HL incident on 2013-11-25 — TX

Operator
Enterprise Crude Pipeline Llc
Cause
Corrosion Failure
Commodity
Crude Oil
Program
HL
Damage and Injuries
0 fatalities 0 injuries
Property damage (nominal)
$20,000
Incident datetime
2013-11-25 15:30
Report number
Location
TX
Narrative
Third party notified enterprise local operations of a leak on the c150 regulated gathering line. Approximately 20 bbls of crude oil was released on to the ground with 2 bbls entering a dry creek bed with no water impact discovered. A temporary clamp was placed on the line for overnight. The line was replaced the next day and put back into service. The replaced line was sent for metallurgical analysis. Remediation and repairs were completed. Metallurgical report confirmed that external corrosion and microbiological- assisted corrosion contributed to wall loss and eventually a leak in the pipe. The line is being purged and capped and placed in an idled operating status. Future intent is to abandon the line.
Detailed record list
Report Received Date
2013-12-19 00:00:00
Iyear
2013
Report Number
20130401
Supplemental Number
19717
Report Type
Supplemental Final
Operator Id
Name
Enterprise Crude Pipeline Llc
Operator Street Address
1100 Louisiana Street
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2013-11-25 15:30:00
Location Latitude
Location Longitude
Commodity Released Type
Crude Oil
Unintentional Release Bbls
20
Recovered Bbls
20
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Notification From Public
Incident Identified Datetime
2013-11-25 15:30:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
No
Shutdown Explain
Not Flowing At The Time.
On Site Datetime
2013-11-25 15:45:00
Nrc Rpt Datetime
2013-11-25 20:23:00
Nrc Rpt Num
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Manual
Downstream Valve Type Ind
Manual
Num Pub Evacuated
0
Pipe Fac Name
C150 Gathering Line
Segment Name
C150
Onshore State Abbreviation
Ok
Onshore Postal Code
73438
Onshore City Name
Healdton
Onshore County Name
Carter
Designated Location
Milepost/valve Station
Federal
No
Location Type
Originated On Operator-Controlled Property, But Then Flowed Or Migrated Off The Property
Incident Area Type
Aboveground
Incident Area Subtype
Other
Incident Area Details
Gathering Line Above Ground Piping
Crossing
No
Pipe Facility Type
Intrastate
Item Involved
Pipe
Pipe Type
Pipe Body
Pipe Diameter
6
Pipe Wall Thickness
0.28
Pipe Smys
24000
Pipe Specification
Api 5l
Pipe Seam Type
Lap Welded
Pipe Manufacturer
Unknown
Pipe Coating Type
Coal Tar
Installation Year
1950
Manufactured Year
1950
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Pinhole
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
Yes
Soil Remed Ind
Yes
Water Contam Ind
No
Could Be Hca
Yes
Commodity Reached Hca
Yes
Other Pop Ind
Yes
Est Cost Oper Paid
0
Est Cost Gas Released
2000
Est Cost Prop Damage
20000
Est Cost Emergency
5000
Est Cost Environmental
15000
Est Cost Other
25000
Est Cost Other Details
Metallurgical Analysis Costs
Prpty
67000
Accident Psig
50
Mop Psig
100
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
8000
Internal Inspection Ind
No
Diameter Change Ind
Yes
Other Restrictions Ind
Yes
Operation Complications Ind
Yes
Low Flow Ind
Yes
Pipeline Function
=< 20% Smys Regulated Gathering
Scada In Place Ind
No
Cpm In Place Ind
No
Investigation Status
No, the facility was not monitored by a controller(s) at the time of the accident
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Corrosion Failure
Cause Details
External Corrosion
Internal External
External Corrosion
Visual Exam Results
General Corrosion
Atmosphere Corrosion Ind
Yes
Microbiological Corrosion Ind
Yes
Metallurgical Basis Ind
Yes
Underground Location
No
Externally Coated
Yes
Prior Damage
Yes
Collected Data Ind
No
Has Hydrtst Conduc Before Ind
Yes
Hydrtst Most Rcnt Year
2012
Hydrtst Most Rcnt Pressure
120
Direct Asmnt Conducted
No
Non Destructive Exam Ind
No
Preparer Name
S**** D****
Preparer Title
Senior Pipeline Compliance Engineer
Preparer Email
S******@e****.com
Preparer Telephone
713.381.6487
Prepared Date
2014-07-02 00:00:00
Authorizer Name
S**** D****
Authorizer Telephone
713-381-6487
Authorizer Title
Senior Pipeline Compliance Engineer
Authorizer Email
S******@e****.com
Narrative
Third party notified enterprise local operations of a leak on the c150 regulated gathering line. Approximately 20 bbls of crude oil was released on to the ground with 2 bbls entering a dry creek bed with no water impact discovered. A temporary clamp was placed on the line for overnight. The line was replaced the next day and put back into service. The replaced line was sent for metallurgical analysis. Remediation and repairs were completed. Metallurgical report confirmed that external corrosion and microbiological- assisted corrosion contributed to wall loss and eventually a leak in the pipe. The line is being purged and capped and placed in an idled operating status. Future intent is to abandon the line.
Report Received Date 2013-12-19 00:00:00
Iyear 2013
Report Number 20130401
Supplemental Number 19717
Report Type Supplemental Final
Operator Id 30829 PHMSA Enforcement
Name Enterprise Crude Pipeline Llc
Operator Street Address 1100 Louisiana Street
Operator City Name Houston
Operator State Abbreviation TX
Operator Postal Code 77002
Local Datetime 2013-11-25 15:30:00
Location Latitude 34.2391 Google Maps OpenStreetMap
Location Longitude -97.5136 Google Maps OpenStreetMap
Commodity Released Type Crude Oil
Unintentional Release Bbls 20
Recovered Bbls 20
Fatality Ind No
Fatal 0
Injury Ind No
Injure 0
Accident Identifier Notification From Public
Incident Identified Datetime 2013-11-25 15:30:00
System Part Involved Onshore Pipeline, Including Valve Sites
On Off Shore Onshore
Shutdown Due Accident Ind No
Shutdown Explain Not Flowing At The Time.
On Site Datetime 2013-11-25 15:45:00
Nrc Rpt Datetime 2013-11-25 20:23:00
Nrc Rpt Num 1066843 NRC Report How to search
Ignite Ind No
Explode Ind No
Upstream Valve Type Ind Manual
Downstream Valve Type Ind Manual
Num Pub Evacuated 0
Pipe Fac Name C150 Gathering Line
Segment Name C150
Onshore State Abbreviation Ok
Onshore Postal Code 73438
Onshore City Name Healdton
Onshore County Name Carter
Designated Location Milepost/valve Station
Federal No
Location Type Originated On Operator-Controlled Property, But Then Flowed Or Migrated Off The Property
Incident Area Type Aboveground
Incident Area Subtype Other
Incident Area Details Gathering Line Above Ground Piping
Crossing No
Pipe Facility Type Intrastate
Item Involved Pipe
Pipe Type Pipe Body
Pipe Diameter 6
Pipe Wall Thickness 0.28
Pipe Smys 24000
Pipe Specification Api 5l
Pipe Seam Type Lap Welded
Pipe Manufacturer Unknown
Pipe Coating Type Coal Tar
Installation Year 1950
Manufactured Year 1950
Material Involved Carbon Steel
Release Type Leak
Leak Type Pinhole
Wildlife Impact Ind No
Soil Contamination Yes
Long Term Assessment No
Remediation Ind Yes
Soil Remed Ind Yes
Water Contam Ind No
Could Be Hca Yes
Commodity Reached Hca Yes
Other Pop Ind Yes
Est Cost Oper Paid 0
Est Cost Gas Released 2000
Est Cost Prop Damage 20000
Est Cost Emergency 5000
Est Cost Environmental 15000
Est Cost Other 25000
Est Cost Other Details Metallurgical Analysis Costs
Prpty 67000
Accident Psig 50
Mop Psig 100
Accident Pressure Pressure Did Not Exceed Mop
Pressure Restriction Ind No
Length Segment Isolated 8000
Internal Inspection Ind No
Diameter Change Ind Yes
Other Restrictions Ind Yes
Operation Complications Ind Yes
Low Flow Ind Yes
Pipeline Function =< 20% Smys Regulated Gathering
Scada In Place Ind No
Cpm In Place Ind No
Investigation Status No, the facility was not monitored by a controller(s) at the time of the accident
Employee Drug Test Ind No
Contractor Drug Test Ind No
Cause Corrosion Failure
Cause Details External Corrosion
Internal External External Corrosion
Visual Exam Results General Corrosion
Atmosphere Corrosion Ind Yes
Microbiological Corrosion Ind Yes
Metallurgical Basis Ind Yes
Underground Location No
Externally Coated Yes
Prior Damage Yes
Collected Data Ind No
Has Hydrtst Conduc Before Ind Yes
Hydrtst Most Rcnt Year 2012
Hydrtst Most Rcnt Pressure 120
Direct Asmnt Conducted No
Non Destructive Exam Ind No
Preparer Name S**** D****
Preparer Title Senior Pipeline Compliance Engineer
Preparer Email S******@e****.com
Preparer Telephone 713.381.6487
Prepared Date 2014-07-02 00:00:00
Authorizer Name S**** D****
Authorizer Telephone 713-381-6487
Authorizer Title Senior Pipeline Compliance Engineer
Authorizer Email S******@e****.com
Narrative Third party notified enterprise local operations of a leak on the c150 regulated gathering line. Approximately 20 bbls of crude oil was released on to the ground with 2 bbls entering a dry creek bed with no water impact discovered. A temporary clamp was placed on the line for overnight. The line was replaced the next day and put back into service. The replaced line was sent for metallurgical analysis. Remediation and repairs were completed. Metallurgical report confirmed that external corrosion and microbiological- assisted corrosion contributed to wall loss and eventually a leak in the pipe. The line is being purged and capped and placed in an idled operating status. Future intent is to abandon the line.