HL incident on 2014-08-29 — AK

Operator
Bp Pipelines (Alaska), Inc
Cause
Equipment Failure
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$1,000
Incident datetime
2014-08-29 20:45
Report number
Location
AK
Narrative
On august 29, 2014, maintenance of three tk ball valves (xv-1326, xv-1327, xv- 1328) at skid 50 was initiated during a scheduled outage. Unanticipated gouging found on the bonnets of the tk ball valves and the unavailability of spare parts delayed completion of the valve maintenance beyond the amount of time scheduled. While the valve bonnets were being repaired, xv-1326 valve remained open and the single-block isolation remained in place due to the delay in completion of the maintenance work and extension beyond the august 29 dayshift, the skid 50 operator began preparing the skid for hand over to the night shift operator. A portion of this preparation involved re-opening sdv-3415 valve upstream, which had been function-tested earlier in the day, though not as part of the energy isolation procedure. With assistance from an instrument technician, the skid 50 operator opened sdv3415 at 6:02pm; associated pressure trend data shows a drop in the ot18 line at 6:02pm from 43.5 pounds to 7.6 pounds. Approximately 1.5 hours later during a joint walk-down of the isolation by the day and night skid 50 operators, a crude oil leak was discovered from the open top of xv-1326. The operator closed several valves upstream of the isolation but the leak did not immediately stop. After receiving permission from the fs3 otl the skid 50 operator accessed one of the locked out drains and began draining crude to an open-top tank outside of the module. After about five minutes, the leak from xv1326 stopped. Approximately 252 gallons (~6 bbls) of crude oil was recovered from inside module 4955 at skid 50. No injuries occurred during the incident or response, and the release was confined to module 4955 at skid 50.
Detailed record list
Report Received Date
2014-09-25 00:00:00
Iyear
2014
Report Number
20140340
Supplemental Number
20528
Report Type
Supplemental Final
Operator Id
Name
Bp Pipelines (Alaska), Inc
Operator Street Address
3800 Centerpoint Drive Suite 1400
Operator City Name
Anchorage
Operator State Abbreviation
AK
Operator Postal Code
99503
Local Datetime
2014-08-29 19:45:00
Location Latitude
Location Longitude
Commodity Released Type
Crude Oil
Unintentional Release Bbls
6
Recovered Bbls
6
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Local Operating Personnel, Including Contractors
Operator Type
Operator Employee
Incident Identified Datetime
2014-08-29 20:45:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
No
Shutdown Explain
The Pipeline Was Already Down Due To Scheduled Maintenance
On Site Datetime
2014-08-29 20:45:00
Nrc Rpt Datetime
2014-08-30 01:49:00
Nrc Rpt Num
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Automatic
Downstream Valve Type Ind
Automatic
Num Pub Evacuated
0
Pipe Fac Name
Ot28 Skid 50
Segment Name
Ot28
Onshore State Abbreviation
Ak
Onshore Postal Code
99721
Onshore City Name
Prudhoe Bay
Onshore County Name
North Slope Borough
Designated Location
Survey Station No.
Designated Name
Skid 50
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Aboveground
Incident Area Subtype
Typical Aboveground Facility Piping Or Appurtenance
Crossing
No
Pipe Facility Type
Intrastate
Item Involved
Valve
Valve Type
Mainline
Valve Mainline Type
Ball
Valve Manufacturer
Cameron
Installation Year
2009
Manufactured Year
2008
Material Involved
Material Other Than Carbon Steel
Material Details
Stainless Steal
Release Type
Leak
Leak Type
Seal Or Packing
Wildlife Impact Ind
No
Soil Contamination
No
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
Yes
Other Pop Ind
Yes
Other Pop Yes No
Yes
Usa Ecological Ind
Yes
Usa Ecological Yes No
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
600
Est Cost Prop Damage
1000
Est Cost Emergency
5000
Est Cost Environmental
0
Est Cost Other
0
Prpty
6600
Accident Psig
25
Mop Psig
740
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
57
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
< 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
Yes
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
Yes, but the investigation of the control room and/or controller actions has not yet been completed by the operator (supplemental report required)
Employee Drug Test Ind
Yes
Contractor Drug Test Ind
No
Num Employees Tested
1
Num Employees Failed
0
Cause
Equipment Failure
Cause Details
Malfunction Of Control/relief Equipment
Eq Failure Type
Malfunction Of Control/relief Equipment
Block Valve Ind
Yes
Additional Defect Ind
Yes
Preparer Name
S**** F*********
Preparer Title
Dot Compliance Advisor
Preparer Email
F*****@b*.com
Preparer Telephone
281-217-3703
Preparer Fax
630-420-5519
Prepared Date
2015-06-17 00:00:00
Authorizer Name
M****** S******
Authorizer Telephone
630 536 3495
Authorizer Title
Dot Team Leader - Affiliates
Authorizer Email
M**************@b*.com
Narrative
On august 29, 2014, maintenance of three tk ball valves (xv-1326, xv-1327, xv- 1328) at skid 50 was initiated during a scheduled outage. Unanticipated gouging found on the bonnets of the tk ball valves and the unavailability of spare parts delayed completion of the valve maintenance beyond the amount of time scheduled. While the valve bonnets were being repaired, xv-1326 valve remained open and the single-block isolation remained in place due to the delay in completion of the maintenance work and extension beyond the august 29 dayshift, the skid 50 operator began preparing the skid for hand over to the night shift operator. A portion of this preparation involved re-opening sdv-3415 valve upstream, which had been function-tested earlier in the day, though not as part of the energy isolation procedure. With assistance from an instrument technician, the skid 50 operator opened sdv3415 at 6:02pm; associated pressure trend data shows a drop in the ot18 line at 6:02pm from 43.5 pounds to 7.6 pounds. Approximately 1.5 hours later during a joint walk-down of the isolation by the day and night skid 50 operators, a crude oil leak was discovered from the open top of xv-1326. The operator closed several valves upstream of the isolation but the leak did not immediately stop. After receiving permission from the fs3 otl the skid 50 operator accessed one of the locked out drains and began draining crude to an open-top tank outside of the module. After about five minutes, the leak from xv1326 stopped. Approximately 252 gallons (~6 bbls) of crude oil was recovered from inside module 4955 at skid 50. No injuries occurred during the incident or response, and the release was confined to module 4955 at skid 50.
Report Received Date 2014-09-25 00:00:00
Iyear 2014
Report Number 20140340
Supplemental Number 20528
Report Type Supplemental Final
Operator Id 1541 PHMSA Enforcement
Name Bp Pipelines (Alaska), Inc
Operator Street Address 3800 Centerpoint Drive Suite 1400
Operator City Name Anchorage
Operator State Abbreviation AK
Operator Postal Code 99503
Local Datetime 2014-08-29 19:45:00
Location Latitude 70.261265 Google Maps OpenStreetMap
Location Longitude -148.611844 Google Maps OpenStreetMap
Commodity Released Type Crude Oil
Unintentional Release Bbls 6
Recovered Bbls 6
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Local Operating Personnel, Including Contractors
Operator Type Operator Employee
Incident Identified Datetime 2014-08-29 20:45:00
System Part Involved Onshore Pipeline, Including Valve Sites
On Off Shore Onshore
Shutdown Due Accident Ind No
Shutdown Explain The Pipeline Was Already Down Due To Scheduled Maintenance
On Site Datetime 2014-08-29 20:45:00
Nrc Rpt Datetime 2014-08-30 01:49:00
Nrc Rpt Num 1093909 NRC Report How to search
Ignite Ind No
Explode Ind No
Upstream Valve Type Ind Automatic
Downstream Valve Type Ind Automatic
Num Pub Evacuated 0
Pipe Fac Name Ot28 Skid 50
Segment Name Ot28
Onshore State Abbreviation Ak
Onshore Postal Code 99721
Onshore City Name Prudhoe Bay
Onshore County Name North Slope Borough
Designated Location Survey Station No.
Designated Name Skid 50
Federal No
Location Type Totally Contained On Operator-Controlled Property
Incident Area Type Aboveground
Incident Area Subtype Typical Aboveground Facility Piping Or Appurtenance
Crossing No
Pipe Facility Type Intrastate
Item Involved Valve
Valve Type Mainline
Valve Mainline Type Ball
Valve Manufacturer Cameron
Installation Year 2009
Manufactured Year 2008
Material Involved Material Other Than Carbon Steel
Material Details Stainless Steal
Release Type Leak
Leak Type Seal Or Packing
Wildlife Impact Ind No
Soil Contamination No
Long Term Assessment No
Remediation Ind No
Water Contam Ind No
Could Be Hca Yes
Commodity Reached Hca Yes
Other Pop Ind Yes
Other Pop Yes No Yes
Usa Ecological Ind Yes
Usa Ecological Yes No Yes
Est Cost Oper Paid 0
Est Cost Gas Released 600
Est Cost Prop Damage 1000
Est Cost Emergency 5000
Est Cost Environmental 0
Est Cost Other 0
Prpty 6600
Accident Psig 25
Mop Psig 740
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Length Segment Isolated 57
Internal Inspection Ind Yes
Operation Complications Ind No
Pipeline Function < 20% Smys Regulated Transmission
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind No
Scada Conf Ind No
Cpm In Place Ind Yes
Cpm Operating Ind Yes
Cpm Functional Ind Yes
Cpm Detection Ind No
Cpm Conf Ind No
Investigation Status Yes, but the investigation of the control room and/or controller actions has not yet been completed by the operator (supplemental report required)
Employee Drug Test Ind Yes
Contractor Drug Test Ind No
Num Employees Tested 1
Num Employees Failed 0
Cause Equipment Failure
Cause Details Malfunction Of Control/relief Equipment
Eq Failure Type Malfunction Of Control/relief Equipment
Block Valve Ind Yes
Additional Defect Ind Yes
Preparer Name S**** F*********
Preparer Title Dot Compliance Advisor
Preparer Email F*****@b*.com
Preparer Telephone 281-217-3703
Preparer Fax 630-420-5519
Prepared Date 2015-06-17 00:00:00
Authorizer Name M****** S******
Authorizer Telephone 630 536 3495
Authorizer Title Dot Team Leader - Affiliates
Authorizer Email M**************@b*.com
Narrative On august 29, 2014, maintenance of three tk ball valves (xv-1326, xv-1327, xv- 1328) at skid 50 was initiated during a scheduled outage. Unanticipated gouging found on the bonnets of the tk ball valves and the unavailability of spare parts delayed completion of the valve maintenance beyond the amount of time scheduled. While the valve bonnets were being repaired, xv-1326 valve remained open and the single-block isolation remained in place due to the delay in completion of the maintenance work and extension beyond the august 29 dayshift, the skid 50 operator began preparing the skid for hand over to the night shift operator. A portion of this preparation involved re-opening sdv-3415 valve upstream, which had been function-tested earlier in the day, though not as part of the energy isolation procedure. With assistance from an instrument technician, the skid 50 operator opened sdv3415 at 6:02pm; associated pressure trend data shows a drop in the ot18 line at 6:02pm from 43.5 pounds to 7.6 pounds. Approximately 1.5 hours later during a joint walk-down of the isolation by the day and night skid 50 operators, a crude oil leak was discovered from the open top of xv-1326. The operator closed several valves upstream of the isolation but the leak did not immediately stop. After receiving permission from the fs3 otl the skid 50 operator accessed one of the locked out drains and began draining crude to an open-top tank outside of the module. After about five minutes, the leak from xv1326 stopped. Approximately 252 gallons (~6 bbls) of crude oil was recovered from inside module 4955 at skid 50. No injuries occurred during the incident or response, and the release was confined to module 4955 at skid 50.