Incident details
Operator, cause, commodity and consequences with raw source fields.
GD incident on 2014-08-25 — AR
Operator
Centerpoint Energy Resources Corp.
Cause
Locating Issue
Commodity
Natural Gas
Program
GD
Damage and Injuries
0 fatalities
1 injury
Property damage (nominal)
$100
Incident datetime
2014-08-25 10:39
Report number
Location
AR, PULASKI
Narrative
J.F. Construction, a contractor working for centerpoint energy, was in the process of replacing an existing 3/4" steel service line to an inactive account at 37 knight drive, north little rock, ar. A locate was requested from the arkansas one call center to located all facilities; however the contractor was responsible for locating the centerpoint energy facilities. Employees of j.F construction used a pipe locator to verify the location of the existing service, found it to not be in conflict with their planned work, but did not completely mark the remainder of the service line. Due to the large trees on the property, the original service line installation did not take a perpendicular path from the main. A pneumatic boring tool was placed in a bell hole for the purpose of installing a new service. After boring for about 20 minutes, the tool struck what was determined to be the existing service line. The impact from the boring tool bent the 3/4' steel service line at the impact point, causing a partial separation of the pipe at a threaded coupling six feet east of the mobile home and another leak of undetermined nature under the mobile home. Approximately 10 minutes after the leak began, a small explosion took place and the resulting flash caused second-degree burns to the resident inside the mobile home. Hydraulic squeeze tools were used to stop the flow of gas and to retire/abandon the service line. The pipeline facility (service line) remains shut down. However, installation of a new service is not anticipated. Therefore, we are not planning to file a supplemental report. Centerpoint energy does not anticipate any additional costs from this incident. We anticipate all associated costs to be borne by the contractor. Also, since we have no access to property damage or medical claim information, we are estimating these to be $50,000.
Detailed record list
Occurred At
2014-08-25 10:39:00
Year
2014
Report Received Date
2014-09-22 00:00:00
Iyear
2014.0
Report Number
20140081.0
Supplemental Number
15930.0
Report Type
Original Final
Operator Id
Name
Centerpoint Energy Resources Corp.
Operator Street Address
401 W. Capitol, Suite 600
Operator City Name
Little Rock
Operator State Abbreviation
AR
Operator Postal Code
72201
Local Datetime
2014-08-25 10:35:00
Location Street Address
37 Knight Dr
Location City Name
North Little Rock
Location County Name
Pulaski
Location State Abbreviation
AR
Location Postal Code
72117
Location Latitude
34.76994416
Location Longitude
-92.26350222
Nrc Rpt Datetime
2014-08-25 11:58:00
Nrc Rpt Num
1093370
Commodity Released Type
Natural Gas
Unintentional Release
1.0
Fatality Ind
No
Fatal
0
Injury Ind
Yes
Num Emp Injuries
0
Num Contr Injuries
0
Num Er Injuries
0
Num Worker Injuries
0
Num Gp Injuries
1
Injure
1
Ignite Ind
Yes
Explode Ind
Yes
Num Pub Evacuated
1.0
Incident Identified Datetime
2014-08-25 10:39:00
On Site Datetime
2014-08-25 10:42:00
Federal
No
Location Type
Private Property
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
24.0
Crossing
No
Pipe Facility Type
Other
Pipe Type Other
Publically Owned Ldc
System Part Involved
Service
Pipe Diameter
0.75
Pipe Specification
Unknown
Pipe Manufacturer
Unknown
Material Involved
Steel
Steel Seam Type
Other
Steel Seam Type Details
Unknown
Release Type
Leak
Leak Type
Connection Failure
Class Location Type
Class 3 Location
Est Cost Oper Paid
50000.0
Est Cost Prop Damage
100.0
Est Cost Emergency
500.0
Est Cost Other
0.0
Est Cost Other Details
None Anticipated-See Remarks In Narrative
Est Cost Unintentional Release
12.0
Prpty
50612.0
Commercial Affected
0.0
Industrial Affected
0.0
Residences Affected
0.0
Accident Psig
10.0
Normal Psig
10.0
Mop Psig
20.0
Accident Pressure
Pressure Did Not Exceed Maop
Scada In Place Ind
No
Accident Identifier
Notification From Emergency Responder
Investigation Status
No, the facility was not monitored by a controller(s) at the time of the incident
Employee Drug Test Ind
No
Contractor Drug Test Ind
Yes
Num Contractors Tested
4
Num Contractors Failed
0
Cause
Excavation Damage
Cause Details
Excavation Damage By Operator's Contractor (Second Party)
Ex Party Type
Excavation Damage By Operator's Contractor (Second Party)
Notify Cga Dirt
No
Private Row Ind
Yes
Private Subtype
Private Landowner
Excavator Type
Contractor
Excavator Equipment
Boring
Work Performed
Natural Gas
One Call Notified Ind
Yes
One Call Ticket Num
1408120262
Locator Type
Contract Locator
Visible Marks
No
Service Interruption
No
Root Cause Category
Locating Issue
Root Cause Type
Facility Not Marked Due To Locator Error
Preparer Name
J** R****
Preparer Title
District Operations Manager
Preparer Email
J********@c****************.com
Preparer Telephone
501-377-4980
Preparer Fax
501-377-4721
Authorizer Name
K**** K********
Authorizer Title
Regional Operations Director
Authorizer Telephone
501-377-4669
Authorizer Email
K**************@c****************.com
Narrative
J.F. Construction, a contractor working for centerpoint energy, was in the process of replacing an existing 3/4" steel service line to an inactive account at 37 knight drive, north little rock, ar. A locate was requested from the arkansas one call center to located all facilities; however the contractor was responsible for locating the centerpoint energy facilities. Employees of j.F construction used a pipe locator to verify the location of the existing service, found it to not be in conflict with their planned work, but did not completely mark the remainder of the service line. Due to the large trees on the property, the original service line installation did not take a perpendicular path from the main. A pneumatic boring tool was placed in a bell hole for the purpose of installing a new service. After boring for about 20 minutes, the tool struck what was determined to be the existing service line. The impact from the boring tool bent the 3/4' steel service line at the impact point, causing a partial separation of the pipe at a threaded coupling six feet east of the mobile home and another leak of undetermined nature under the mobile home. Approximately 10 minutes after the leak began, a small explosion took place and the resulting flash caused second-degree burns to the resident inside the mobile home. Hydraulic squeeze tools were used to stop the flow of gas and to retire/abandon the service line. The pipeline facility (service line) remains shut down. However, installation of a new service is not anticipated. Therefore, we are not planning to file a supplemental report. Centerpoint energy does not anticipate any additional costs from this incident. We anticipate all associated costs to be borne by the contractor. Also, since we have no access to property damage or medical claim information, we are estimating these to be $50,000.
| Occurred At | 2014-08-25 10:39:00 |
|---|---|
| Year | 2014 |
| Report Received Date | 2014-09-22 00:00:00 |
| Iyear | 2014.0 |
| Report Number | 20140081.0 |
| Supplemental Number | 15930.0 |
| Report Type | Original Final |
| Operator Id | 603 PHMSA Enforcement |
| Name | Centerpoint Energy Resources Corp. |
| Operator Street Address | 401 W. Capitol, Suite 600 |
| Operator City Name | Little Rock |
| Operator State Abbreviation | AR |
| Operator Postal Code | 72201 |
| Local Datetime | 2014-08-25 10:35:00 |
| Location Street Address | 37 Knight Dr |
| Location City Name | North Little Rock |
| Location County Name | Pulaski |
| Location State Abbreviation | AR |
| Location Postal Code | 72117 |
| Location Latitude | 34.76994416 Google Maps OpenStreetMap |
| Location Longitude | -92.26350222 Google Maps OpenStreetMap |
| Nrc Rpt Datetime | 2014-08-25 11:58:00 |
| Nrc Rpt Num | 1093370 NRC Report How to search |
| Commodity Released Type | Natural Gas |
| Unintentional Release | 1.0 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | Yes |
| Num Emp Injuries | 0 |
| Num Contr Injuries | 0 |
| Num Er Injuries | 0 |
| Num Worker Injuries | 0 |
| Num Gp Injuries | 1 |
| Injure | 1 |
| Ignite Ind | Yes |
| Explode Ind | Yes |
| Num Pub Evacuated | 1.0 |
| Incident Identified Datetime | 2014-08-25 10:39:00 |
| On Site Datetime | 2014-08-25 10:42:00 |
| Federal | No |
| Location Type | Private Property |
| Incident Area Type | Underground |
| Incident Area Subtype | Under Soil |
| Depth Of Cover | 24.0 |
| Crossing | No |
| Pipe Facility Type | Other |
| Pipe Type Other | Publically Owned Ldc |
| System Part Involved | Service |
| Pipe Diameter | 0.75 |
| Pipe Specification | Unknown |
| Pipe Manufacturer | Unknown |
| Material Involved | Steel |
| Steel Seam Type | Other |
| Steel Seam Type Details | Unknown |
| Release Type | Leak |
| Leak Type | Connection Failure |
| Class Location Type | Class 3 Location |
| Est Cost Oper Paid | 50000.0 |
| Est Cost Prop Damage | 100.0 |
| Est Cost Emergency | 500.0 |
| Est Cost Other | 0.0 |
| Est Cost Other Details | None Anticipated-See Remarks In Narrative |
| Est Cost Unintentional Release | 12.0 |
| Prpty | 50612.0 |
| Commercial Affected | 0.0 |
| Industrial Affected | 0.0 |
| Residences Affected | 0.0 |
| Accident Psig | 10.0 |
| Normal Psig | 10.0 |
| Mop Psig | 20.0 |
| Accident Pressure | Pressure Did Not Exceed Maop |
| Scada In Place Ind | No |
| Accident Identifier | Notification From Emergency Responder |
| Investigation Status | No, the facility was not monitored by a controller(s) at the time of the incident |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | Yes |
| Num Contractors Tested | 4 |
| Num Contractors Failed | 0 |
| Cause | Excavation Damage |
| Cause Details | Excavation Damage By Operator's Contractor (Second Party) |
| Ex Party Type | Excavation Damage By Operator's Contractor (Second Party) |
| Notify Cga Dirt | No |
| Private Row Ind | Yes |
| Private Subtype | Private Landowner |
| Excavator Type | Contractor |
| Excavator Equipment | Boring |
| Work Performed | Natural Gas |
| One Call Notified Ind | Yes |
| One Call Ticket Num | 1408120262 |
| Locator Type | Contract Locator |
| Visible Marks | No |
| Service Interruption | No |
| Root Cause Category | Locating Issue |
| Root Cause Type | Facility Not Marked Due To Locator Error |
| Preparer Name | J** R**** |
| Preparer Title | District Operations Manager |
| Preparer Email | J********@c****************.com |
| Preparer Telephone | 501-377-4980 |
| Preparer Fax | 501-377-4721 |
| Authorizer Name | K**** K******** |
| Authorizer Title | Regional Operations Director |
| Authorizer Telephone | 501-377-4669 |
| Authorizer Email | K**************@c****************.com |
| Narrative | J.F. Construction, a contractor working for centerpoint energy, was in the process of replacing an existing 3/4" steel service line to an inactive account at 37 knight drive, north little rock, ar. A locate was requested from the arkansas one call center to located all facilities; however the contractor was responsible for locating the centerpoint energy facilities. Employees of j.F construction used a pipe locator to verify the location of the existing service, found it to not be in conflict with their planned work, but did not completely mark the remainder of the service line. Due to the large trees on the property, the original service line installation did not take a perpendicular path from the main. A pneumatic boring tool was placed in a bell hole for the purpose of installing a new service. After boring for about 20 minutes, the tool struck what was determined to be the existing service line. The impact from the boring tool bent the 3/4' steel service line at the impact point, causing a partial separation of the pipe at a threaded coupling six feet east of the mobile home and another leak of undetermined nature under the mobile home. Approximately 10 minutes after the leak began, a small explosion took place and the resulting flash caused second-degree burns to the resident inside the mobile home. Hydraulic squeeze tools were used to stop the flow of gas and to retire/abandon the service line. The pipeline facility (service line) remains shut down. However, installation of a new service is not anticipated. Therefore, we are not planning to file a supplemental report. Centerpoint energy does not anticipate any additional costs from this incident. We anticipate all associated costs to be borne by the contractor. Also, since we have no access to property damage or medical claim information, we are estimating these to be $50,000. |