GD incident on 2015-04-29 — WI

Operator
Wisconsin Gas Llc Dba We Energies
Cause
Notification Issue
Commodity
Natural Gas
Program
GD
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$3,000
Incident datetime
2015-04-29 09:32
Report number
Location
WI, TAYLOR
Narrative
On wednesday, april 29th, 2015, at 9:32 a.M., we energies was notified by a local fire department that a gas main had been struck by a contractor performing soil borings at 316 s. Main street in medford, wisconsin. We energies dispatched a first responder to the site at 9:34 a.M. And determined the valves required to stop the flow of gas. While the fire department was evacuating buildings within a 2 block radius of the damaged gas main, the gas ignited at approximately 9:45 a.M. It is believed that the soil boring machine, which was left on, was the source of ignition. The first employee from we energies arrived on site at 10:05 a.M. And the gas was shut off at 10:37 a.M. Once the gas was shut off and the site was deemed safe, we energies employees assessed whether or not this event met the criteria of a reportable incident. It was determined that there were no injuries or fatalities and that the amount of gas released was well below 3 mmcf; however, property damage of more than $50,000 occurred. A phone notification was made to the national response center at 11:38 a.M. Of a possible natural gas incident per 49 cfr part 191.3. The wisconsin public service commission pipeline safety manager was also informed of the incident. After the fire had been completely extinguished and the debris had been removed, we energies replaced the damage section of 4 inch steel main. The main repair was completed by about 4:00 p.M. And restoring service to the 13 customers affected proceeded through the evening. Investigation of the incident determined that the soil boring contractor provided an inadequate description of the area requiring utility locates to the one call system.
Detailed record list
Occurred At
2015-04-29 09:32:00
Year
2015
Report Received Date
2015-05-26 00:00:00
Iyear
2015.0
Report Number
20150051.0
Supplemental Number
16086.0
Report Type
Original Final
Operator Id
Name
Wisconsin Gas Llc Dba We Energies
Operator Street Address
231 W. Michigan Street
Operator City Name
Milwaukee
Operator State Abbreviation
WI
Operator Postal Code
53203
Local Datetime
2015-04-29 10:05:00
Location Street Address
316 S. Main Street
Location City Name
Medford
Location County Name
Taylor
Location State Abbreviation
WI
Location Postal Code
54451
Location Latitude
Location Longitude
Nrc Rpt Datetime
2015-04-29 11:38:00
Nrc Rpt Num
Commodity Released Type
Natural Gas
Unintentional Release
339.0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Ignite Ind
Yes
Explode Ind
No
Num Pub Evacuated
60.0
Incident Identified Datetime
2015-04-29 09:32:00
On Site Datetime
2015-04-29 10:05:00
Federal
No
Location Type
Public Property
Incident Area Type
Underground
Incident Area Subtype
Exposed Due To Excavation
Depth Of Cover
38.0
Crossing
No
Pipe Facility Type
Investor Owned
System Part Involved
Main
Installation Year
1963.0
Pipe Diameter
4.0
Pipe Specification
Api 5l
Pipe Manufacturer
Acme - Newport Steel Company
Material Involved
Steel
Steel Seam Type
Other
Steel Seam Type Details
Erw
Wt Steel
0.156
Release Type
Mechanical Puncture
Puncture Axial
9.0
Puncture Circum
3.0
Class Location Type
Class 3 Location
Est Cost Oper Paid
112500.0
Est Cost Prop Damage
3000.0
Est Cost Emergency
2500.0
Est Cost Other
0.0
Est Cost Unintentional Release
1836.0
Prpty
119836.0
Commercial Affected
4.0
Industrial Affected
0.0
Residences Affected
9.0
Accident Psig
55.0
Normal Psig
55.0
Mop Psig
60.0
Accident Pressure
Pressure Did Not Exceed Maop
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Accident Identifier
Notification From Emergency Responder
Investigation Status
Yes, specify investigation result(s): (select all that apply)
Invest No Schedule Ind
Yes
Invest No Schedule Ind Details
The Incident Was Clearly The Result Of 3rd Party Excavation Damage.
Invest No Control Room Ind
Yes
Invest No Controller Ind
Yes
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Excavation Damage
Cause Details
Excavation Damage By Third Party
Ex Party Type
Excavation Damage By Third Party
Prior Notification Ind
Yes
One Call System Ind
Yes
Notify Cga Dirt
No
Public Row Ind
Yes
Public Subtype
City Street
Excavator Type
Contractor
Excavator Equipment
Auger
Work Performed
Unknown/other
One Call Notified Ind
Yes
One Call Ticket Num
20151715490
Locator Type
Contract Locator
Visible Marks
No
Service Interruption
Yes
Service Interruption Hours
6.0
Root Cause Category
Notification Issue
Root Cause Type
Excavator Provided Incorrect Notification Information
Preparer Name
C********** G****
Preparer Title
Engineer
Preparer Email
C****************@w**********.com
Preparer Telephone
(414) 221-5347
Authorizer Name
T** S*******
Authorizer Title
Manager Regulatory Compliance
Authorizer Telephone
414-221-5173
Authorizer Email
T***********@w**********.com
Narrative
On wednesday, april 29th, 2015, at 9:32 a.M., we energies was notified by a local fire department that a gas main had been struck by a contractor performing soil borings at 316 s. Main street in medford, wisconsin. We energies dispatched a first responder to the site at 9:34 a.M. And determined the valves required to stop the flow of gas. While the fire department was evacuating buildings within a 2 block radius of the damaged gas main, the gas ignited at approximately 9:45 a.M. It is believed that the soil boring machine, which was left on, was the source of ignition. The first employee from we energies arrived on site at 10:05 a.M. And the gas was shut off at 10:37 a.M. Once the gas was shut off and the site was deemed safe, we energies employees assessed whether or not this event met the criteria of a reportable incident. It was determined that there were no injuries or fatalities and that the amount of gas released was well below 3 mmcf; however, property damage of more than $50,000 occurred. A phone notification was made to the national response center at 11:38 a.M. Of a possible natural gas incident per 49 cfr part 191.3. The wisconsin public service commission pipeline safety manager was also informed of the incident. After the fire had been completely extinguished and the debris had been removed, we energies replaced the damage section of 4 inch steel main. The main repair was completed by about 4:00 p.M. And restoring service to the 13 customers affected proceeded through the evening. Investigation of the incident determined that the soil boring contractor provided an inadequate description of the area requiring utility locates to the one call system.
Occurred At 2015-04-29 09:32:00
Year 2015
Report Received Date 2015-05-26 00:00:00
Iyear 2015.0
Report Number 20150051.0
Supplemental Number 16086.0
Report Type Original Final
Operator Id 22763 PHMSA Enforcement
Name Wisconsin Gas Llc Dba We Energies
Operator Street Address 231 W. Michigan Street
Operator City Name Milwaukee
Operator State Abbreviation WI
Operator Postal Code 53203
Local Datetime 2015-04-29 10:05:00
Location Street Address 316 S. Main Street
Location City Name Medford
Location County Name Taylor
Location State Abbreviation WI
Location Postal Code 54451
Location Latitude 45.136 Google Maps OpenStreetMap
Location Longitude -90.3428 Google Maps OpenStreetMap
Nrc Rpt Datetime 2015-04-29 11:38:00
Nrc Rpt Num 115011 NRC Report How to search
Commodity Released Type Natural Gas
Unintentional Release 339.0
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Ignite Ind Yes
Explode Ind No
Num Pub Evacuated 60.0
Incident Identified Datetime 2015-04-29 09:32:00
On Site Datetime 2015-04-29 10:05:00
Federal No
Location Type Public Property
Incident Area Type Underground
Incident Area Subtype Exposed Due To Excavation
Depth Of Cover 38.0
Crossing No
Pipe Facility Type Investor Owned
System Part Involved Main
Installation Year 1963.0
Pipe Diameter 4.0
Pipe Specification Api 5l
Pipe Manufacturer Acme - Newport Steel Company
Material Involved Steel
Steel Seam Type Other
Steel Seam Type Details Erw
Wt Steel 0.156
Release Type Mechanical Puncture
Puncture Axial 9.0
Puncture Circum 3.0
Class Location Type Class 3 Location
Est Cost Oper Paid 112500.0
Est Cost Prop Damage 3000.0
Est Cost Emergency 2500.0
Est Cost Other 0.0
Est Cost Unintentional Release 1836.0
Prpty 119836.0
Commercial Affected 4.0
Industrial Affected 0.0
Residences Affected 9.0
Accident Psig 55.0
Normal Psig 55.0
Mop Psig 60.0
Accident Pressure Pressure Did Not Exceed Maop
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind No
Scada Conf Ind No
Accident Identifier Notification From Emergency Responder
Investigation Status Yes, specify investigation result(s): (select all that apply)
Invest No Schedule Ind Yes
Invest No Schedule Ind Details The Incident Was Clearly The Result Of 3rd Party Excavation Damage.
Invest No Control Room Ind Yes
Invest No Controller Ind Yes
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Excavation Damage
Cause Details Excavation Damage By Third Party
Ex Party Type Excavation Damage By Third Party
Prior Notification Ind Yes
One Call System Ind Yes
Notify Cga Dirt No
Public Row Ind Yes
Public Subtype City Street
Excavator Type Contractor
Excavator Equipment Auger
Work Performed Unknown/other
One Call Notified Ind Yes
One Call Ticket Num 20151715490
Locator Type Contract Locator
Visible Marks No
Service Interruption Yes
Service Interruption Hours 6.0
Root Cause Category Notification Issue
Root Cause Type Excavator Provided Incorrect Notification Information
Preparer Name C********** G****
Preparer Title Engineer
Preparer Email C****************@w**********.com
Preparer Telephone (414) 221-5347
Authorizer Name T** S*******
Authorizer Title Manager Regulatory Compliance
Authorizer Telephone 414-221-5173
Authorizer Email T***********@w**********.com
Narrative On wednesday, april 29th, 2015, at 9:32 a.M., we energies was notified by a local fire department that a gas main had been struck by a contractor performing soil borings at 316 s. Main street in medford, wisconsin. We energies dispatched a first responder to the site at 9:34 a.M. And determined the valves required to stop the flow of gas. While the fire department was evacuating buildings within a 2 block radius of the damaged gas main, the gas ignited at approximately 9:45 a.M. It is believed that the soil boring machine, which was left on, was the source of ignition. The first employee from we energies arrived on site at 10:05 a.M. And the gas was shut off at 10:37 a.M. Once the gas was shut off and the site was deemed safe, we energies employees assessed whether or not this event met the criteria of a reportable incident. It was determined that there were no injuries or fatalities and that the amount of gas released was well below 3 mmcf; however, property damage of more than $50,000 occurred. A phone notification was made to the national response center at 11:38 a.M. Of a possible natural gas incident per 49 cfr part 191.3. The wisconsin public service commission pipeline safety manager was also informed of the incident. After the fire had been completely extinguished and the debris had been removed, we energies replaced the damage section of 4 inch steel main. The main repair was completed by about 4:00 p.M. And restoring service to the 13 customers affected proceeded through the evening. Investigation of the incident determined that the soil boring contractor provided an inadequate description of the area requiring utility locates to the one call system.