HL incident on 2014-04-17 — TX

Operator
Enbridge Energy, Limited Partnership
Cause
Equipment Failure
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$10,508
Incident datetime
2014-04-17 00:18
Report number
Location
TX
Narrative
On april 16 at 11:45 pm, the edmonton control center received a gas alarm at the deer river station on line 3. Line 3 was shut down and the technician called out to investigate. Upon arrival at the station at approximately 12:18 am on april 17, the technician confirmed approximately 15 gallons of oil contained in the pump room. Further investigation discovered the seal failed on line 3 unit 1. At approximately 1:18 am two plm employees and a vac truck were en route to the station to assist with clean up. At approximately 2:09 am start up on bypass was initiated. It was discovered that the thrust bearing failed causing the pump shaft to move axially during start up which caused both pump seals to fail allowing product to escape from the system. Both the inboard and outboard seals have been replaced and the unit placed back into service on april 21.
Detailed record list
Report Received Date
2014-05-15 00:00:00
Iyear
2014
Report Number
20140190
Supplemental Number
19390
Report Type
Original Final
Operator Id
Name
Enbridge Energy, Limited Partnership
Operator Street Address
915 N Eldridge Parkway, Suite 1100
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77079
Local Datetime
2014-04-16 23:45:00
Location Latitude
Location Longitude
Commodity Released Type
Crude Oil
Unintentional Release Bbls
0.36
Recovered Bbls
0.36
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Incident Identified Datetime
2014-04-17 00:18:00
System Part Involved
Onshore Pump/meter Station Equipment And Piping
On Off Shore
Onshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2014-04-16 23:45:00
Restart Datetime
2014-04-17 02:09:00
On Site Datetime
2014-04-17 00:18:00
Ignite Ind
No
Explode Ind
No
Num Pub Evacuated
0
Pipe Fac Name
Line 3/dr
Segment Name
Line 3 Unit 1 Seal
Onshore State Abbreviation
Mn
Onshore Postal Code
56636
Onshore City Name
Deer River
Onshore County Name
Itasca
Designated Location
Milepost/valve Station
Designated Name
996.03 Mp
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Aboveground
Pipe Facility Type
Interstate
Item Involved
Pump
Release Type
Leak
Leak Type
Seal Or Packing
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
Yes
Usa Ecological Ind
Yes
Usa Ecological Yes No
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
40
Est Cost Prop Damage
10508
Est Cost Emergency
8495
Est Cost Environmental
0
Est Cost Other
0
Prpty
19043
Pipeline Function
> 20% Smys Regulated Transmission
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Equipment Failure
Cause Details
Pump Or Pump-Related Equipment
Eq Failure Type
Pump Or Pump-Related Equipment
Preparer Name
S**** S****
Preparer Title
Compliance Analyst
Preparer Email
S**********@e*******.com
Preparer Telephone
218-464-5754
Preparer Fax
218-464-5992
Prepared Date
2014-05-15 00:00:00
Authorizer Name
D**** S*******
Authorizer Telephone
218-464-5751
Authorizer Title
Manager Us Pipeline Compliance
Authorizer Email
D*************@e*******.com
Narrative
On april 16 at 11:45 pm, the edmonton control center received a gas alarm at the deer river station on line 3. Line 3 was shut down and the technician called out to investigate. Upon arrival at the station at approximately 12:18 am on april 17, the technician confirmed approximately 15 gallons of oil contained in the pump room. Further investigation discovered the seal failed on line 3 unit 1. At approximately 1:18 am two plm employees and a vac truck were en route to the station to assist with clean up. At approximately 2:09 am start up on bypass was initiated. It was discovered that the thrust bearing failed causing the pump shaft to move axially during start up which caused both pump seals to fail allowing product to escape from the system. Both the inboard and outboard seals have been replaced and the unit placed back into service on april 21.
Report Received Date 2014-05-15 00:00:00
Iyear 2014
Report Number 20140190
Supplemental Number 19390
Report Type Original Final
Operator Id 11169 PHMSA Enforcement
Name Enbridge Energy, Limited Partnership
Operator Street Address 915 N Eldridge Parkway, Suite 1100
Operator City Name Houston
Operator State Abbreviation TX
Operator Postal Code 77079
Local Datetime 2014-04-16 23:45:00
Location Latitude 47.32556 Google Maps OpenStreetMap
Location Longitude -93.76389 Google Maps OpenStreetMap
Commodity Released Type Crude Oil
Unintentional Release Bbls 0.36
Recovered Bbls 0.36
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Incident Identified Datetime 2014-04-17 00:18:00
System Part Involved Onshore Pump/meter Station Equipment And Piping
On Off Shore Onshore
Shutdown Due Accident Ind Yes
Shutdown Datetime 2014-04-16 23:45:00
Restart Datetime 2014-04-17 02:09:00
On Site Datetime 2014-04-17 00:18:00
Ignite Ind No
Explode Ind No
Num Pub Evacuated 0
Pipe Fac Name Line 3/dr
Segment Name Line 3 Unit 1 Seal
Onshore State Abbreviation Mn
Onshore Postal Code 56636
Onshore City Name Deer River
Onshore County Name Itasca
Designated Location Milepost/valve Station
Designated Name 996.03 Mp
Federal No
Location Type Totally Contained On Operator-Controlled Property
Incident Area Type Aboveground
Pipe Facility Type Interstate
Item Involved Pump
Release Type Leak
Leak Type Seal Or Packing
Water Contam Ind No
Could Be Hca Yes
Commodity Reached Hca Yes
Usa Ecological Ind Yes
Usa Ecological Yes No Yes
Est Cost Oper Paid 0
Est Cost Gas Released 40
Est Cost Prop Damage 10508
Est Cost Emergency 8495
Est Cost Environmental 0
Est Cost Other 0
Prpty 19043
Pipeline Function > 20% Smys Regulated Transmission
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Equipment Failure
Cause Details Pump Or Pump-Related Equipment
Eq Failure Type Pump Or Pump-Related Equipment
Preparer Name S**** S****
Preparer Title Compliance Analyst
Preparer Email S**********@e*******.com
Preparer Telephone 218-464-5754
Preparer Fax 218-464-5992
Prepared Date 2014-05-15 00:00:00
Authorizer Name D**** S*******
Authorizer Telephone 218-464-5751
Authorizer Title Manager Us Pipeline Compliance
Authorizer Email D*************@e*******.com
Narrative On april 16 at 11:45 pm, the edmonton control center received a gas alarm at the deer river station on line 3. Line 3 was shut down and the technician called out to investigate. Upon arrival at the station at approximately 12:18 am on april 17, the technician confirmed approximately 15 gallons of oil contained in the pump room. Further investigation discovered the seal failed on line 3 unit 1. At approximately 1:18 am two plm employees and a vac truck were en route to the station to assist with clean up. At approximately 2:09 am start up on bypass was initiated. It was discovered that the thrust bearing failed causing the pump shaft to move axially during start up which caused both pump seals to fail allowing product to escape from the system. Both the inboard and outboard seals have been replaced and the unit placed back into service on april 21.