HL incident on 2013-09-17 — TX
Operator
Enterprise Products Operating Llc
Cause
Equipment Failure
Commodity
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Program
HL
Damage and Injuries
0 fatalities
0 injuries
Property damage (nominal)
$194,000
Incident datetime
2013-09-17 02:06
Report number
Location
TX
Narrative
On 9/17/2013, a third party operator notified enterprise pipeline control of an ice ball on the 10" south leg loop line valve. An enterprise technician was dispatched and confirmed a pin hole leak on the valve body. The pipeline was not running at the time. Two valves were closed to block the leaking segment and flares were set up to displace the line. Once displaced, the leaking valve was cut out and replaced with another valve. The line was returned to service on 9/26/2013 upon completion of the repairs. Metallurgical analysis identified the failure was caused by a poor quality weld repair. Weld defects that were observed include a small section of unmelted filler rod or wire that was inadvertently left in the weld, porosity, lack of fusion, mechanical notches, and severe gouging of the base metal. These conditions constituted latent defects that eventually resulted in crack propagation to failure and loss of containment. Note: the name plate on the valve identifies it was rebuilt in 1/17/1992 and the repair procedures and inspection records are not available.
Detailed record list
Report Received Date
2013-10-15 00:00:00
Iyear
2013
Report Number
20130338
Supplemental Number
21876
Report Type
Supplemental Final
Operator Id
31618
Name
Enterprise Products Operating Llc
Operator Street Address
1100 Louisiana Street
Operator City Name
Houston
Operator State Abbreviation
TX
Operator Postal Code
77002
Local Datetime
2013-09-17 02:06:00
Location Latitude
36.086068
Location Longitude
-101.046424
Commodity Released Type
Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions
Commodity Subtype
Other Hvl
Commodity Details
Ethane/propane Mix
Unintentional Release Bbls
4
Intentional Release Bbls
2200
Recovered Bbls
0
Fatality Ind
No
Fatal
0
Injury Ind
No
Injure
0
Accident Identifier
Other
Accident Details
Third Party Pipeline Technician Working In The Area
Incident Identified Datetime
2013-09-17 02:06:00
System Part Involved
Onshore Pipeline, Including Valve Sites
On Off Shore
Onshore
Shutdown Due Accident Ind
No
Shutdown Explain
The Pipeline Was Not Running At The Time.
On Site Datetime
2013-09-17 02:06:00
Nrc Rpt Datetime
2013-09-17 03:01:00
Nrc Rpt Num
1060390
Ignite Ind
No
Explode Ind
No
Upstream Valve Type Ind
Manual
Downstream Valve Type Ind
Manual
Num Pub Evacuated
0
Pipe Fac Name
South Leg Loop
Segment Name
Lid 220
Onshore State Abbreviation
Tx
Onshore Postal Code
79081
Onshore City Name
Waka
Onshore County Name
Ochiltree
Designated Location
Milepost/valve Station
Designated Name
Spearman
Federal
No
Location Type
Totally Contained On Operator-Controlled Property
Incident Area Type
Aboveground
Incident Area Subtype
Typical Aboveground Facility Piping Or Appurtenance
Crossing
No
Pipe Facility Type
Interstate
Item Involved
Valve
Valve Type
Mainline
Valve Mainline Type
Gate
Valve Manufacturer
Grove
Installation Year
1971
Manufactured Year
1971
Material Involved
Carbon Steel
Release Type
Leak
Leak Type
Pinhole
Wildlife Impact Ind
No
Soil Contamination
No
Long Term Assessment
No
Remediation Ind
No
Water Contam Ind
No
Could Be Hca
No
Commodity Reached Hca
No
Est Cost Oper Paid
0
Est Cost Gas Released
40
Est Cost Prop Damage
194000
Est Cost Emergency
15000
Est Cost Environmental
0
Est Cost Other
7000
Est Cost Other Details
Lab Analysis Of Valve
Prpty
216040
Accident Psig
862
Mop Psig
1275
Accident Pressure
Pressure Did Not Exceed Mop
Pressure Restriction Ind
No
Length Segment Isolated
31680
Internal Inspection Ind
Yes
Operation Complications Ind
No
Pipeline Function
> 20% Smys Regulated Transmission
Scada In Place Ind
Yes
Scada Operating Ind
Yes
Scada Functional Ind
Yes
Scada Detection Ind
No
Scada Conf Ind
No
Cpm In Place Ind
Yes
Cpm Operating Ind
Yes
Cpm Functional Ind
Yes
Cpm Detection Ind
No
Cpm Conf Ind
No
Investigation Status
Yes, specify investigation result(s): (select all that apply)
Invest Schedule Ind
Yes
Invest No Control Room Ind
Yes
Invest No Controller Ind
Yes
Employee Drug Test Ind
No
Contractor Drug Test Ind
No
Cause
Equipment Failure
Cause Details
Failure Of Equipment Body (Except Pump), Tank Plate, Or Other Material
Eq Failure Type
Failure Of Equipment Body (Except Pump), Tank Plate, Or Other Material
Eq Additional Other Ind
Yes
Eq Additional Other Details
The Failure Was Caused By A Poor Quality Weld Repair.
Preparer Name
R** L**
Preparer Title
Pipeline Compliance Engineer
Preparer Email
R***@e****.com
Preparer Telephone
7133816741
Prepared Date
2016-11-21 00:00:00
Authorizer Name
R** L**
Authorizer Telephone
7133816741
Authorizer Title
Pipeline Compliance Engineer
Authorizer Email
R***@e****.com
Narrative
On 9/17/2013, a third party operator notified enterprise pipeline control of an ice ball on the 10" south leg loop line valve. An enterprise technician was dispatched and confirmed a pin hole leak on the valve body. The pipeline was not running at the time. Two valves were closed to block the leaking segment and flares were set up to displace the line. Once displaced, the leaking valve was cut out and replaced with another valve. The line was returned to service on 9/26/2013 upon completion of the repairs. Metallurgical analysis identified the failure was caused by a poor quality weld repair. Weld defects that were observed include a small section of unmelted filler rod or wire that was inadvertently left in the weld, porosity, lack of fusion, mechanical notches, and severe gouging of the base metal. These conditions constituted latent defects that eventually resulted in crack propagation to failure and loss of containment. Note: the name plate on the valve identifies it was rebuilt in 1/17/1992 and the repair procedures and inspection records are not available.
| Report Received Date | 2013-10-15 00:00:00 |
|---|---|
| Iyear | 2013 |
| Report Number | 20130338 |
| Supplemental Number | 21876 |
| Report Type | Supplemental Final |
| Operator Id | 31618 PHMSA Enforcement |
| Name | Enterprise Products Operating Llc |
| Operator Street Address | 1100 Louisiana Street |
| Operator City Name | Houston |
| Operator State Abbreviation | TX |
| Operator Postal Code | 77002 |
| Local Datetime | 2013-09-17 02:06:00 |
| Location Latitude | 36.086068 Google Maps OpenStreetMap |
| Location Longitude | -101.046424 Google Maps OpenStreetMap |
| Commodity Released Type | Hvl Or Other Flammable Or Toxic Fluid Which Is A Gas At Ambient Conditions |
| Commodity Subtype | Other Hvl |
| Commodity Details | Ethane/propane Mix |
| Unintentional Release Bbls | 4 |
| Intentional Release Bbls | 2200 |
| Recovered Bbls | 0 |
| Fatality Ind | No |
| Fatal | 0 |
| Injury Ind | No |
| Injure | 0 |
| Accident Identifier | Other |
| Accident Details | Third Party Pipeline Technician Working In The Area |
| Incident Identified Datetime | 2013-09-17 02:06:00 |
| System Part Involved | Onshore Pipeline, Including Valve Sites |
| On Off Shore | Onshore |
| Shutdown Due Accident Ind | No |
| Shutdown Explain | The Pipeline Was Not Running At The Time. |
| On Site Datetime | 2013-09-17 02:06:00 |
| Nrc Rpt Datetime | 2013-09-17 03:01:00 |
| Nrc Rpt Num | 1060390 NRC Report How to search |
| Ignite Ind | No |
| Explode Ind | No |
| Upstream Valve Type Ind | Manual |
| Downstream Valve Type Ind | Manual |
| Num Pub Evacuated | 0 |
| Pipe Fac Name | South Leg Loop |
| Segment Name | Lid 220 |
| Onshore State Abbreviation | Tx |
| Onshore Postal Code | 79081 |
| Onshore City Name | Waka |
| Onshore County Name | Ochiltree |
| Designated Location | Milepost/valve Station |
| Designated Name | Spearman |
| Federal | No |
| Location Type | Totally Contained On Operator-Controlled Property |
| Incident Area Type | Aboveground |
| Incident Area Subtype | Typical Aboveground Facility Piping Or Appurtenance |
| Crossing | No |
| Pipe Facility Type | Interstate |
| Item Involved | Valve |
| Valve Type | Mainline |
| Valve Mainline Type | Gate |
| Valve Manufacturer | Grove |
| Installation Year | 1971 |
| Manufactured Year | 1971 |
| Material Involved | Carbon Steel |
| Release Type | Leak |
| Leak Type | Pinhole |
| Wildlife Impact Ind | No |
| Soil Contamination | No |
| Long Term Assessment | No |
| Remediation Ind | No |
| Water Contam Ind | No |
| Could Be Hca | No |
| Commodity Reached Hca | No |
| Est Cost Oper Paid | 0 |
| Est Cost Gas Released | 40 |
| Est Cost Prop Damage | 194000 |
| Est Cost Emergency | 15000 |
| Est Cost Environmental | 0 |
| Est Cost Other | 7000 |
| Est Cost Other Details | Lab Analysis Of Valve |
| Prpty | 216040 |
| Accident Psig | 862 |
| Mop Psig | 1275 |
| Accident Pressure | Pressure Did Not Exceed Mop |
| Pressure Restriction Ind | No |
| Length Segment Isolated | 31680 |
| Internal Inspection Ind | Yes |
| Operation Complications Ind | No |
| Pipeline Function | > 20% Smys Regulated Transmission |
| Scada In Place Ind | Yes |
| Scada Operating Ind | Yes |
| Scada Functional Ind | Yes |
| Scada Detection Ind | No |
| Scada Conf Ind | No |
| Cpm In Place Ind | Yes |
| Cpm Operating Ind | Yes |
| Cpm Functional Ind | Yes |
| Cpm Detection Ind | No |
| Cpm Conf Ind | No |
| Investigation Status | Yes, specify investigation result(s): (select all that apply) |
| Invest Schedule Ind | Yes |
| Invest No Control Room Ind | Yes |
| Invest No Controller Ind | Yes |
| Employee Drug Test Ind | No |
| Contractor Drug Test Ind | No |
| Cause | Equipment Failure |
| Cause Details | Failure Of Equipment Body (Except Pump), Tank Plate, Or Other Material |
| Eq Failure Type | Failure Of Equipment Body (Except Pump), Tank Plate, Or Other Material |
| Eq Additional Other Ind | Yes |
| Eq Additional Other Details | The Failure Was Caused By A Poor Quality Weld Repair. |
| Preparer Name | R** L** |
| Preparer Title | Pipeline Compliance Engineer |
| Preparer Email | R***@e****.com |
| Preparer Telephone | 7133816741 |
| Prepared Date | 2016-11-21 00:00:00 |
| Authorizer Name | R** L** |
| Authorizer Telephone | 7133816741 |
| Authorizer Title | Pipeline Compliance Engineer |
| Authorizer Email | R***@e****.com |
| Narrative | On 9/17/2013, a third party operator notified enterprise pipeline control of an ice ball on the 10" south leg loop line valve. An enterprise technician was dispatched and confirmed a pin hole leak on the valve body. The pipeline was not running at the time. Two valves were closed to block the leaking segment and flares were set up to displace the line. Once displaced, the leaking valve was cut out and replaced with another valve. The line was returned to service on 9/26/2013 upon completion of the repairs. Metallurgical analysis identified the failure was caused by a poor quality weld repair. Weld defects that were observed include a small section of unmelted filler rod or wire that was inadvertently left in the weld, porosity, lack of fusion, mechanical notches, and severe gouging of the base metal. These conditions constituted latent defects that eventually resulted in crack propagation to failure and loss of containment. Note: the name plate on the valve identifies it was rebuilt in 1/17/1992 and the repair procedures and inspection records are not available. |
External Resources
PHMSA pipeline safety insights.
Product
Features
Company
All rights reserved. Copyright © by ClearPHMSA