GD incident on 2014-10-01 — OH

Operator
Dominion East Ohio
Cause
Corrosion Failure
Commodity
Natural Gas
Program
GD
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$84,000
Incident datetime
2014-10-01 21:26
Report number
Location
OH, STARK
Narrative
On october 1, 2014 a 30" distribution main leaked resulting in a reportable incident. At approximately 9:26 p.M. On 10/1/2014, dominion east ohio received an odor complaint at 7373 sherman church rd. A technician was immediately dispatched to the area. At 9:48 p.M. The technician arrived on site, conducted a leak survey of the area and concluded that gas was not migrating and according to available data did not believe the leak to be on a dominion facility. The technician notified the fire chief of his findings. At approximately 11:55 p.M. Dominion was notified by the epa that oil was bubbling up from the ground and that they were picking up high natural gas readings. Another technician was immediately dispatched to the scene, arrived at 12:47 a.M. On 10/2/2014, and upon investigation determined that deo's 30" distribution line was leaking and called in for a construction crew. The technician continued to leak survey throughout the night. As additional dominion personnel arrived on site, the investigation continued and determined that the line was deeper than a dominion crew could handle, therefore a contracting crew was mobilized. At approximately 5:00 a.M. Dominion's environmental contractors arrived on site and began environmental cleanup activities. The area was evacuated at approximately 6:00 a.M. As measure of safety, before excavating could occur dominion decided to lower the pressure in the pipeline. At approximately 10:00 am the pressure was lowered from 155 psig to 60 psig. Once the pressure was stabilized dominion began excavating. At approximately 5:00 p.M. A clamp was installed and pressure restored. The section of pipe that leaked was cut out and sent to kiefner & associates for a 3rd party failure analysis. The results of the test concluded that the cause of the leak was a through-wall internal corrosion pit at the 6 o'clock position. Test results suggest that microbial-induced corrosion (mic) played a role in the pitting corrosion. Dominion replaced approximately 800 feet of the 30" high pressure distribution line that leaked and will replace additional portions of adjacent pipelines throughout 2015.
Detailed record list
Occurred At
2014-10-01 21:26:00
Year
2014
Report Received Date
2014-10-31 00:00:00
Iyear
2014.0
Report Number
20140093.0
Supplemental Number
16031.0
Report Type
Supplemental Final
Operator Id
Name
Dominion East Ohio
Operator Street Address
1201 East 55th Street
Operator City Name
Cleveland
Operator State Abbreviation
OH
Operator Postal Code
44103
Local Datetime
2014-10-01 21:26:00
Location Street Address
7373 Sherman Church Rd
Location City Name
East Sparta
Location County Name
Stark
Location State Abbreviation
OH
Location Postal Code
44626
Location Latitude
Location Longitude
-81.43497065
Nrc Rpt Datetime
2014-10-02 06:15:00
Nrc Rpt Num
Commodity Released Type
Natural Gas
Unintentional Release
75.0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Ignite Ind
No
Explode Ind
No
Num Pub Evacuated
170.0
Incident Identified Datetime
2014-10-01 21:26:00
On Site Datetime
2014-10-01 21:48:00
Federal
No
Location Type
Private Property
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
144.0
Crossing
No
Pipe Facility Type
Privately Owned
System Part Involved
Main
Installation Year
1972.0
Pipe Diameter
30.0
Pipe Specification
Api 5l
Pipe Manufacturer
U.s. Steel
Material Involved
Steel
Steel Seam Type
Other
Steel Seam Type Details
Double Submerged Arc Welded
Wt Steel
0.298
Release Type
Leak
Leak Type
Pinhole
Class Location Type
Class 3 Location
Est Cost Oper Paid
1500.0
Est Cost Prop Damage
84000.0
Est Cost Emergency
5000.0
Est Cost Other
700000.0
Est Cost Other Details
Cost Of Pipeline Replacement
Est Cost Unintentional Release
375.0
Prpty
790875.0
Commercial Affected
0.0
Industrial Affected
0.0
Residences Affected
0.0
Accident Psig
155.0
Normal Psig
155.0
Mop Psig
174.0
Accident Pressure
Pressure Did Not Exceed Maop
Scada In Place Ind
No
Accident Identifier
Notification From Emergency Responder
Investigation Status
Yes, specify investigation result(s): (select all that apply)
Invest Schedule Ind
Yes
Invest No Control Room Ind
Yes
Invest No Controller Ind
Yes
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Corrosion Failure
Cause Details
Internal Corrosion
Internal External
Internal Corrosion
Int Visual Exam Results
Localized Pitting
Int Microbiological Ind
Yes
Int Metallurgical Basis Ind
Yes
Int Low Point Pipe Loc Ind
Yes
Corrosion Inhibitors
No
Liquid Found
Yes
Cor Hydrotest Leak Survey Date
2014-02-04 00:00:00
Cor Hydrotest Conducted Ind
No
Preparer Name
A**** M****
Preparer Title
Technical Specialist
Preparer Email
A************@d**.com
Preparer Telephone
3304589186
Preparer Fax
3304783760
Authorizer Name
A**** M****
Authorizer Title
Technical Specialist
Authorizer Telephone
3304589186
Authorizer Email
A************@d**.com
Narrative
On october 1, 2014 a 30" distribution main leaked resulting in a reportable incident. At approximately 9:26 p.M. On 10/1/2014, dominion east ohio received an odor complaint at 7373 sherman church rd. A technician was immediately dispatched to the area. At 9:48 p.M. The technician arrived on site, conducted a leak survey of the area and concluded that gas was not migrating and according to available data did not believe the leak to be on a dominion facility. The technician notified the fire chief of his findings. At approximately 11:55 p.M. Dominion was notified by the epa that oil was bubbling up from the ground and that they were picking up high natural gas readings. Another technician was immediately dispatched to the scene, arrived at 12:47 a.M. On 10/2/2014, and upon investigation determined that deo's 30" distribution line was leaking and called in for a construction crew. The technician continued to leak survey throughout the night. As additional dominion personnel arrived on site, the investigation continued and determined that the line was deeper than a dominion crew could handle, therefore a contracting crew was mobilized. At approximately 5:00 a.M. Dominion's environmental contractors arrived on site and began environmental cleanup activities. The area was evacuated at approximately 6:00 a.M. As measure of safety, before excavating could occur dominion decided to lower the pressure in the pipeline. At approximately 10:00 am the pressure was lowered from 155 psig to 60 psig. Once the pressure was stabilized dominion began excavating. At approximately 5:00 p.M. A clamp was installed and pressure restored. The section of pipe that leaked was cut out and sent to kiefner & associates for a 3rd party failure analysis. The results of the test concluded that the cause of the leak was a through-wall internal corrosion pit at the 6 o'clock position. Test results suggest that microbial-induced corrosion (mic) played a role in the pitting corrosion. Dominion replaced approximately 800 feet of the 30" high pressure distribution line that leaked and will replace additional portions of adjacent pipelines throughout 2015.
Occurred At 2014-10-01 21:26:00
Year 2014
Report Received Date 2014-10-31 00:00:00
Iyear 2014.0
Report Number 20140093.0
Supplemental Number 16031.0
Report Type Supplemental Final
Operator Id 4060 PHMSA Enforcement
Name Dominion East Ohio
Operator Street Address 1201 East 55th Street
Operator City Name Cleveland
Operator State Abbreviation OH
Operator Postal Code 44103
Local Datetime 2014-10-01 21:26:00
Location Street Address 7373 Sherman Church Rd
Location City Name East Sparta
Location County Name Stark
Location State Abbreviation OH
Location Postal Code 44626
Location Latitude 40.70302259 Google Maps OpenStreetMap
Location Longitude -81.43497065 Google Maps OpenStreetMap
Nrc Rpt Datetime 2014-10-02 06:15:00
Nrc Rpt Num 1097118 NRC Report How to search
Commodity Released Type Natural Gas
Unintentional Release 75.0
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Ignite Ind No
Explode Ind No
Num Pub Evacuated 170.0
Incident Identified Datetime 2014-10-01 21:26:00
On Site Datetime 2014-10-01 21:48:00
Federal No
Location Type Private Property
Incident Area Type Underground
Incident Area Subtype Under Soil
Depth Of Cover 144.0
Crossing No
Pipe Facility Type Privately Owned
System Part Involved Main
Installation Year 1972.0
Pipe Diameter 30.0
Pipe Specification Api 5l
Pipe Manufacturer U.s. Steel
Material Involved Steel
Steel Seam Type Other
Steel Seam Type Details Double Submerged Arc Welded
Wt Steel 0.298
Release Type Leak
Leak Type Pinhole
Class Location Type Class 3 Location
Est Cost Oper Paid 1500.0
Est Cost Prop Damage 84000.0
Est Cost Emergency 5000.0
Est Cost Other 700000.0
Est Cost Other Details Cost Of Pipeline Replacement
Est Cost Unintentional Release 375.0
Prpty 790875.0
Commercial Affected 0.0
Industrial Affected 0.0
Residences Affected 0.0
Accident Psig 155.0
Normal Psig 155.0
Mop Psig 174.0
Accident Pressure Pressure Did Not Exceed Maop
Scada In Place Ind No
Accident Identifier Notification From Emergency Responder
Investigation Status Yes, specify investigation result(s): (select all that apply)
Invest Schedule Ind Yes
Invest No Control Room Ind Yes
Invest No Controller Ind Yes
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Corrosion Failure
Cause Details Internal Corrosion
Internal External Internal Corrosion
Int Visual Exam Results Localized Pitting
Int Microbiological Ind Yes
Int Metallurgical Basis Ind Yes
Int Low Point Pipe Loc Ind Yes
Corrosion Inhibitors No
Liquid Found Yes
Cor Hydrotest Leak Survey Date 2014-02-04 00:00:00
Cor Hydrotest Conducted Ind No
Preparer Name A**** M****
Preparer Title Technical Specialist
Preparer Email A************@d**.com
Preparer Telephone 3304589186
Preparer Fax 3304783760
Authorizer Name A**** M****
Authorizer Title Technical Specialist
Authorizer Telephone 3304589186
Authorizer Email A************@d**.com
Narrative On october 1, 2014 a 30" distribution main leaked resulting in a reportable incident. At approximately 9:26 p.M. On 10/1/2014, dominion east ohio received an odor complaint at 7373 sherman church rd. A technician was immediately dispatched to the area. At 9:48 p.M. The technician arrived on site, conducted a leak survey of the area and concluded that gas was not migrating and according to available data did not believe the leak to be on a dominion facility. The technician notified the fire chief of his findings. At approximately 11:55 p.M. Dominion was notified by the epa that oil was bubbling up from the ground and that they were picking up high natural gas readings. Another technician was immediately dispatched to the scene, arrived at 12:47 a.M. On 10/2/2014, and upon investigation determined that deo's 30" distribution line was leaking and called in for a construction crew. The technician continued to leak survey throughout the night. As additional dominion personnel arrived on site, the investigation continued and determined that the line was deeper than a dominion crew could handle, therefore a contracting crew was mobilized. At approximately 5:00 a.M. Dominion's environmental contractors arrived on site and began environmental cleanup activities. The area was evacuated at approximately 6:00 a.M. As measure of safety, before excavating could occur dominion decided to lower the pressure in the pipeline. At approximately 10:00 am the pressure was lowered from 155 psig to 60 psig. Once the pressure was stabilized dominion began excavating. At approximately 5:00 p.M. A clamp was installed and pressure restored. The section of pipe that leaked was cut out and sent to kiefner & associates for a 3rd party failure analysis. The results of the test concluded that the cause of the leak was a through-wall internal corrosion pit at the 6 o'clock position. Test results suggest that microbial-induced corrosion (mic) played a role in the pitting corrosion. Dominion replaced approximately 800 feet of the 30" high pressure distribution line that leaked and will replace additional portions of adjacent pipelines throughout 2015.

All rights reserved. Copyright © by ClearPHMSA