GTG incident on 2014-11-19 — CA

Operator
Southern California Gas Co
Cause
Excavation Issue
Commodity
Natural Gas
Program
GTG
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$63,821
Incident datetime
2014-11-19 21:02
Report number
Location
CA
Narrative
On november 19, 2014, a third party contractor was operating a ripper at night and struck a 10 inch steel transmission line, resulting in a gas leak. No injuries or further damage resulted from this incident. The incident location is 3,000 feet south of millux rd, bakersfield. The initial incident location reported to DOT was lake road, taft. All repairs to the damaged line were completed and the pipeline was returned to service in approximately 26 hours. Service to affected customers was restored over a period of 2 days. Investigation of the incident showed that the contractor had notified the one-call center and the line had been marked correctly, but the contractor failed to maintain proper clearance by not digging within 25 feet of either side of the line markings as required by agreement.
Detailed record list
Report Received Date
2014-12-17 00:00:00
Iyear
2014
Report Number
20140142
Supplemental Number
16583
Report Type
Original Final
Operator Id
Name
Southern California Gas Co
Operator Street Address
555 West Fifth Street
Operator City Name
Los Angeles
Operator State Abbreviation
CA
Operator Postal Code
90013
Local Datetime
2014-11-19 21:02:00
Location Latitude
Location Longitude
Nrc Rpt Num
Nrc Rpt Datetime
2014-11-19 23:50:00
Commodity Released Type
Natural Gas
Unintentional Release
36589
Intentional Release
140
Accompanying Liquid
0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2014-11-19 22:41:00
Restart Datetime
2014-11-21 00:15:00
Ignite Ind
No
Explode Ind
No
Num Pub Evacuated
0
Incident Identified Datetime
2014-11-19 21:02:00
On Site Datetime
2014-11-19 21:29:00
On Off Shore
Onshore
Onshore State Abbreviation
Ca
Onshore Postal Code
93311
Onshore City Name
Bakersfield
Onshore County Name
Kern
Designated Location
Milepost
Designated Name
0.78
Pipe Fac Name
203
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
48
Crossing
No
Pipe Facility Type
Intrastate
System Part Involved
Onshore Pipeline, Including Valve Sites
Item Involved
Pipe
Pipe Type
Pipe Body
Pipe Diameter
10.75
Pipe Wall Thickness
0.25
Pipe Smys
35000
Pipe Specification
Grade B
Pipe Seam Type
Seamless
Pipe Manufacturer
Youngstown Steel Products Co.
Pipe Coating Type
Coal Tar
Installation Year
1955
Manufactured Year
1955
Material Involved
Carbon Steel
Release Type
Mechanical Puncture
Puncture Axial
10
Puncture Circum
10
Class Location Type
Class 1 Location
Could Be Hca
No
Pir Radius
242
Heat Damage Ind
No
Non Heat Damage Ind
No
Hca Fatalities Ind
No
Est Cost Oper Paid
0
Est Cost Unintentional Release
147512
Est Cost Intentional Release
564
Est Cost Prop Damage
63821
Est Cost Emergency
31000
Est Cost Other
0
Prpty
242897
Accident Psig
640
Mop Psig
771
Mop Cfr Section
Not On Omb-Approved Form When Submitted
Accident Pressure
Pressure Did Not Exceed Maop
Pressure Restriction Ind
No
Upstream Valve Type Ind
Manual
Downstream Valve Type Ind
Manual
Length Segment Isolated
47853
Internal Inspection Ind
No
Unsuitable Mainline Ind
Yes
Other Inspection Ind
Yes
Internal Inspection Details
Non-Hca Pipeline
Operation Complications Ind
No
Pipeline Function
Transmission System
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
Yes
Scada Conf Ind
Yes
Accident Identifier
Controller
Operator Type
Operator Employee
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
The pressure drop was identified by the controller and was confirmed by the field crew as third party damage.
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Excavation Damage
Cause Details
Excavation Damage By Third Party
Ex Party Type
Excavation Damage By Third Party
Prior Notification Ind
Yes
One Call System Ind
Yes
Notify Cga Dirt
No
Private Row Ind
Yes
Private Subtype
Private Landowner
Pipeline Easement Row Ind
Yes
Excavator Type
Farmer
Excavator Equipment
Farm Equipment
Work Performed
Agriculture
One Call Notified Ind
Yes
One Call Ticket Num
478602
One Call Center Name
There Are Two Tickets Associated With This Incident. 478040
Locator Type
Utility Owner
Visible Marks
Yes
Service Interruption
Yes
Service Interruption Hours
25
Root Cause Category
Excavation Issue
Root Cause Type
Excavator Failed To Maintain Clearance After Verifying Marks
Preparer Name
T*** B****
Preparer Title
Pipeline Safety And Compliance Advisor
Preparer Email
T*****@s**************.com
Preparer Telephone
909-376-7208
Preparer Fax
909-885-6270
Authorizer Name
T*** B****
Authorizer Title
Pipeline Safety And Compliance Advisor
Authorizer Telephone
909-376-7208
Authorizer Email
T*****@s**************.com
Narrative
On november 19, 2014, a third party contractor was operating a ripper at night and struck a 10 inch steel transmission line, resulting in a gas leak. No injuries or further damage resulted from this incident. The incident location is 3,000 feet south of millux rd, bakersfield. The initial incident location reported to DOT was lake road, taft. All repairs to the damaged line were completed and the pipeline was returned to service in approximately 26 hours. Service to affected customers was restored over a period of 2 days. Investigation of the incident showed that the contractor had notified the one-call center and the line had been marked correctly, but the contractor failed to maintain proper clearance by not digging within 25 feet of either side of the line markings as required by agreement.
Report Received Date 2014-12-17 00:00:00
Iyear 2014
Report Number 20140142
Supplemental Number 16583
Report Type Original Final
Operator Id 18484 PHMSA Enforcement
Name Southern California Gas Co
Operator Street Address 555 West Fifth Street
Operator City Name Los Angeles
Operator State Abbreviation CA
Operator Postal Code 90013
Local Datetime 2014-11-19 21:02:00
Location Latitude 35.1694 Google Maps OpenStreetMap
Location Longitude -119.17974 Google Maps OpenStreetMap
Nrc Rpt Num 1101516 NRC Report How to search
Nrc Rpt Datetime 2014-11-19 23:50:00
Commodity Released Type Natural Gas
Unintentional Release 36589
Intentional Release 140
Accompanying Liquid 0
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Shutdown Due Accident Ind Yes
Shutdown Datetime 2014-11-19 22:41:00
Restart Datetime 2014-11-21 00:15:00
Ignite Ind No
Explode Ind No
Num Pub Evacuated 0
Incident Identified Datetime 2014-11-19 21:02:00
On Site Datetime 2014-11-19 21:29:00
On Off Shore Onshore
Onshore State Abbreviation Ca
Onshore Postal Code 93311
Onshore City Name Bakersfield
Onshore County Name Kern
Designated Location Milepost
Designated Name 0.78
Pipe Fac Name 203
Federal No
Location Type Pipeline Right-Of-Way
Incident Area Type Underground
Incident Area Subtype Under Soil
Depth Of Cover 48
Crossing No
Pipe Facility Type Intrastate
System Part Involved Onshore Pipeline, Including Valve Sites
Item Involved Pipe
Pipe Type Pipe Body
Pipe Diameter 10.75
Pipe Wall Thickness 0.25
Pipe Smys 35000
Pipe Specification Grade B
Pipe Seam Type Seamless
Pipe Manufacturer Youngstown Steel Products Co.
Pipe Coating Type Coal Tar
Installation Year 1955
Manufactured Year 1955
Material Involved Carbon Steel
Release Type Mechanical Puncture
Puncture Axial 10
Puncture Circum 10
Class Location Type Class 1 Location
Could Be Hca No
Pir Radius 242
Heat Damage Ind No
Non Heat Damage Ind No
Hca Fatalities Ind No
Est Cost Oper Paid 0
Est Cost Unintentional Release 147512
Est Cost Intentional Release 564
Est Cost Prop Damage 63821
Est Cost Emergency 31000
Est Cost Other 0
Prpty 242897
Accident Psig 640
Mop Psig 771
Mop Cfr Section Not On Omb-Approved Form When Submitted View CFR 49 §192
Accident Pressure Pressure Did Not Exceed Maop
Pressure Restriction Ind No
Upstream Valve Type Ind Manual
Downstream Valve Type Ind Manual
Length Segment Isolated 47853
Internal Inspection Ind No
Unsuitable Mainline Ind Yes
Other Inspection Ind Yes
Internal Inspection Details Non-Hca Pipeline
Operation Complications Ind No
Pipeline Function Transmission System
Scada In Place Ind Yes
Scada Operating Ind Yes
Scada Functional Ind Yes
Scada Detection Ind Yes
Scada Conf Ind Yes
Accident Identifier Controller
Operator Type Operator Employee
Investigation Status No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details The pressure drop was identified by the controller and was confirmed by the field crew as third party damage.
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Excavation Damage
Cause Details Excavation Damage By Third Party
Ex Party Type Excavation Damage By Third Party
Prior Notification Ind Yes
One Call System Ind Yes
Notify Cga Dirt No
Private Row Ind Yes
Private Subtype Private Landowner
Pipeline Easement Row Ind Yes
Excavator Type Farmer
Excavator Equipment Farm Equipment
Work Performed Agriculture
One Call Notified Ind Yes
One Call Ticket Num 478602
One Call Center Name There Are Two Tickets Associated With This Incident. 478040
Locator Type Utility Owner
Visible Marks Yes
Service Interruption Yes
Service Interruption Hours 25
Root Cause Category Excavation Issue
Root Cause Type Excavator Failed To Maintain Clearance After Verifying Marks
Preparer Name T*** B****
Preparer Title Pipeline Safety And Compliance Advisor
Preparer Email T*****@s**************.com
Preparer Telephone 909-376-7208
Preparer Fax 909-885-6270
Authorizer Name T*** B****
Authorizer Title Pipeline Safety And Compliance Advisor
Authorizer Telephone 909-376-7208
Authorizer Email T*****@s**************.com
Narrative On november 19, 2014, a third party contractor was operating a ripper at night and struck a 10 inch steel transmission line, resulting in a gas leak. No injuries or further damage resulted from this incident. The incident location is 3,000 feet south of millux rd, bakersfield. The initial incident location reported to DOT was lake road, taft. All repairs to the damaged line were completed and the pipeline was returned to service in approximately 26 hours. Service to affected customers was restored over a period of 2 days. Investigation of the incident showed that the contractor had notified the one-call center and the line had been marked correctly, but the contractor failed to maintain proper clearance by not digging within 25 feet of either side of the line markings as required by agreement.