Incident details
Operator, cause, commodity and consequences with raw source fields.
HL incident on 2014-11-19 — TX
Operator
Sunoco Pipeline L.p.
Cause
Incorrect Operation
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$2,000
Incident datetime
2014-11-19 15:00
Report number
Location
TX
Narrative
Crude oil leaked from an underground flange connection that was not supported properly after installation in the ditch. The lack of proper support may have been a key contributing factor in the loosening of the flange bolts which ultimately led to the release. During line refill crude oil surfaced at this location and migrated into a drainage ditch that ultimately discharges into hawkins branch creek. Approximately one (1) gallon of crude oil impacted hawkins branch creek. After discovery of the release proper nrc and rrc notifications were made. All free oil was promptly cleaned up from the soil and water surfaces. The flanged connection was excavated, proper supporting fill material was installed in the ditch and the flange was re-torqued. The line was refilled, pressurized and checked for leakage. No further leakage was present and the line was returned to service.
Detailed record list
Report Received Date
2014-12-16 00:00:00
Iyear
2014
Report Number
20140426
Supplemental Number
20173
Report Type
Supplemental Final
Operator Id
18718
Name
Sunoco Pipeline L.p.
Operator Street Address
1300 Main Street
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2014-11-19 15:00:00
Location Latitude
32.53403
Location Longitude
-94.84332
Commodity Released Type
Crude Oil
Unintentional Release Bbls
1.5
Recovered Bbls
1
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Operator Employee
Incident Identified Datetime
2014-11-19 15:00:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
No
Shutdown Explain
Line Segment Already Down For Scheduled Maintenance.
On Site Datetime
2014-11-19 15:00:00
Nrc Rpt Datetime
2014-11-19 15:48:00
Nrc Rpt Num
1101483
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Manual
Downstream Valve Type Ind
Manual
Num Pub Evacuated
0
Pipe Fac Name
Longview Gathering
Segment Name
612060-Longview Gathering-4-8" A
Onshore State Abbreviation
Tx
Onshore Postal Code
75693
Onshore City Name
White Oak
Onshore County Name
Gregg
Designated Location
Survey Station No.
Designated Name
0+00
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
36
Crossing
No
Pipe Facility Type
Intrastate
Item Involved
Flange Assembly
Installation Year
2014
Material Involved
Material Other Than Carbon Steel
Material Details
Interface Btn Poly & Carbon Steel Flange
Release Type
Leak
Leak Type
Connection Failure
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
Yes
Surface Water Remed Ind
Yes
Soil Remed Ind
Yes
Water Contam Ind
Yes
Surface Contam Ind
Yes
Amount Released
0.1
Rel Water Name
Hawkins Branch Creek
Could Be Hca
Yes
Commodity Reached Hca
Yes
High Pop Ind
Yes
High Pop Yes No
Yes
Usa Drinking Ind
Yes
Usa Drinking Yes No
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
50
Est Cost Prop Damage
2000
Est Cost Emergency
0
Est Cost Environmental
47458
Est Cost Other
0
Prpty
49508
Accident Psig
50
Mop Psig
125
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
6000
Internal Inspection Ind
No
Diameter Change Ind
Yes
Operation Complications Ind
Yes
Low Op Pressure Ind
Yes
Low Flow Ind
Yes
Pipeline Function
< 20% Smys Regulated Transmission
Scada In Place Ind
No
Cpm In Place Ind
No
Investigation Status
No, the facility was not monitored by a controller(s) at the time of the accident
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Incorrect Operation
Cause Details
Equipment Not Installed Properly
Operation Type
Equipment Not Installed Properly
Related Failure Follow Ind
Yes
Category Type
Commissioning
Operator Qualification Ind
Yes
Qualified Individuals
No, But They Were Performing The Task(S) Under The Direction And Observation Of A Qualified Individual
Preparer Name
T*** G* N*******
Preparer Title
Dot Compliance Manager
Preparer Email
T*********@s**************.com
Preparer Telephone
281-637-6576
Preparer Fax
877-917-0448
Prepared Date
2015-02-25 00:00:00
Authorizer Name
T*** G* N*******
Authorizer Telephone
281-637-6576
Authorizer Title
Dot Compliance Manager
Authorizer Email
T*********@s**************.com
Narrative
Crude oil leaked from an underground flange connection that was not supported properly after installation in the ditch. The lack of proper support may have been a key contributing factor in the loosening of the flange bolts which ultimately led to the release. During line refill crude oil surfaced at this location and migrated into a drainage ditch that ultimately discharges into hawkins branch creek. Approximately one (1) gallon of crude oil impacted hawkins branch creek. After discovery of the release proper nrc and rrc notifications were made. All free oil was promptly cleaned up from the soil and water surfaces. The flanged connection was excavated, proper supporting fill material was installed in the ditch and the flange was re-torqued. The line was refilled, pressurized and checked for leakage. No further leakage was present and the line was returned to service.
| Report Received Date | 2014-12-16 00:00:00 |
|---|---|
| Iyear | 2014 |
| Report Number | 20140426 |
| Supplemental Number | 20173 |
| Report Type | Supplemental Final |
| Operator Id | 18718 PHMSA Enforcement |
| Name | Sunoco Pipeline L.p. |
| Operator Street Address | 1300 Main Street |
| Operator City Name | Houston |
| Operator State Abbreviation | TX |
| Operator Postal Code | 77002 |
| Local Datetime | 2014-11-19 15:00:00 |
| Location Latitude | 32.53403 Google Maps OpenStreetMap |
| Location Longitude | -94.84332 Google Maps OpenStreetMap |
| Commodity Released Type | Crude Oil |
| Unintentional Release Bbls | 1.5 |
| Recovered Bbls | 1 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Local Operating Personnel, Including Contractors |
| Operator Type | Operator Employee |
| Incident Identified Datetime | 2014-11-19 15:00:00 |
| System Part Involved | Onshore Pipeline, Including Valve Sites |
| On Off Shore | Onshore |
| Shutdown Due Accident Ind | No |
| Shutdown Explain | Line Segment Already Down For Scheduled Maintenance. |
| On Site Datetime | 2014-11-19 15:00:00 |
| Nrc Rpt Datetime | 2014-11-19 15:48:00 |
| Nrc Rpt Num | 1101483 NRC Report How to search |
| Ignite Ind | No |
| Explode Ind | No |
| Upstream Valve Type Ind | Manual |
| Downstream Valve Type Ind | Manual |
| Num Pub Evacuated | 0 |
| Pipe Fac Name | Longview Gathering |
| Segment Name | 612060-Longview Gathering-4-8" A |
| Onshore State Abbreviation | Tx |
| Onshore Postal Code | 75693 |
| Onshore City Name | White Oak |
| Onshore County Name | Gregg |
| Designated Location | Survey Station No. |
| Designated Name | 0+00 |
| Federal | No |
| Location Type | Pipeline Right-Of-Way |
| Incident Area Type | Underground |
| Incident Area Subtype | Under Soil |
| Depth Of Cover | 36 |
| Crossing | No |
| Pipe Facility Type | Intrastate |
| Item Involved | Flange Assembly |
| Installation Year | 2014 |
| Material Involved | Material Other Than Carbon Steel |
| Material Details | Interface Btn Poly & Carbon Steel Flange |
| Release Type | Leak |
| Leak Type | Connection Failure |
| Wildlife Impact Ind | No |
| Soil Contamination | Yes |
| Long Term Assessment | No |
| Remediation Ind | Yes |
| Surface Water Remed Ind | Yes |
| Soil Remed Ind | Yes |
| Water Contam Ind | Yes |
| Surface Contam Ind | Yes |
| Amount Released | 0.1 |
| Rel Water Name | Hawkins Branch Creek |
| Could Be Hca | Yes |
| Commodity Reached Hca | Yes |
| High Pop Ind | Yes |
| High Pop Yes No | Yes |
| Usa Drinking Ind | Yes |
| Usa Drinking Yes No | Yes |
| Est Cost Oper Paid | 0 |
| Est Cost Gas Released | 50 |
| Est Cost Prop Damage | 2000 |
| Est Cost Emergency | 0 |
| Est Cost Environmental | 47458 |
| Est Cost Other | 0 |
| Prpty | 49508 |
| Accident Psig | 50 |
| Mop Psig | 125 |
| Accident Pressure | Pressure Did Not Exceed Mop |
| Pressure Restriction Ind | No |
| Length Segment Isolated | 6000 |
| Internal Inspection Ind | No |
| Diameter Change Ind | Yes |
| Operation Complications Ind | Yes |
| Low Op Pressure Ind | Yes |
| Low Flow Ind | Yes |
| Pipeline Function | < 20% Smys Regulated Transmission |
| Scada In Place Ind | No |
| Cpm In Place Ind | No |
| Investigation Status | No, the facility was not monitored by a controller(s) at the time of the accident |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | No |
| Cause | Incorrect Operation |
| Cause Details | Equipment Not Installed Properly |
| Operation Type | Equipment Not Installed Properly |
| Related Failure Follow Ind | Yes |
| Category Type | Commissioning |
| Operator Qualification Ind | Yes |
| Qualified Individuals | No, But They Were Performing The Task(S) Under The Direction And Observation Of A Qualified Individual |
| Preparer Name | T*** G* N******* |
| Preparer Title | Dot Compliance Manager |
| Preparer Email | T*********@s**************.com |
| Preparer Telephone | 281-637-6576 |
| Preparer Fax | 877-917-0448 |
| Prepared Date | 2015-02-25 00:00:00 |
| Authorizer Name | T*** G* N******* |
| Authorizer Telephone | 281-637-6576 |
| Authorizer Title | Dot Compliance Manager |
| Authorizer Email | T*********@s**************.com |
| Narrative | Crude oil leaked from an underground flange connection that was not supported properly after installation in the ditch. The lack of proper support may have been a key contributing factor in the loosening of the flange bolts which ultimately led to the release. During line refill crude oil surfaced at this location and migrated into a drainage ditch that ultimately discharges into hawkins branch creek. Approximately one (1) gallon of crude oil impacted hawkins branch creek. After discovery of the release proper nrc and rrc notifications were made. All free oil was promptly cleaned up from the soil and water surfaces. The flanged connection was excavated, proper supporting fill material was installed in the ditch and the flange was re-torqued. The line was refilled, pressurized and checked for leakage. No further leakage was present and the line was returned to service. |