible leak on the c 959 pipeline at 1200 hours and arrived on site at approximately 1230 hours. The pipeline was already down therefore the only action required was to confirm isolation. After excavating the site and identifying the location of the leak, a temporary clamp was installed to evacuated crude oil from the pipeline. The pipeline was cleared of crude oil and the affected pipe was cut out and a pressure tested replacement pipe was welded. A determination was made on july 28, 2015, that the cause of the leak was microbial internal corrosion. Affected soil was remediated and the pipeline was made available for return to service on august 3, 2015. Final report 12-14-2015 updated part a and part d.
Detailed record list
Report Received Date
2015-08-20 00:00:00
Iyear
2015
Report Number
20150295
Supplemental Number
20978
Report Type
Supplemental Final
Operator Id
20202
Name
Ultramar Inc
Operator Street Address
One Valero Way
Operator City Name
San Antonio
Operator State Abbreviation
TX
Operator Postal Code
78249
Local Datetime
2015-07-22 11:00:00
Location Latitude
33.804707
Location Longitude
-118.222597
Commodity Released Type
Crude Oil
Unintentional Release Bbls
264
Recovered Bbls
56
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Other
Accident Details
Third Party Operator Chevron Discovered The Leak And Notified Valero
Incident Identified Datetime
2015-07-22 12:00:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
No
Shutdown Explain
Pipeline Was Already Down At The Time Of Discovery
On Site Datetime
2015-07-22 14:30:00
Nrc Rpt Datetime
2015-07-22 11:00:00
Nrc Rpt Num
1123585
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Manual
Downstream Valve Type Ind
Manual
Num Pub Evacuated
0
Pipe Fac Name
C-959 Csfm #495
Segment Name
C-959 Csfm #495
Onshore State Abbreviation
Ca
Onshore Postal Code
90744
Onshore City Name
Wilmington
Onshore County Name
Los Angeles
Designated Location
Milepost/valve Station
Designated Name
2401_e_sepulv
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
96
Crossing
No
Pipe Facility Type
Intrastate
Item Involved
Pipe
Pipe Type
Pipe Body
Pipe Diameter
6.625
Pipe Wall Thickness
0.28
Pipe Smys
24000
Pipe Specification
Unknown
Pipe Seam Type
Seamless
Pipe Manufacturer
Unknown
Pipe Coating Type
Cold Applied Tape
Installation Year
1992
Manufactured Year
1992
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Pinhole
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
Yes
Soil Remed Ind
Yes
Water Contam Ind
No
Could Be Hca
No
Commodity Reached Hca
Yes
High Pop Ind
Yes
High Pop Yes No
No
Est Cost Oper Paid
0
Est Cost Gas Released
27720
Est Cost Prop Damage
0
Est Cost Emergency
0
Est Cost Environmental
267152
Est Cost Other
0
Prpty
294872
Accident Psig
0
Mop Psig
740
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
10560
Internal Inspection Ind
No
Diameter Change Ind
Yes
Unsuitable Mainline Ind
Yes
Tight Mitered Ind
Yes
Other Restrictions Ind
Yes
Operation Complications Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
Pipeline was down at the time of the incident
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Corrosion Failure
Cause Details
Internal Corrosion
Internal External
Internal Corrosion
Int Visual Exam Results
Localized Pitting
Int Microbiological Ind
Yes
Int Field Exam Basis Ind
Yes
Int Low Point Pipe Loc Ind
Yes
Int Elbow Loc Ind
Yes
Corrosion Inhibitors
No
Corrosion Lining
No
Cleaning Dewatering
No
Corrosion Coupons
No
Collected Data Ind
No
Has Hydrtst Conduc Before Ind
Yes
Hydrtst Most Rcnt Year
2014
Hydrtst Most Rcnt Pressure
1050
Direct Asmnt Conducted
No
Non Destructive Exam Ind
No
Preparer Name
J**** T******
Preparer Title
Manager Regulatory
Preparer Email
No Email Address
Preparer Telephone
2103455145
Preparer Fax
2103706235
Prepared Date
2015-12-14 00:00:00
Authorizer Name
M*** S*****
Authorizer Telephone
5624916753
Authorizer Title
Superintendent
Authorizer Email
No Email Address
Narrative
On july 22, 2015 at 1100 hours, a third party pipeline operator discovered a leak on a common right-of-way. Valero was notified of a possible leak on the c 959 pipeline at 1200 hours and arrived on site at approximately 1230 hours. The pipeline was already down therefore the only action required was to confirm isolation. After excavating the site and identifying the location of the leak, a temporary clamp was installed to evacuated crude oil from the pipeline. The pipeline was cleared of crude oil and the affected pipe was cut out and a pressure tested replacement pipe was welded. A determination was made on july 28, 2015, that the cause of the leak was microbial internal corrosion. Affected soil was remediated and the pipeline was made available for return to service on august 3, 2015. Final report 12-14-2015 updated part a and part d.
| Report Received Date | 2015-08-20 00:00:00 |
|---|---|
| Iyear | 2015 |
| Report Number | 20150295 |
| Supplemental Number | 20978 |
| Report Type | Supplemental Final |
| Operator Id | 20202 PHMSA Enforcement |
| Name | Ultramar Inc |
| Operator Street Address | One Valero Way |
| Operator City Name | San Antonio |
| Operator State Abbreviation | TX |
| Operator Postal Code | 78249 |
| Local Datetime | 2015-07-22 11:00:00 |
| Location Latitude | 33.804707 Google Maps OpenStreetMap |
| Location Longitude | -118.222597 Google Maps OpenStreetMap |
| Commodity Released Type | Crude Oil |
| Unintentional Release Bbls | 264 |
| Recovered Bbls | 56 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Other |
| Accident Details | Third Party Operator Chevron Discovered The Leak And Notified Valero |
| Incident Identified Datetime | 2015-07-22 12:00:00 |
| System Part Involved | Onshore Pipeline, Including Valve Sites |
| On Off Shore | Onshore |
| Shutdown Due Accident Ind | No |
| Shutdown Explain | Pipeline Was Already Down At The Time Of Discovery |
| On Site Datetime | 2015-07-22 14:30:00 |
| Nrc Rpt Datetime | 2015-07-22 11:00:00 |
| Nrc Rpt Num | 1123585 NRC Report How to search |
| Ignite Ind | No |
| Explode Ind | No |
| Upstream Valve Type Ind | Manual |
| Downstream Valve Type Ind | Manual |
| Num Pub Evacuated | 0 |
| Pipe Fac Name | C-959 Csfm #495 |
| Segment Name | C-959 Csfm #495 |
| Onshore State Abbreviation | Ca |
| Onshore Postal Code | 90744 |
| Onshore City Name | Wilmington |
| Onshore County Name | Los Angeles |
| Designated Location | Milepost/valve Station |
| Designated Name | 2401_e_sepulv |
| Federal | No |
| Location Type | Pipeline Right-Of-Way |
| Incident Area Type | Underground |
| Incident Area Subtype | Under Soil |
| Depth Of Cover | 96 |
| Crossing | No |
| Pipe Facility Type | Intrastate |
| Item Involved | Pipe |
| Pipe Type | Pipe Body |
| Pipe Diameter | 6.625 |
| Pipe Wall Thickness | 0.28 |
| Pipe Smys | 24000 |
| Pipe Specification | Unknown |
| Pipe Seam Type | Seamless |
| Pipe Manufacturer | Unknown |
| Pipe Coating Type | Cold Applied Tape |
| Installation Year | 1992 |
| Manufactured Year | 1992 |
| Material Involved | Carbon Steel |
| Release Type | Leak |
| Leak Type | Pinhole |
| Wildlife Impact Ind | No |
| Soil Contamination | Yes |
| Long Term Assessment | No |
| Remediation Ind | Yes |
| Soil Remed Ind | Yes |
| Water Contam Ind | No |
| Could Be Hca | No |
| Commodity Reached Hca | Yes |
| High Pop Ind | Yes |
| High Pop Yes No | No |
| Est Cost Oper Paid | 0 |
| Est Cost Gas Released | 27720 |
| Est Cost Prop Damage | 0 |
| Est Cost Emergency | 0 |
| Est Cost Environmental | 267152 |
| Est Cost Other | 0 |
| Prpty | 294872 |
| Accident Psig | 0 |
| Mop Psig | 740 |
| Accident Pressure | Pressure Did Not Exceed Mop |
| Pressure Restriction Ind | No |
| Length Segment Isolated | 10560 |
| Internal Inspection Ind | No |
| Diameter Change Ind | Yes |
| Unsuitable Mainline Ind | Yes |
| Tight Mitered Ind | Yes |
| Other Restrictions Ind | Yes |
| Operation Complications Ind | No |
| Pipeline Function | > 20% Smys Regulated Transmission |
| Scada In Place Ind | Yes |
| Scada Operating Ind | Yes |
| Scada Functional Ind | Yes |
| Scada Detection Ind | No |
| Scada Conf Ind | No |
| Cpm In Place Ind | No |
| Investigation Status | No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate) |
| Investigation Status Details | Pipeline was down at the time of the incident |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | No |
| Cause | Corrosion Failure |
| Cause Details | Internal Corrosion |
| Internal External | Internal Corrosion |
| Int Visual Exam Results | Localized Pitting |
| Int Microbiological Ind | Yes |
| Int Field Exam Basis Ind | Yes |
| Int Low Point Pipe Loc Ind | Yes |
| Int Elbow Loc Ind | Yes |
| Corrosion Inhibitors | No |
| Corrosion Lining | No |
| Cleaning Dewatering | No |
| Corrosion Coupons | No |
| Collected Data Ind | No |
| Has Hydrtst Conduc Before Ind | Yes |
| Hydrtst Most Rcnt Year | 2014 |
| Hydrtst Most Rcnt Pressure | 1050 |
| Direct Asmnt Conducted | No |
| Non Destructive Exam Ind | No |
| Preparer Name | J**** T****** |
| Preparer Title | Manager Regulatory |
| Preparer Email | No Email Address |
| Preparer Telephone | 2103455145 |
| Preparer Fax | 2103706235 |
| Prepared Date | 2015-12-14 00:00:00 |
| Authorizer Name | M*** S***** |
| Authorizer Telephone | 5624916753 |
| Authorizer Title | Superintendent |
| Authorizer Email | No Email Address |
| Narrative | On july 22, 2015 at 1100 hours, a third party pipeline operator discovered a leak on a common right-of-way. Valero was notified of a possible leak on the c 959 pipeline at 1200 hours and arrived on site at approximately 1230 hours. The pipeline was already down therefore the only action required was to confirm isolation. After excavating the site and identifying the location of the leak, a temporary clamp was installed to evacuated crude oil from the pipeline. The pipeline was cleared of crude oil and the affected pipe was cut out and a pressure tested replacement pipe was welded. A determination was made on july 28, 2015, that the cause of the leak was microbial internal corrosion. Affected soil was remediated and the pipeline was made available for return to service on august 3, 2015. Final report 12-14-2015 updated part a and part d. |