Incident details
Operator, cause, commodity and consequences with raw source fields.
HL incident on 2013-10-31 — OK
Operator
Magellan Pipeline Company, Lp
Cause
Incorrect Operation
Commodity
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$62,000
Incident datetime
2013-10-31 13:23
Report number
Location
OK
Narrative
The line was being cleaned by sand-blasting as part of a rehab following an in-line-inspection when a leak developed. Operations control was notified and promptly shut down the line. The line was initially repaired by the installation of a full encirclement sleeve and subsequently repaired by removing the segment with the leak feature and replaced with new new pre-tested pipe. The specimen with the feature was sent to a laboratory for metalourgical analysis, which confirmed that the release was the result of sandblasting material penetrating through the remaining wall of an existing corrosion pit. Approximately 5.50 cubic yards of soil was remediated in accordance with company and state standards.
Detailed record list
Report Received Date
2013-11-26 00:00:00
Iyear
2013
Report Number
20130381
Supplemental Number
19323
Report Type
Supplemental Final
Operator Id
22610
Name
Magellan Pipeline Company, Lp
Operator Street Address
100 West 5th Street
Operator City Name
Tulsa
Operator State Abbreviation
OK
Operator Postal Code
74103
Local Datetime
2013-10-31 13:23:00
Location Latitude
41.61566
Location Longitude
-93.12757
Commodity Released Type
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Commodity Subtype
Other Hvl
Commodity Details
Propane
Unintentional Release Bbls
21
Intentional Release Bbls
22.05
Recovered Bbls
0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Other
Accident Details
Contractor Working For Operator On Pipeline Rehab Project
Incident Identified Datetime
2013-10-31 13:23:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
Yes
Shutdown Datetime
2013-10-31 13:26:00
Restart Datetime
2013-11-04 16:10:00
On Site Datetime
2013-10-31 13:23:00
Nrc Rpt Datetime
2013-10-31 14:42:00
Nrc Rpt Num
1064550
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Manual
Downstream Valve Type Ind
Manual
Num Pub Evacuated
0
Pipe Fac Name
Des Moines To Mississippi River #5-8" Line
Segment Name
6150
Onshore State Abbreviation
Ia
Onshore Postal Code
50228
Onshore City Name
Prarie City
Onshore County Name
Jasper
Designated Location
Milepost/valve Station
Designated Name
23.57
Federal
No
Location Type
Pipeline Right-Of-Way
Incident Area Type
Underground
Incident Area Subtype
Under Soil
Depth Of Cover
32
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Pipe
Pipe Type
Pipe Body
Pipe Diameter
8.625
Pipe Wall Thickness
0.322
Pipe Smys
35000
Pipe Specification
Api Grade B
Pipe Seam Type
Seamless
Pipe Manufacturer
National Tube
Pipe Coating Type
Coal Tar
Installation Year
1931
Manufactured Year
1931
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Other
Leak Type Other
Plug During Sandblasting
Wildlife Impact Ind
No
Soil Contamination
Yes
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
2000
Est Cost Gas Released
1030
Est Cost Prop Damage
62000
Est Cost Emergency
8000
Est Cost Environmental
15000
Est Cost Other
0
Prpty
88030
Accident Psig
693
Mop Psig
1440
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
76954
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
Yes
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate)
Investigation Status Details
Rehabilitation based on an in-line inspection was being performed when the anomaly resulting in the release was created. It was subsequently determined that neither the control room nor the controller on duty caused or contributed to the release.
Employee Drug Test Ind
Yes
Contractor Drug Test Ind
Yes
Num Employees Tested
1
Num Employees Failed
0
Num Contractors Tested
1
Num Contractors Failed
0
Cause
Incorrect Operation
Cause Details
Other Incorrect Operation
Operation Type
Other Incorrect Operation
Operation Details
During Sandblasting Of The Line A Plug Of Scale Was Knocked Loose
Related Failure Follow Ind
Yes
Category Type
Other Maintenance
Operator Qualification Ind
Yes
Qualified Individuals
Yes, They Were Qualified For The Task(S)
Preparer Name
K****** L* L*******
Preparer Title
Sr. Compliance Coordinator
Preparer Email
K***********@m*********.com
Preparer Telephone
918-574-7315
Preparer Fax
918-574-7377
Prepared Date
2014-04-28 00:00:00
Authorizer Name
K****** L* L*******
Authorizer Telephone
918-574-7315
Authorizer Title
Sr. Compliance Coordinator
Authorizer Email
K***********@m*********.com
Narrative
The line was being cleaned by sand-blasting as part of a rehab following an in-line-inspection when a leak developed. Operations control was notified and promptly shut down the line. The line was initially repaired by the installation of a full encirclement sleeve and subsequently repaired by removing the segment with the leak feature and replaced with new new pre-tested pipe. The specimen with the feature was sent to a laboratory for metalourgical analysis, which confirmed that the release was the result of sandblasting material penetrating through the remaining wall of an existing corrosion pit. Approximately 5.50 cubic yards of soil was remediated in accordance with company and state standards.
| Report Received Date | 2013-11-26 00:00:00 |
|---|---|
| Iyear | 2013 |
| Report Number | 20130381 |
| Supplemental Number | 19323 |
| Report Type | Supplemental Final |
| Operator Id | 22610 PHMSA Enforcement |
| Name | Magellan Pipeline Company, Lp |
| Operator Street Address | 100 West 5th Street |
| Operator City Name | Tulsa |
| Operator State Abbreviation | OK |
| Operator Postal Code | 74103 |
| Local Datetime | 2013-10-31 13:23:00 |
| Location Latitude | 41.61566 Google Maps OpenStreetMap |
| Location Longitude | -93.12757 Google Maps OpenStreetMap |
| Commodity Released Type | Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions |
| Commodity Subtype | Other Hvl |
| Commodity Details | Propane |
| Unintentional Release Bbls | 21 |
| Intentional Release Bbls | 22.05 |
| Recovered Bbls | 0 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Other |
| Accident Details | Contractor Working For Operator On Pipeline Rehab Project |
| Incident Identified Datetime | 2013-10-31 13:23:00 |
| System Part Involved | Onshore Pipeline, Including Valve Sites |
| On Off Shore | Onshore |
| Shutdown Due Accident Ind | Yes |
| Shutdown Datetime | 2013-10-31 13:26:00 |
| Restart Datetime | 2013-11-04 16:10:00 |
| On Site Datetime | 2013-10-31 13:23:00 |
| Nrc Rpt Datetime | 2013-10-31 14:42:00 |
| Nrc Rpt Num | 1064550 NRC Report How to search |
| Ignite Ind | No |
| Explode Ind | No |
| Upstream Valve Type Ind | Manual |
| Downstream Valve Type Ind | Manual |
| Num Pub Evacuated | 0 |
| Pipe Fac Name | Des Moines To Mississippi River #5-8" Line |
| Segment Name | 6150 |
| Onshore State Abbreviation | Ia |
| Onshore Postal Code | 50228 |
| Onshore City Name | Prarie City |
| Onshore County Name | Jasper |
| Designated Location | Milepost/valve Station |
| Designated Name | 23.57 |
| Federal | No |
| Location Type | Pipeline Right-Of-Way |
| Incident Area Type | Underground |
| Incident Area Subtype | Under Soil |
| Depth Of Cover | 32 |
| Crossing | No |
| Pipe Facility Type | Interstate |
| Item Involved | Pipe |
| Pipe Type | Pipe Body |
| Pipe Diameter | 8.625 |
| Pipe Wall Thickness | 0.322 |
| Pipe Smys | 35000 |
| Pipe Specification | Api Grade B |
| Pipe Seam Type | Seamless |
| Pipe Manufacturer | National Tube |
| Pipe Coating Type | Coal Tar |
| Installation Year | 1931 |
| Manufactured Year | 1931 |
| Material Involved | Carbon Steel |
| Release Type | Leak |
| Leak Type | Other |
| Leak Type Other | Plug During Sandblasting |
| Wildlife Impact Ind | No |
| Soil Contamination | Yes |
| Long Term Assessment | No |
| Remediation Ind | No |
| Water Contam Ind | No |
| Could Be Hca | No |
| Commodity Reached Hca | No |
| Est Cost Oper Paid | 2000 |
| Est Cost Gas Released | 1030 |
| Est Cost Prop Damage | 62000 |
| Est Cost Emergency | 8000 |
| Est Cost Environmental | 15000 |
| Est Cost Other | 0 |
| Prpty | 88030 |
| Accident Psig | 693 |
| Mop Psig | 1440 |
| Accident Pressure | Pressure Did Not Exceed Mop |
| Pressure Restriction Ind | No |
| Length Segment Isolated | 76954 |
| Internal Inspection Ind | Yes |
| Operation Complications Ind | No |
| Pipeline Function | > 20% Smys Regulated Transmission |
| Scada In Place Ind | Yes |
| Scada Operating Ind | Yes |
| Scada Functional Ind | Yes |
| Scada Detection Ind | No |
| Scada Conf Ind | No |
| Cpm In Place Ind | Yes |
| Cpm Operating Ind | Yes |
| Cpm Functional Ind | Yes |
| Cpm Detection Ind | No |
| Cpm Conf Ind | No |
| Investigation Status | No, the operator did not find that an investigation of the controller(s) actions or control room issues was necessary due to: (provide an explanation for why the operator did not investigate) |
| Investigation Status Details | Rehabilitation based on an in-line inspection was being performed when the anomaly resulting in the release was created. It was subsequently determined that neither the control room nor the controller on duty caused or contributed to the release. |
| Employee Drug Test Ind | Yes |
| Contractor Drug Test Ind | Yes |
| Num Employees Tested | 1 |
| Num Employees Failed | 0 |
| Num Contractors Tested | 1 |
| Num Contractors Failed | 0 |
| Cause | Incorrect Operation |
| Cause Details | Other Incorrect Operation |
| Operation Type | Other Incorrect Operation |
| Operation Details | During Sandblasting Of The Line A Plug Of Scale Was Knocked Loose |
| Related Failure Follow Ind | Yes |
| Category Type | Other Maintenance |
| Operator Qualification Ind | Yes |
| Qualified Individuals | Yes, They Were Qualified For The Task(S) |
| Preparer Name | K****** L* L******* |
| Preparer Title | Sr. Compliance Coordinator |
| Preparer Email | K***********@m*********.com |
| Preparer Telephone | 918-574-7315 |
| Preparer Fax | 918-574-7377 |
| Prepared Date | 2014-04-28 00:00:00 |
| Authorizer Name | K****** L* L******* |
| Authorizer Telephone | 918-574-7315 |
| Authorizer Title | Sr. Compliance Coordinator |
| Authorizer Email | K***********@m*********.com |
| Narrative | The line was being cleaned by sand-blasting as part of a rehab following an in-line-inspection when a leak developed. Operations control was notified and promptly shut down the line. The line was initially repaired by the installation of a full encirclement sleeve and subsequently repaired by removing the segment with the leak feature and replaced with new new pre-tested pipe. The specimen with the feature was sent to a laboratory for metalourgical analysis, which confirmed that the release was the result of sandblasting material penetrating through the remaining wall of an existing corrosion pit. Approximately 5.50 cubic yards of soil was remediated in accordance with company and state standards. |